Same WareHouse  Assigned to different plants under different company codes

Hi Guys,
             I assigned a warehouse to two different storage location under two plants under two different company codes. I did do the movement in one plant and i could do TR and TO
but when i post a material movement in other one. I cant c the TR created for the next one.
Any idea y?
thanks a bunch

Yes i did extend the material master for both the plants and extended to the warehouse too...
pls help
thanks a bunch for the reply

Similar Messages

  • All plants Under specific company code

    Hi,
    What is the Tcode for All plants under Specific company Code.
    I Know about EC01 Navigation..
    But is there any other tcode available or not?
    Is there any table for all plants under company code?

    Go to SE11.. Give table name T001K..Execute... Give the company code in the field BURKS.. the result will give u all the plants under it....(WERKS is the field name for Plant)..
    Karthick

  • Creation of same personnel number for different company codes

    Hi All,
    I am having the requirement to cerate same personnel number under different compant codes.
    Eg. There are 2 company codes MO10 and MO20 for the same country
    Personnel number- 0100000023 should exist for both company code MO10 and MO20.
    Please help.
    regards,
    Gaurav

    Dear Roger,
    Thanks for replying, I have been waiting for this. We are a group  of copmanies with the name of orient and have  four different  companies and currently  using one payroll area Z1 for payroll processing for  OEL; company code 1000. we have these company codes 2000, 3000 and 4000 for rest three companies and want to use same payroll area Z1 for processing payroll of these three companies. is that possible to do in SAP HCM if yes then how?
    Can you please guide on this? Look forward for your response.
    Stay Blessed,
    Waqar

  • Transfer Posting between plant to plant under 2 company codes

    Hello all,
    I have 2 company codes 9002 and 2850.
    Under 9002 there is a plant 9002 with storage location WHSE.
    Under 2850 there is a plant 3105 with storage location WHSE.
    Whenever I am moving a material from plant 3105 to 9002, I am getting the following error in the system:
    No accts maintained for company code clearing between comp.cds 9002 and 2850.
    The system clearly requires a configuration to solve this error. But my doubt is, is there any other way by which I can solve this error without making any new configuration??? My client does not need any configuration but wants this error to be resolved. Is there any way???
    Kindly advise.
    Thanks and Regards,
    Umakanth.

    This is absolutely a SAP standard error which can be easily solved by FI guys.
    Though I dont remember the transaction code now but it becomes necessary to maintain clearing accounts between two company codes for accounting consistency.
    Please convince your client and get it done from FI guys. You will have to show your consulting skills here.

  • STO - PLANT TO PLANT UNDER DIFFERNT COMPANY CODES

    GREETINGS!
    I AM GETTING PROBLEM AT *PO LEVEL*( THEY ARE NOT BLOKING THE PO) LIKE:
    1 ) MATERIAL IS INTERNALLY PROCURED
    2) THIS SHIPPING POINT IS RELEVENT FOR SHIPPING COND AND LOADING GROUP AND PLANT, HTOUGH I MAINTAINED THEM PROPERLY IN XD02, MM02, VOV8
    AT VL02N LEVEL LIKE:
    THERE IS PROBLEM IN MOVEMENT TYPE 645-XX--
    WILL U PLEASE GUIDE ME TO KNOW THE WHY THE PROBLEM IS OCURING AND SOLVE THE PROBLEM

    Hi,
    You need an intercompany flow. Check the notes
    Note 543821 - FAQ: cross-company processing
    Note 308989 - Consultant note for cross-company transactions
    and related
    I hope this help you
    Regards,
    Eduardo

  • Same warehouse for different company codes

    Hello Guru's
                     is there a possibility in WM , considering decentralized WMS to create a warehouse which can be managed by two different company codes.
    thanks a lot for ur suggestions

    yeah i do understand that warehouse is connected to plant and we can also have one warehouse to two plants and manage the inventory but in my company case, we manage the inventory of two different company codes in one warehouse by their legacy systems, so i was wondering how to map that in SAP.
    In the centralized warehouse as far as i know i dont think we can assign the warehouse to 2 different company codes but i was wondering can we do that in decentralized warehouse.
    thanks for the reply

  • EXTERNAL OPERATION in a production order with  different company code plant

    Hi,
    in my case i am having a production order with  4 operations.
      0010 milling
      0020 winding
      0030 cutting
      0040 milling
    among this opearion 0030 i want to do it in a plant which is assigned to different company code than mine.
    in this case whether i should proceed with PP01 Control key  with opearion plant as that plant which is lieing in diffent company code or
    i should specify  PP02 control key saying that plant as an external vendor for me and do PR  and PO for that service .
    which should i follow for my case and how cost gets updated .

    Hi,
          For different company code, u have to specify PP02 in the routing for external vendor. In PP02 control key indicator must be set in external opn.
    Before that create purchase info record.
    Enter subcontract info record in routing.
    after running MRP , convert the PR to PO.
    Send the material by MB1B by 541 mvt
    Receive the material by MIGO  by 101 mvt.
    Regards,
    Raja sd

  • Plant to plant subcontracting(Under one company code)

    Hi,
    I need a help on one issue.
    We are having multiple plants under one company code.
    Material goes with 57F4 challan for subcontracting plant to plant.
    How to do the subcontracting process for plant to plant.
    Please explain step by step.
    I know the normal process (with vendor)
    Also, if I have create a subcontracting PO, how the receiving plant will come to know about this?
    How will he receive the material which I have send?
    How the production activities at their end?
    Do I need to do the MIRO?
    Please thrwo some light.
    Thanks in advance,
    Piyush

    1)  Create Subcontracting Purchase Order with `0` Cost
    2) Transfer of Components to Subcontractor
    3) Create Subcontracting Challan
       a)Receive the Components as non valuated Materials
       b)Process the Materials to get the SF Product
       c)Create the Outbound Delivery without Ref. To Sales Order
       d)Endorse the Subcontract Challan Manually
    4) Post Goods Receipt
    5) Reconcile Subcontracting Challan
    6) Complete / Reversal / Re-credit SubcontractingChallan
    During Reconcile the Subcontract Challan - J1IFQ,Enter Manually into the Assigned Quantity Field the Components that are actually assigned for this Subcontracting Process.
    Regards,
    eswarmanu...

  • Reassign Plants from one company code to another company code

    Hi Gurus,
    We need to move plants from the current company code to a new company code. I know this is possible in configurartion, however, I not sure on what implications this may cause to the new company code. We are looking for a way to not creating new plants under the company code, and we believe reassign plants to the new company is the best way.
    Could you please let me know what might be the impact on this? on Finance? etc...
    Thanks in advance,
    Richard

    To me, it is something alarming!!!
    You are trying to assign the plants to new company codes after removing the assignment from the other company code. In my opinion you need to first consult a MM and a FI specialist and not a SD specialist.
    In the old assignment, there might be transactions done (for example goods movement, different material documents etc..). If you assign the plant to new company code, then how will you retrieve the old historical documents? I don't think even if you archive the documents,  you could retrieve after assigning the plant to new company code.
    I would suggest, think twice before you do anything/do enough testing in development system, or consult with MM/FI personnel or consult SAP before reassigning the plant.
    Regards,

  • Plant convert to Company code

    Dear Friends,
    We have 4 plants under one Company code.
    Work is going smoothly.
    From FI point of view they want seperate transaction ,payment,profit & loss records with different Number ranges.
    For this they want 4 company codes for 4 plants.i.e.total seperation.
    Now tell if all is going ok since 1.5years then it is fisible to do that?any risk?
    If yes it can be done then please reply.
    Regards,
    Chandra.

    Hi
    Pls forget sap and think in general , is it possible to make the plants to each company code.
    with ur full fuctional knowledge.
    if you feel, you can. then in sap also we can do it .ok

  • What is the configuration step assigen 2 plant to one company code

    hi all,
    i want assigen one code to 2 plants, what is configuration  step
    what is the special roll in chart of a/c, document number range,
    thanks in advance
    milind

    hi
    Milind Patil         
    You can assign no of plants to one company code .you can follow below navigation path
    --Enterprise Structure
    --Assignment
    --Logistics - General
    --Assign plant to company code
    Doubble click on assign plant to company code
    Enter following entries
    CO-CODE     -     PLANT
    1000             -     1000
    1000             -     1100
    AND SO ON----
    there is no extra settings in chart of accouts and document number ranges for assign morethan on plant to co code
    REGARDS
    TRINADHNAIDU.A

  • Is it possible to assign different company code employees(country grouping also different) under same Organizational Unit?

    Hi SAP Experts,
    In OM side, Org Unit is linked to company code "GB**" cost center, when we tried to assign new cost center(company code is GB**), system throws error "Company Code changes involves Invalid change of country". I know when we try to assign cost center, belongs to another country company code, this error comes. I checked and found that employees under OU belong to 2 different countries.Few of the employees belong to GB** company code while other employees belong to FI** company code.
    Is it possible to assign different company code employees(different country code) to the same OU? if yes, how can we do that?
    Please reply soon
    BR,
    RG

    Hi RG
    "Is it possible to assign different company code employees(different country code) to the same OU? if yes, how can we do that?"
    Yes it is possible to assign by creating sub org unit and then assigning cost center based on the company code (and country code)
    When the child org unit is created under the Parent org unit - maintain the Account assignment details - cost center details based on the company code of other countries i.e Finland and any positions created it will be under Finland and that way you can choose different countries.
    Example :
    Root Org unit : XYZ / OU
    Sub Org units : GB  / Finland / Italy / NL   etc with respective cost centers
    Sub Org units or positions: GB_HR / GB_Sales etc which will default the cost center from the GB org unit.
    In our current clients we have more than 5 + countries under the Root Org unit and then sub org units as each country which are further divided and have respective cost centers assigned.
    best wishes
    V

  • Urgent: Maintain std cost for plants under different company codes

    Hi all,
    Company code(s)/Plant(s): C1/P1, C2/P2, ..., CnPn
    BOMs and Routings are maintained under P1. I believe that unlike BOM routing can't be made available across plants. So how does one maintain std cost across plants under different company codes?
    Thanks.

    Hi,
    You have to maintain individual BOM, Routing and varaint for all plants.
    Best Regards
    Ashish Jain

  • Project stock exist in a plant and WBS but with different company code

    Hello,
    As I know I can not create a PO in company A, but was assigned to a WBS maintained in company code B. The system will check if the WBS getting the same company code with the PO, and pop up  the error message if the company code was differect.
    But seems the project stock could exists in a plant  but assign to  WBS was maintained with different company code. For example, A material stock was in plant A assigned to company code A, and it is also assigned to WBS belong to company code B.
    Any one know it is correct?
    Thanks!

    I knew crossing company code to assign WBS element to PO is not allowed since i got the error message, and I think it's reasonable, cause the expense from the project PO should post to the same company code through the WBS element.
    But why for  the inventory crossing company code is allowed?  The stock in plant A belong to company code A, was assigned to WBS element B belong to company code B. That means the inventory is in the GL balance of company A but under the profit center belong to company B.  How to understand it? I think it's wrong

  • Billing in Stock Transfer between two plants of two different company codes

    Hi Friends,
    I am doing the scenario of stock transfer between two plants of different  company codes.
    I have some issues in Billing for this..
    What are the settings do i need to to for Pricing in SD point of view.
    Ex:
    Supplying         /         Receiving
    Com.Code:2000     /        CompanyCode:1000
    Plant:2100              /         Plant:1100
    SA:2000/10/00      /          SA:1000/10/00
    I created Customer 5555 w.r.t sales area of supplying company code (2000/10/00)
    I created Vendor  7777 and assigned Supplying Plant 2100 in add purchasing data.
    In IMG Settings:
    Define Shipping Data for Plants: In Receving Plant i assigned customer 5555 and sales area blank
                                                        In Supplying Plant i assigned customer blank and sales area as 2000/10/00
    Create Checking Rule: Standard(B SD Delivery)
    Define Checking Rule: Standard(Avallability-01assigned to checking rule B)
    Assign Delivery Type and Checking rule: Document type(NB)-Supplying Plant(2100)-Delivery Type(NLCC)-Checking Rule-(B)
    Assign Doc Type:Supplying Plant(2100)-Receving Plant(1100)-Doc type(NB)
    What are Pricing settings in SD i have to do?????????
    Process:
    ME21N->VL10B->VL02N(PGI)->VF01(IV)->MIGO->MIRO
    I have gone through many threads in Forum but confusion in Pricing Part..
    Some are mixing with the inter company sales proces..
    Pls guide me..
    With Regards

    Do the following steps for STO Customizing:-
    1. Create a customer master record for the issuing plant.
    2. Create a vendor master record for the issuing plant, and enter customer account number in the Customer field on the Control screen.
    3. Repeat steps 1 and 2 for the receiving plant.
    4. Assign the plants to the customer master record in Customizing for Materials Management (MM), by choosing Purchasing <Purchase Order < Set Up Stock Transport Order< Plants.
    The Process Flow would be as follows :-
    Create a stock transport order, following the standard procedure, and send the order to the issuing plant.
    Issuing plant has processes your order, and when it is ready to ship,the storeperson at the issuing plant issues the goods using a transfer posting. The excise clerk there creates an excise invoice.The excise supervisor verifies and posts the excise invoice.It then sends the goods to you, together with the excise invoice.
    Once the goods arrive, you follow the standard procedure for incoming excise invoices:
    The excise clerk captures the excise invoice, using the stock transport order as the reference document. The storeperson enters the goods receipt, again using the stock transport order as the reference document.Alternatively, you can first enter the goods receipt and then capture the excise invoice.
    The excise supervisor then posts the excise invoice.
    Best Regards,