I have a procedure to be scheduled everynight in the DB. How I can do it ?.. I need to check the output of this execution also ?
Db : 10.2.0.4
SOlaris 5.10
Kai

Assuming its a database stored procedure that you want to execute every night and since you are on 10g already, use DBMS_SCHEDULER.
http://download.oracle.com/docs/cd/B19306_01/appdev.102/b14258/d_sched.htm#CIHHBGGI
I need to check the output of this execution also ?Do you mean to check whether the procedure was executed successfully or there is some output expected from this procedure, which needs to be spooled?

Similar Messages

  • Customize Workflow: remove or change schedule activity

    Hi,
    does anyone here have experience with customizing a workflow in OM? We use the standard workflows of Oracle (e.g. Order Flow - Generic).
    Within these workflows is a scheduling activity which re-calculates and overwrites the Schedule Ship Date in our Order Lines. I want to get rid of that. I want to have this field only manually entered, but not changed by the workflow / scheduling activity.
    Anyone experience with such a thing? Can somebody share his ideas and experiences and give recommendations? Is this a good idea or not? Maybe some links to some guidelines on how to do this? I have already the white paper "Using Workflow in Oracle Order Management", but some information from experience people would be highly appreciated.
    Thanks a lot,
    David.

    Hello Sai and Sandeep,
    thanks a lot for your response.
    Yes my idea was to create a copy of the standard workflow and modify the copy. But I have not yet done such a thing with OM flows, so I was not sure if this is a recommended way at all. And also I need to find out if I can really prevent that the Schedule Ship Date gets updated automatically by some workflow.
    But your response made me more confident that this is not a really bad practice ;)
    Thanks a lot,
    David.

  • After activating a Resource Plan, scheduler activity is very high

    Hi folks,
    This is our first attempt at using the Resource Manager built into the 10.2.0.4 database.
    I've activated a Resource Plan that limits a Resource Group's CPU to 40%.
    Since activating the plan, I've noticed a very high amount of activity from my Grid Server application for the Scheduler. Is this normal behavior when using Resource Plans? When the Resource Plan is NOT active, the Grid Server Performance page shows almost no scheduler activity.
    I'm wondering if anyone else sees this behavior when using Resource Plans?

    In grid control you get to see wait events for class Scheduler. If you drill down you will see what actually causes this. The light green color only pops up when the Resource Manager is intervening with the application.
    I hope this helps,
    Ronald.
    http://ronr.blogspot.com

  • Error in APO GATP: Exception while scheduling activit & Internal error 0010

    Hello APO experts,
    I am working for a APO project where GATP is used. At the time of sales order creation user is getting ,
    The following errors / warnings are being returned by APO
    W VV                   800 APO: Exception when scheduling an activity
    E VV                   800 APO: Internal error: Item /000010
    Has anybody come across such issues. Waiting for your replies.
    Regards
    Ravindra

    Hi,
    This is a very generic error message but points to the scheduling. Goto your SCM system and check the settings for your scheduling. Do you use CPS - configurable process scheduling ? Then I assume an error in the scheduling schema.
    Please check your settings and maybe userexits and provide us some further details.
    regards,
    MIchael

  • KSPP -Scheduled Activity are not updated for last 2 periods

    Hi All,
    When we run KSPP by using LTP, noticed that for one cost center and activity type the plan scheduled Acivities are not updated for last 2 period's.(shows Zero)
    Do we miss any thing.
    Regards,
    Raj

    Hi,
    It can be due to the sales demand you have uploaded and the Lead time in the material master
    because of the that, the demand gets shifted before (say, Dec demand gets shifted for manufacturing in October) and the activity qty in the last month comes zero
    So, upload 14 months demand where 13 and 14th month is the same as 12th month... Most of the companies do this way
    Ajay M

  • Cost from a Pay App Schedule of Value to P6 Schedule Activity

    Is there anyone that has attempted to push the cost and scheduled value from a payment application from several contracts to ONE activity ID? The results I get are illogical and hit-and-miss.
    Ready to go back to manual input which is I don't believe was the intention when the Contract Management/P6 Cost connection was created.
    Rick
    Edited by: RickS on Jul 11, 2011 8:47 PM

    OK. Got it.
    For those interested:
    For each contract and unique payment application, there is a corresponding activity in P6 that serves as a budget bucket in the schedule under the expense tab with a one-to-one relationship. Each new Pay App will update the schedule 'Total Actual Expense' each time a new payment is collected and imported. Therefore, as the contract is spent, the actual expense in the P6 schedule reflects the same amount after an import form Contract Management to P6.
    With this, the 'Stored Period Performance' function can be used along with a new monthly Cost-to-complete to store monthly activity progress. Then using the tracking function, PV, EV, Actual and planned cost can be viewed on a Gannt chart.
    All said and done, there can be a responsibility given to an account person on the CM side and a forecasting/analysis responsibility on the P6 side.
    I welcome further discussion from interested parties. email: [email protected]
    Edited by: RickS on Jul 11, 2011 8:48 PM

  • CRM - Activity scheduling duplicated

    Hello!
    I've got a problem with the Schedule Activity transaction.
    At first I maintained Visit plans in the CRMM_TOUR transaction. It's working good.
    After that I starting Schedule Activity transaction (CRMM_ACT_SCHED), and after I choose the corresponding visit plan, I try to scheduling the activities. At first in the calendar the activities is seeing. But after I saving the activities are duplicating in the calendar, and also there will be come into being every activity twice.
    So please try to solve my problem!
    Thanks,
    Gábor Somogyvári

    Hi,
    The ideea behind this flag is if the system should check the available time in the calendar for the given business partner & the user which is running the application.
    Be aware that this flag is working in combination with the "Maintain Calendar" flag from the partner determination procedure.
    BR,
    Valentin

  • Schedule Line Delivery Date Calculation with Transportation Scheduling

    Hi All,
    We are currently running into a problem where our Sales Order Schedule Line delivery dates are being pushed out too far into the future - because of the Calendar being used to determine the transit time.
    We have 'Delivery Scheduling' and 'Transportation Scheduling' activated for our Sales Document type
    We have Routes that are configured with a 'Transit Time' and a 'Factory Calendar'
    Order Scenario:
    'Factory Calendar' assigned to our 'Route' is setup with only one 'Workday' in a given week e.g. Wednesday
    Our 'Route' has a Transit Time of 2 days
    We create a Sales Order on Monday for a Material that is available in our Plant
    The 'Goods Issue' date is being determined correctly for the next Workday - being Wednesday
    The 'Delivery Date' is extending out over 15 days (2 Wednesdays into the future) - since it is working on 'Calendar Days' and not 'Actual Days'
    Does anyone know of a way (config or other) to only influence the 'Goods Issue' date with the 'Factory Calendar' assigned to the Route, and have the 'Delivery Date' calculated using the Transit Time on the Route and 'Actual Days' rather than Calendar days?
    All help greatly appreciated.
    Thanks,
    Ravelle<i></i>

    Hi Pathik,
    Thanks for your reply.  I have already maintained the Calendars I'm using for this business process in <SCAL> - same as <OY05>. 
    The problem I'm having though is that by assigning a Calendar directly to my route (which I doing to influence the goods issue date - using a 1 Working Day Calendar) it is also taking precedence in determining the Transit time - which in this case I don't want, as I want my Transit time to be determined using a 5 Working Day Calendar.
    I don't think this problem has a config option as a work around...I think the only possibility in this case is a development to achieve the results we need.
    Thanks,
    Ravelle

  • Manual scheduling phases in Process order

    Hello dears,
    a question came out to my business during Process order (PP-PI module) testing.
    When a order is created, the system uses master recipe data to schedule each phase, and to assign them a start and finish time. These values are displaied in the process order for each phase.
    The question is: is it possible to change them manually, in case I need to reschedule only a specific phase and not the whole order? Because currently I see that dates fields are not editable in COR2.
    Thanks a lot.
    Kind regards,
    Giovanni

    Dear ,
    You ca not  able to manually chanes  the date and time unless they are Dispatched  after capacity evalution  or leveling at the Resource level.
    Generally , if your resource is having finite scheduling active and you have CRP planning is in place , then you need to goto CM07/CM05 to check the Overload/Availablit of the resouce in a certain date n time so that you can re-scheule them manually from CM21/CM22/CM23 .
    To meet this requirement , you have to adop Capacity Requirement Planning set up .
    Check our earlier posting  on the similar issue : Capacity Planning not considering plnd order
    Capacity requirements generation at phase level only
    Regards
    JH
    Edited by: Jiaul Haque on Dec 8, 2010 9:30 AM

  • Task scheduler in windows 2008 R2 cluster.

    We have clustered server and there's two nodes - Active(A1)/Active(A2).
    Ordinary client can connect A1, but A1 is failed then connect A2 by windows 2008 R2 cluster.
    We have a task scheduler exe module created by .net framework in each node.
    When A1 server is operated, we wanna just A1 job scheduler active.
    And A2 server is operated, just only A2 job scheduler acitve.
    Can We contoller  this situation in exe module or Failover Cluster Manager?
    parky

    If you upgrade to Win2012 or higher you can.  Here's a blog on it:
    http://blogs.msdn.com/b/clustering/archive/2012/05/31/10312527.aspx
    Thanks!
    Elden

  • Schedule an ICM Script

    Is it possible to schedule Activation of an ICM Script which does NOT have a direct DN/Call Type associated to it?
    I know we can do it for a Script versions which has a DN/CT associated to it, but how do I do it for a script which is referenced by a 'Go to Script' only.

    Thanks Joseph, but the issue is that we have 100s of production scripts and we do not that how many of those point to or reference to this 1 script (hence this post). And now we want a new version of this 1 script to go live (get activated) at midnight, and I did not want to do it manually at 12:00.
    Any ideas Please?
    Regards,
    Kartik

  • DB13 Calender Scheduling backup failed

    Hi Guru's/Experts,
    Our DBAcockpit backup planning is on every Wednesday... Yesterday it was failed and the status it is showing is 'Scheduling Failed'  I tried to Re-Scheduled it is giving the message "Action Successfully Completed". When I tried to check the jobs in sm37 named DBA:BACKUP it is not present in any case neither scheduled,active,released nor cancelled.
    After running the Rescheduled i check the SM21 status in that it is giving the warning Failed to maintain status entry for job DBA:BACKUP_DEV______@131106/400
    I have checked the SAP Note 1242278 - DB6: Status 'Scheduling failed' in planning calendar   but it is not compatible with my release version i have SAP_BASIS 702 with support package SAPKB70210 (level 10)
    Can we have updated version of this note so that i can implement this on my system to resolve this issue
    If you have any further quick suggestions it will be appreciated...
    Would be looking forward for your help..
    Thanks & Regards,
    Prasad Deshpande

    Hi Deepak,
    Thanks 4 the quick reply when i am clicking on DBA Planning Calender and after selecting the job when i clicked on Action Details it is showing only this as per screen below
    Is there any further option apart from this...
    Please Excuse me for the silly question as i am new in SAP Basis...
    Thanks & Regards,
    Prasad Deshpande

  • ESS Scheduler metadata information in SOA Composite

    Hi,
    I am working on SOA 12c and Scheduling a SOA Composite, in the process i need to track the ess scheduler request id within SOA Composite and log the composite details with ess scheduler request id.
    how this can be achieved
    Thanks & Regards,
    ANVV

    Hi Markus,
    Thanks for the link.
    i have scheduled the SOA Composite in the similar way, and get it working
    1) Developed the SOAComposite1
    2) configured the ESS Scheduler in the similar way shown in the link.
    3) Developed a bpel process <bpelprocess> scheduled ; drag & drop the scheduler activity and deployed it to schedule.
    4) Run the scheduler from <Scheduling Service> under em console
    5) in <SOAComposite1> ; i am trying to get the requestId of the scheduler which ran in step 4 and store the same in the custom database tables for tracking / logging purpose; with current SOAComposite ecid, requestId (which is required and the purpose of this thread), compositename, etc., using ESS API.
    Hope i made it clear
    Thanks & Regards,
    ANVV

  • Complex schedule requirement - every 2 hours at even hours

    Hi all,
    I have a schedule requirement, wherein I need a runbook to run every 2 hours starting at 6am till 12am Sun-Friday (i.e. 6am,8am,10am...)
    I looked at the monitor date/time task, however the challenge with that is that the runbook could end up running at 7am,9am,11am... etc. depending on when it started.
    Is there a way to accomplish the above without having to create 10 runbooks, 1 per start time, as that would eat up significantly into the policy throttle limit.
    Thank you.

    Hi,
    In Global Settings define a Schedule mit even hours. After "Monitor Date/Time" use "Check Schedule" Activity with the Schedule defined in Global Settings. In the link condition after "Check Schedule" filter only if "Conforms
    to Schedule equals true".
    Regards,
    Stefan
    www.sc-orchestrator.eu ,
    Blog sc-orchestrator.eu

  • SAP Error Msg No. KP236, Cost Ctr 112233, act type AABB: Activity Schd. Act

    Hi Experts,
    When I do KSPI - Plan price calculation.  I am getting the error message no KP236.  Cost center 112233, activity type AAABBB: Activity<scheduled Activity.  When I go to KP27 and see the detials for the cost center and for the activity type, I can see that there is some value present in the column Act. Scheduled which is greater than planned activity.  How to make this Act. Sched column to Zero.  I tried transaction KPSI, but this only copies the values from Act. Sched to planned activity.  But I want to make the Activity Scheduled column to be Zero. Can anyone give me some pointers as in where to look to solve the issue?
    Thanks

    Dear Sir,
       Please read note 597159, specially point 7
    "Planned activity < scheduled activity:
    The calculation occurs with the scheduled activity instead of the planned activity or capacity. In the list of results, the
    system issues error message KP236. The results are not updated, unless the "still post" indicator is set in the
    settings for the price determination. See the long text of message KP 236 for further information (the same applies for
    capacity instead of scheduled activity)."
    regards
    Waman

Maybe you are looking for

  • How to count number of CRCResults in list CRCResult ?

    I obtained the list<CRCResult> from GetContentSpace  operation. I need  to know ,how many files  are in the folder in ContentSpace (from wchich i've obtained list<CRCResult>). How should I figure it out? I tried  get-list-item-count  to count,for exa

  • Splitting and tiling in Illustrator

    i need to find a way to slice an image (jpeg) into 9 or 16 or more equal parts and then convert to PDF so  it can be printerd and that its ends up looking like a large poster.. that can be repasted together...also would be nice if each image spliced

  • No power to our time capsule

    Today, I was able to use wifi with my time capsule. Now, no light is on. I unplugged the power cord from the TM, plugged it in again, and got an amber light. Then, when listening to it, it sounded as though it shut off. I also tried other outlets on

  • Adobe forms date Validation

    In webdynpro application am using interactive forms . In that i have a Date field. i want the user to type only in the (DD-MMM-YYYY). it should not allow the other formats. if he enters any other format it should say an error message and should clear

  • 11g airport card music cuts out on AExpress "g" all on AExtreme 'N' network

    airport extreme n network with imac intel core duo (leopard) and imac g4 (tiger), both stream music to airport express. imac core duo streams well, but imac g4 with older 11g airport card cuts out every 20 seconds or so, and it's within 10' of expres