Secondary costs planning on network activity
Is possible to plan secondary costs on network activity (without activity type on work center)?
Thanx
Hello Keshav
I have in CO Area currency CHF
In Company Code I have EUR
Then object currency for network activity field AFVGD-OWAER is u201CEURu201D
For Material planning in networks Currency Key field TKA01-WAERS is u201CCHFu201D
Before reporting, I would like see the above currencies as equal using CJ20N.
Thanks
Salvo50
Edited by: Salvo50 on Nov 7, 2011 11:33 AM
Similar Messages
-
EASY COST PLANNING at Network Activity Level
Hi All
I am using EHP4 system. I want to do easy cost planning at NWA level for this I already activate ECP for NWA in configuration setting and other necessary settings but still when I create ECP from CJ20N or CJ9ECP I can not able to do ECP on NWA activity level. Please give your inputs on same.
RegardsHi Gokul
All basic settings for ECP have been maintain. It allow me for ECP on WBS level but it not show me any activity or Network in ECP as I activate Planning for Network Activities with Easy Cost Plan in configuration.
Regards -
Easy Cost Planning at Network Level
Hi All,
I was able to implement ECP at WBS level, but not able to implement at network level. I am using SAP ECC 6.0 EHP 4.
I have activated the business function ops_ps_ci_1 and also activated the 'Activate Planning for Network Activities with Easy Cost Planning' in the configuration settings in SPRO-IMG. I had gone through most of the threads on this topic like :
Network Activity Easy Cost planning
ECP at activity level not triggered
I am not able to find the option for 'Create Alternate CO Version' and 'Activate Multiple CO Version' under the Easy Cost Planning and Execution Services in SPRO-IMG.Please advise me in implementing Easy Cost Planning at Network Level and correct me if I was wrong in completing the configuration steps.Thanku All,
I have done all the steps as you mentioned
1. Activated the business function OPS_PS_CI_1.
3
2.
3.
Activated Multiple Plan Version using the tcode RCNPRECP
Still not able to view the options under SPRO-IMG Easy Cost Planning
* Create Alternate CO Version
* Activate Multiple CO Version
Also not able to implement ECP at network level. -
Is it Possible to do easy cost planning in network and acitivity level
Hi,
Is it possible to do easy cost planning in network and acitivity level
Rgds
Purna.MDear Sanjeev,
ECP not possible at Network or activities but it is not like that as you saying " any of cost planning not possible at activity level as per sap standard."
It is possible to do Network Cost Planning, for that you have to make the settings required for to determining the plan costs in networks.
In networks/activities the plan costs are:
Calculated automatically on the basis of the defined price and quantity structures
Planned using unit costings for general costs activities or material components
for this make the setting in config of PS node Project System -> Cost -> Planned Costs -> Automatic Costing in Networks/Activities.
Rgds
Rajesh -
Cost Planning on Network Activities
Hi,
Can any one help me to enter planned cost on network activities with out using capacity planning.
Thanks
MurtazaDear Murtaza,
Refer below sap help link for Cost planning in Network Activities.
http://help.sap.com/saphelp_46C/helpdata/EN/86/98853478616434e10000009b38f83b/frameset.htm
Click on above link follow the menu path
Cost Planning > Cost Planning in Networks > Network Planned Costs > Basis Values for Network Costings
Cost Planning > Cost Planning in Networks > Network Planned Costs > Unit Costing in Networks
Hope its useful.
Sandeep -
Cost Planning for networks in a CO plan version other than 0
Hi,
We have a specific requirement of getting the planned cost in terms of $ and hours on a network activity getting posted to some other CO version other than 0 in certain cases.
It would be great if anyone could suggest a FM or a BAPI to achieve this end?
Please reply if you need any clarification on the requirement
Regards,
JibatIn Cj30 you will get the CO version '000 , If you want to your can copy cost planning values of your version V01 & V02 to
Version 0 and do the budgeting Because you actual will happen to 0 only so, to compare your plan should be there idealy.
Apart from that network cost planning can only be done in 0 version. And system give you option of copying the your preliminary plannning to version 0.
Virendra - Thanks for the explanation. It made my understanding better as well.
With Regards
Nitin P.
Edited by: Nitin Patoliya on Dec 3, 2009 12:50 PM -
Costs on internal network activity
Hi,
I use SAP ECC6, actually.
I created an internal network activity and I linked it a work center and an activity type.
When I run a report, every report, I don't see the costs relative to this network activity.
Please, could you help me?
Thanks a lot in advance
RegardsHi,
Please ensure you have followed following steps:
1. Assigned cost center and activity type on costing view of workcenter. After this assignment when you assign work center to activity, the activity type gets automatically populated.
2. Maintain rate for activity type in Tcode KP26. Take help of your FI consultant.
3. If your system is not calculating cost during saving of project, you need to manually calculate cost. Click on activity and press CtrlF10 to calculate cost and CtrlF11 to display cost.
Hope this helps.
Regards -
Work Order Cost/Planned data by Activity Type
Does anyone know the cube that would contain planned and actual cost for work orders using the work order activity type (AUFK-ILART)
Will reward points as always.
RichardHi Ashish Jain,
I have planned activity type/price with the transaction KP26, but the system doesn't return any value in planned costs of WBE.
Why?
Thanks
Nicola -
Error occured during budget check while planning in network activity
Dear All,
i have created a project with 4 WBSE. i have assigned budget to one of these WBSE and released that project. than i want to do planning in next WBSE this is giving error while saving this planning as Error occured during budget check, see cost.
i have created user status for budgeting like if we have not budgeted than WBS is not able to release. i have added availability control as Forbidden while not budgeted but this not effective.
please suggest me some thing to remove this problem
thanks
Sunilhi,
In WBS you can Plan and budget to group WBS , the below wbs will consume budget form top.
Proj>WBS1(Group WBS- Plan/Budget) it is applicable for below all wbs elements say WBS2>WBS3
When you are determining Hierarchy you should create WBS in same levels then only you can allocate Budget.
If you wan to allocate budget for WBS2 and WBS3 separately.
Proj
WBS1
WBS2 WBS3
WBS2A WBS3A
WBS2B WBS3B
WBS2C WBS3C
Proj>WBS1 (it will no more act as Group wbs element) then you can directly plan and budget for below wbs elements WBS2 and WBS3.
Below hierarchy will consume budget from as displayed above.
Note: In you case as per my understanding return budget make zero, then plan and budget the same it will work.
Thanks and regards
Sadiq -
Easy Cost Planning version 0 cannot be used in DP81
Dear SAP Expert,
Please advice.
We have requirement to do sales pricing in DP81 with project and inquiry.
Some steps that we are doing :
1. Create Inquiry : VA11
2. Create Project : CJ20n
3. Create cost planning with network activity in CJ20n and use Planning cost version 1. ( We are trying to use more than 1 version, not only version 0)
4. Run DP81. It shows error message no expenditure.
In the config ODP1 ( DIP Profile) , version has been activated.
Is there any solution to use ECP with version more than version 0?
Appreciate for the advice.
Thank you.
NiesHi Sanjeev,
Sales Pricing (DP81) can read ECP with standard version 0. The issue is that DP81 cannot read version other then 0.
I need to do planning cost using version other than version 0 ( Actual/Planning version)
Thank you for your advice. -
Project system network activity cost distribute
it is possible that i distribute the plan cost of external network activity to period wise. if yes then how ..........
thanksHi
You can't plan the cost of external network activity period wise. The lowest level you can plan period wise is WBS Element level.
Regards,
Suraj -
Hi PS Gurus,
Do you know of any way for a user to set a custom distribution of costs for a network activity? For example, a cost activity is created for $100,000 which runs for 12 months. In current design, this value will be evenly distributed over the 12 months according to the factory calendar. What the user would like to do is manually adjust the profile by which these costs are planned.
Many thanks, and I hope you all are well.
Cheers, DianaI can suggest two options:-
1. Create as many distribution profiles as possible and let the user select as per the project need.
2. Create invoice plan for general cost activity as per your distribution requirement. -
Product Costing - Planning & Actuals
Hi All
I'm new to Product Costing. I dnt have much of functional knowledge aswell. I want to how the Planning Values & the actuals values are calculated in SAP thru PC. May be if you can explain me with an example, it wld be of grt help to me. I want PC for Make to Stock scenario. Expecting your reply.
Regards
RajaramDear,
I will explain with an example.
Main product is A, Raw materials are B,C & D. Let us assume that relationship between FERT & ROH is 1:1 ,
So for manufacturing 100 EA of A we need 100 EA of B,C & D.
Next let us assume that there is one operation involved in the shopfloor. The machine rate per hour (200 Rs) & the Labor rate per hour (300 Rs) . Let us say for manufacturing 100 EA it involves 2 hours of M/C & Labor.
The overhead costs of the company is 50 % of the operation cost (this percentage is maintained in the costing sheet against the secondary cost elements of the activity types).
Say there is a sub-contracting process involved which costs around 100 Rs per 100 EA of A.
Given the above conditions ,when you do the cost estimate the system will arrive at the cost of the product as follows.
Product A
Material Cost
Component Qty Per unit Cost Total Cost
B 100 2 200
C 100 1 100
D 100 2.5 250
Operation Cost
Activity Hours Per hour Rate Total Cost
Machine 2 200 400
Labor 2 300 600
Overhead
Overhead is 50 % of total operation cost = 1000 * 0.5 = 500
External Processing Costs
Sub-contracting = 100
Total Cost of Goods Manufactured = 2150
Price of 1 A is 21.5 Rs.
Hope this explains you the four main segments invovlved in the product costing clearly.
Thanks & Regards,
Vijaya Bhaskar A
Edited by: Vijaya Bhaskar A on Jan 11, 2009 1:01 PM -
How to check plan line items for plan cost at network activity level?
Dear all,
How to check plan line items for plan cost at network activity level? The plan cost is done in network activity in CJ20N.
I am not able to check using CJI4 or CJI9 report.
Kindly advise.
Thanks and regards,
JessieHi Jess,
Have you checked the navigation part which is being displayed on left hand side of report S_ALR_87013565 and S_ALR_87013533.? There you have option to check transaction currency and object currency when you double click on it.
In case if it is not being displayed under navigation. Then you can bring them on from transaction code CJE2. For eg: Report group for S_ALR_87013533 is 12KST1C. Double click on it and it will open up to do changes in report layout and many more. There you also have options to bring on transaction currency too. Similarly, you can check for other report groups as well just by checking the report description.
But I am not sure if suits your requirements. Wait for other experts to comment on this.
Regards,
Amit -
Actual Activity allocation and Planned and actual activity comparison issue in Product Costing
Friends,
I have tried to explain the issue i am facing currently under Product Costing......
1.Cost Component Structure
10 – Material
20 – Labour
30 – Diesel
40 – Electricity
2.KP26 – Planned under Fixed Price
Labour – 2.0 HR
Diesel – 1.0 HR
Electricity – 5.0 HR
3. When I run CK11N system collecting correct rates for all activities (Costing Lot Size- 1)
Like;
1 E LAB10 994310 2.00 2.00 AED 1.0 HR Labour Cost New
2 E DIE20 994320 5.00 5.00 AED 1.0 HR Diesel Cost New
3 E ELE30 994330 1.00 1.00 AED 1.0 HR Electricity Cost
4 M 1100000042 5.00 0.00 AED 1 PC RAW MATERIAL BAKERY CONSUMED
5 G 994201 0.00 0.00 AED Depriciation Cost
6 G 994202 0.00 0.00 AED Sales & Distribution Cost
13.00 AED
4.When I do process order Cost analysis for the produced goods it shows me different figures as my
BOM – RM is 1100000042 1 Quantity
Routing – All activity time is 1 Hr
40002 RAW MATERIAL BAKERY CONSUMED 1005/1100000042 5.00
40015 COST OF GOODS MANUFACTURED 1005/4400000071 13.00-
994310 Labour Cost New CBAKYPDDXB/LAB10 1.33
994320 Diesel Cost New CBAKYPDDXB/DIE20 3.33
994330 Electricity Cost CBAKYPDDXB/ELE30 0.67
2.67- AED
Note :- As per my understanding it should be
Labour Cost New 2.00
Diesel Cost New 5.00
Electricity Cost 1.00
5.Now after Process Order confirmation
40002 RAW MATERIAL BAKERY CONSUMED 1005/1100000042 5.00
40015 COST OF GOODS MANUFACTURED 1005/4400000071 00.00
994310 Labour Cost New CBAKYPDDXB/LAB10 4.00
994320 Diesel Cost New CBAKYPDDXB/DIE20 5.00
994330 Electricity Cost CBAKYPDDXB/ELE30 2.00
16.00
6.For Month end actual Activity calculation and load the activaty actual rates on product
I have configured the system in below manner
1 Work center = Mapped to 1 Production Cost center
Three Different Activities mapped to Secondary Cost Element with 43 Category
For Electrictity Activity assesment from Primary to secondary 1 more cost element created with
Category 42 Like; 994215-Electricity Cost All
One Actual Assessment has been configured to allocate Electricity cost from Primary Cost element to
Product/Order
7.Assessment Cycle Details
Controlling Area 1000 Controlling Area
Cycle ZELE01 Status Reviewed
Start Date 01.01.2014 To 31.10.2014
Text Elec. Cost Allocation to PROD
IND- Interactive
Assessment CEle 994215 Electricity Cost All
Sender
Cost Center CBAKYDXBAD
Cost Element 40204
Receiver
Cost Center CBAKYPDDXB
Tracing Factor
Var.portion type – Actual Activity
Selaction Criteria
Activity Type - ELE30
Receivers Tracing Factor
Cost Ctr Factor per 100
CBAKYPDDXB 100
8.I have received the actuall electricity bill for 1100 AED and the same has accocated through KSU5
After Cycle run when I follow below procedure
KSS2 Actual cost splitting
CBAKYPDDXB Production Dxb LAB01 183.33
CBAKYPDDXB Production Dxb DIE02 183.33
CBAKYPDDXB Production Dxb ELE03 183.33
CBAKYPDDXB Production Dxb DIE20 183.33
CBAKYPDDXB Production Dxb ELE30 183.33
CBAKYPDDXB Production Dxb LAB10 183.35
1100.00
Issue – System Split Electricity cost between all the activities assigned to Workcentres Cost Centre.
But I want to post that cost only to ELE30 Activity and not for all
When I RUN KSSI for actual Price determination system shows
OTy Object Name AUn Act Qty Total price Price (Fixed) PUnit
ATY CBAKYPDDXB/DIE20 Production Dxb HR 5.0 366.66 366.66 10
ATY CBAKYPDDXB/ELE30 Production Dxb HR 2.0 916.65 916.65 10
ATY CBAKYPDDXB/LAB10 Production Dxb HR 2.0 916.75 916.75 10
2200.06
2200.06 is almost double than 1100.00 which is actual electricity cost and the same is actually determined for all the activities.
After revaluation of the process order system posting below values
40002 RAW MATERIAL BAKERY CONSUMED 1005/1100000042 5.00 5.00
40015 COST OF GOODS MANUFACTURED 1005/4400000071 13.00- 13.00-
994310 Labour Cost New CBAKYPDDXB/LAB10 1.33 183.35
994320 Diesel Cost New CBAKYPDDXB/DIE20 3.33 183.33
994330 Electricity Cost CBAKYPDDXB/ELE30 0.67 183.33
2.67- 542.01
Production Variance is posted as 542.01….
I strongly believe there is some issue in configuration for activity allocation….
Main issue is
Point No. 4 – Different Figures in Process Order Cost Analysis
Point No. 7 – Assessment cycle run
Point No. 8 – KSS2 and KSII for Actual cost Allocation and Production variance…
Friends… I have tried to explain maximum please help me to understand the concept or missing configuration/Process.
Thanks
Sagar ChinchkarDear Rajneesh,
I have made the changes as suggested....
It seems now my Order Cost analysis and Product cost analysis are showing the same figures.
I have also maintained cost center splitting structure for ELE30 Activity allocation.
Structure Z1
Splitting structure for AT
Assignment 10
Electricity Cost
100
Allocation for ELE
Cost Element
994215
Activity Type
ELE30
Splitting Rule
100
Allocation for ELE
12
Activity quantity
Version 0
In my case actual activity confirmed is 3.1 for 2 orders in period 5
Order 1 - QTY 2
Order 2 - QTY 1.1
Total actual Electricity exp is 1150 in period 5
followed procedure to post actual activity on product is mentioned below
KSS2 Actual cost splitting - Result as expected 1150 for ELE30
KSII Actual price determination - Result as expected 3.1 actual confirmed QTY for ELE30 with actual price
QTY 3.1 Tot Price 3,709.68 Planned(FIX) 3,709.68 Per Units 10
(System is doing 1150/3.1*10=3709.68)
3.CON2 Actual revaluation of orders
Here while reevaluating the Process Orders system calculation is different
Order 1 - QTY 2 - 558.00
Order 2 - QTY 1.1 - 407.56
Total - 965.57
4. After CON2 system is changing the value of other activities like
LAB10 - Actual confirmed Value 10 to 0
DIE20 - Actual confirmed Value 10 to 0
Which should not be the case....
PL Act Var
40002
RAW MATERIAL BAKERY CONSUMED
1005/1100000042
10.00
15.00
50.00
40015
COST OF GOODS MANUFACTURED
1005/4400000074
26.00-
26.00-
994201
Depriciation Cost
WMBDDEP01
1.00
0.00
100.00-
994202
Sales & Distribution Cost
WMBDS&A01
1.00
0.00
100.00-
994310
Labour Cost New
CBAKYPDDXB/LAB10
4.00
0.00
100.00-
994320
Diesel Cost New
CBAKYPDDXB/DIE20
10.00
0.00
100.00-
994330
Electricity Cost
CBAKYPDDXB/ELE30
2.00
408.06
20,303.00
If we want to just post Electricity cost based on actual Electricity expenses and Labor and Diesel are based on planned activity rates.
What setting is required in current system.....
Million thanks in advance....
Regards
Sagar Chinchkar
Maybe you are looking for
-
Perhaps this app already exists. If not, would someone please write one. I want an app that monitors each application's run time/power consumption (or whatever you want to call it. I want to be able to open this app and instantly see which app is con
-
I have a some pieces of equipment that I'm looking to consolidate into fewer pieces but am having trouble deciding. I have an ibook g4 867, dual g5 2.7, and 2 20" cinemas. I am considering selling off the laptop and 20" displays to make room for a 30
-
I need to get rid of a calendar alert
I keep getting a calendar alert that I need to delete (it's a medication prompt that is now a week off from the proper schedule.) It says it is attached to the home calendar at my me.com account, but when I sign into the cloud to check, there is no
-
How much disk space is needed to run Boot Camp using Windows XP?
How much disk space is needed to run Boot Camp using Windows XP?
-
Update Global Temp Table in Oracle 11g
Hi Experts, Scenario: I have stored procedure A which calls procedure B. Procedure B uses Global temp Tables(With On Commit Preserve Rows) to work with the data. I am trying to update one of the GTT in Proc B but unable to do it .. via SQL or via P