Significance of deliveries in STOs

Hi
Please explain the significance and the process when deliveries used in STO processes
Reagrds
Jupudi

Hi Jupudi,
a lot of companies want to have the same kind of documentation for a goods issue for an STO as they have it with a delivery for a sales order.
Process:
1. create STO (ME21N)
2. create delivery (VL10B/VL10D/VL10F etc)
3. PGI (VL02N, VL06G, VL06O)
4. PGR against the delivery to correctly update document flow (MIGO). In case of a one step STO the PGR is done automatically when doing PGI
5. cross company STO: create intercompany billing doc (VF01)
6. cross company STO: create invoice for PO (MIRO)
You need to set up sales views for the materials affected, and execute the IMG activities for STOs (OLME -> Purchase Order -> Set up Stock Transport Order). These steps and the process is really just the basics, you can complicate it if you want.
Please also search the forum, I'm pretty sure you'll find more than enough threads
Cheers,
Attila

Similar Messages

  • Inbound deliveries with STO

    Hi,
    I am currently designing an interface with an external WMS and I am thinking to use inbound deliveries but it seems inbound deliveries with stock transport order have important restrictions :
    1. inbound deliveries are created with the quantity from the STO and not from the outbound delivery => risk on stock in transit
    2. The batch numbers are not copied from the outbound delivery to the inbound delivery (it is done in GR with MIGO if you post from outbound delivery)
    3. I haven't (yet) found a way to create automatically an inbound delivery when you post the goods issue from the outbound delivery. (it seems SAP is providing special development for that ?)
    Does anyone experienced the use of inbound deliveries with STO and what are your recommendation?
    Thanks a lot,
    JP

    Hi,
    We want to create inbound delivery in order to interface with an external WMS (Warehouse Management). We are not using standard SAP "decentralized WMS" interface.
    By using inbound deliveries for the interface, we can initiate the GR in SAP and then wait for confirmation from WMS. The WMS can then confirm different quantities if some discrepancies are identified during unloading.
    Also, creating inbound deliveries allow planning for receiving (i.e yard management).
    => We do not want to post the GR first in SAP and then send it to the WMS as they can find some differences during unloading
    => We do not want warehouse operators to work in SAP
    => We need a document in the WMS which will trigger task creation for GR for warehouse operators.
    => We want to use same solution for GR for external purchase orders and STO. So if we use inbound deliveries for PO, we want to use it for STO.
    Does anyone has experienced to create inbound delivery for STO from outbound delivery with Idoc (i.e ASN with DESADV) or specific development ?
    Thanks for your help,
    JP

  • Why there is no manual creation of deliveries for STO...

    Individual(VL01N) : You can create one delivery for each sale order on the screen. There is no manual creation of deliveries for STOu2019s. Transaction VL01N
    Why there is no manual creation of deliveries for STO...
    Thank you very much.
    Hoolaa
    Edited by: Hoo Laa on Mar 28, 2011 12:28 PM

    hi ,
             you have  to create a sale order process to delivery the tcode VL10B for STO Porcess. not VL01N.
    Regards,
    A.Sithanandan

  • Partial deliveries in STO

    Hello,
    I am rather new to MRP and ATP check.  I have already searched the forum but i could not find how to solve this issue.
    Can you please help me solve the issue below?
    When we were creating outbound deliveries against STO, the deliveries were not appearing in transaction MD04.
    Well sometimes the delivery appears in MD04 and sometimes it doesn’t.
    In the material master, the strategy group defined was 00 - Noplanning / no requirements transfer
    So we have added an additional entry in transaction OVZI, with source 1 - MRP type.
    After this change in customizing, the deliveries started to appear in MD04. 
    However since this change, the deliveries are now being created in partial quantity (probably due to stock availability).  The client doesn’t want to have partial deliveries they want only one delivery with total quantity.
    I have checked the shipping details defined in the customer and it seems to be ok.  Partial delivery are not allowed
    Could you please help me prevent the creation of partial deliveries?
    Thanks and regards,
    Yannick

    Hi,
    Do refer the below OSS Notes , it explain why we can stop the partial deliveries.
    842829 - Characteristics of replenishment deliveries from STOs
    16239 - Complete delivery indicator is not checked

  • Combined Deliveries for STO

    Can anyone tell me the criteria for combining deliveries for STO's.., I believe the delivering plant, receiving plant and delivery data....is there anything else........where do you configure this...
    i have two STO's where the delivering plants are different but the receiving plant/shipping point/ delivery date are the same and the deliveries are combining and give me a single delivery...that doesnt seem rite...can anyone help me in this..
    Thanks,
    Michelle

    Hi Sivanand,
    Thanks for responding.., but my problem is that i do not want combined deliveries when the delivering plants are different.say I have two or more delivering plants which have the same shipping point and when they transfer to the same recieving plant, the deliveries are combining. I want the deliveries to combine if there are more than 1 delivery from the same delivering plant but a delivery split if deliveries are from different delivering plants.
    A -
    > B
    C -
    > B
    D -
    > B
    A -
    > B
    I want total of 3 deliveries going to plant B
    I want the 2 deliveries to combine going from A ---> B
    a single delivery from C----> B and another delivery from D -
    > B
    All the plants belong to the same company code.
    Thanks,
    Michelle.

  • Significance and scope of STO & STR

    Folks
    I am trying to understand the Significance and scope of STO & STR.
    1. Are STO & STRu2019s primarily used to transport the stock between
           a). Plants within same company or
           b). Plants within different company or
    2. At what point in the logistics/SCM process does STR/STO get created?
    3. Are STR/STO created manually or through MRP / SNP?
    4. Whatu2019s the standard approach to convert STR to STO.
    Thanks

    How do you differentiate STO and PO?  Both are pruchase orders that are created with ME21N and changed in ME22N.
    if the plants are in the same company then you use order document type UB.
    if the plants are in different company codes then you either stay with the standard and use NB as document type (or you still want differentiate between real external orders and purchase orders made to a partner company, then you can create an extra document type like IC for intercompany)
    MRP creates planned order or requisitions only, based on settings made in MRP parameters and indicators set in material master, but never an external document like purchase order or STO.
    The main difference between UB and NB stock transport orders is that in UB orders you just  mention a plant instead of a vendor number. further in NB orders you need to have an price because there is  a billing requirement  between two legal entities while UB orders do not have price conditions (except for freight costs with external carriers).
    The setting from which SAP knows whether it has to create a NB or UB  is made in purchasing customizing of stock transports. Further SAP will know from enterprise customizing if the plants involved belong to same or different company codes.
    In case of different company codes, you need to create vendor master data for each plant,  and the vendor needs to be linked to a plant. (table T001W)

  • Item Category Determination in Deliveries against STO

    Dear Guru,
    In our STO process, there will always have a Outbound delivery created for this STO PO.
    Actually my question is how the system deterermine the correct item category for the outbound delivery.
    I checked through configuration under "Define Item Category Determination in Deliveries" or tcode "0184", from which i can find the conbination by "delivery type" + Item category group, but there are many different item category usage and default item category
    As such, can anyone please advice me if there is any place where i can maintain the "item category usage" or "Default Item category" to allow the UB STO PO determine the correct item category.
    thank you very much
    Regards
    Chee Wee

    Dear Pankaj,
    So sorry, i'm still not clear.
    Actually for my client, they have a non-standard PO document type UB2 for the Stock transport order between 2 different plant and the physical address or location will determine by the storage location.
    and the complete flow is STO PO--> Outbound delivery --> Inbound Delivery with Ref. with outbound Delivery
    --> Goods Issue --> Goods Receipt
    and understand from other post, the Mvt type to be use for the outbound delivery will be determine by the item category and Sales Order Schedule line.
    For my case, the default Order type is YDL, and Item cat group in Sales Org view 2 is Norm, but for YDL + Norm conbination are many which having different Item catogory usage and Item category.
    So how can i know which one the correct item category in "0184" which i can use it to determine the Sales order schedule line.?

  • Need a report to see the inbound deliveries on STO

    Hello,
    I would like to run a report which will give me the list of open STOs which i can filter by material, supply plant, receiving plant or date.
    Is there a standard report available for this?
    Thanks
    Bala

    Hi,
    Check the transcation ME2N with following option
    Scope of list - ALV
    Selection Parameters - WE101
    Document Type - UB
    Hope this will be of some help to you.
    Thanks & Best Regards,
    Devendra Gaware

  • Multiple outbound deliveries in STO

    Hi
    We have created a new purchase order document type for intercompany stock transport order.  If a PO has two line items, system is creating two outbound deliveries, though shipping point is same for both the line items.
    Am I missing any config step
    please advice
    regards
    satyaprasad

    Hi
    Use the solution from note  377501 to solve the issue. please read this one
    regards,
    Ramana

  • Reg:list of stock tranporting order(STO) deliveries whose GR is open

    Hi All,
    please respond ,
    i search this question in forums,this question was repeated
    but unanswerd, my requirement is.
    get the list of deliveries for STO and whose GR is open
    is there any standard bapi to get like this...
    if there is no bapi for this let me know the table names to maintain GR status for deliveries, so that i will generate my own function module.
    ( please dont suggest me to use transaction VL06I and so,
    i want bapi or table names)
    Thank you
    Sumalatha.

    Hi lakshmi kumar  thanks for u r reply,
    but i didn't get you, please tell me the table names
    for holding delivery orders and status for GR (for STO).
    Thank you
    Sumalatha.

  • One Invoice from 2 deliveries

    Hi Gurus,
    can anybody Plz help?
    1.) Suppose i have two deliveries say 80015009 and 80015010. I want to make one invoice from it how to do it? I tried through VF01 and also all the header data is same. is there any copy control setting which is left out?plz answer in details?
    2.) In case of STO Intra company I have purchase order through ME21N, Than created a delivery by VL01n and now that i am trying to create Invoice from it , it says " Not relevant for billing" can anybody plz help?
    3.) How to make Multiple deliveries in STO Intracompany from One Purchase order?

    1. check for you PO no in standard system po is also one of the selection creteria in zuk table -- dist channel, div and purchase order.
      or change you ref no alter no in copy control.  may be po mentioned in it. check vbrk/vbap field in copy control (item)-select sample
    2. in sto process you have select through collective processing only VL10b or vl10g.
    3. select fore ground(not back grond)--select only single doc(PO) and in the del doc you change qty

  • Using a Non-valuated, non-stock material in an STO

    Created a planning material with UNBW material type in ECC 6 to use to help manage shipping capacity at the mill.  Added to a sales order and it decremented the plan as expected.
    Half of the mill's deliveries are STO's so now trying to get this to work on an STO.
    Does anybody have advice on how to get a non-valuated, non-stock material (ideally, a planning material, but we could work around this) that we don't plan to deliver, to work on an STO?

    Thx for replying.  I need the material to be accepted by the STO but also to work with planning so it decrements a planned shipping capacity for the mill.  So I am trying to figure out how to get it on the STO and be differentiated from other, normal materials that have $ value, inventory, and account assignment,  This material will only have a planned quantity that can be decremented by demand coming from either sales orders or STO's.

  • Is it possible to add item in Outbound delivery from a different STO

    Hi experts
    I have a question regarding adding an item in delivery from different STO.
    we create outbound deliveries from STOs and at times we have all conditions same for shipping and we need to add another item in delivery from a different STO.
    I am not getting an option in VL02 to ad another item with reference to STO, is it possible to create delivery by adding another item from STO?
    Thanks & Regards
    Anand

    You can combine STOS in to one OB delivery if they are all from teh same plant. You could use the customer master >> order combination indicator

  • Full STO delivery

    Folks,
    I have multiple items on an STO and would like to delivery those in 1 delivery. SO delivery should only be created in case all items are fully in stock.
    I've set the partial delivery indiactor off in the customer master. I've also set that a complete delivery is required by law in the customer master.
    Now, I have created a situation in which not all items are on stock and would have expected that VL10b would not create a delivery. However, it does create a delivery for those items that are on stock.
    It seems that the indicators set in customer master are not applicable for STO?
    Is this functionality not present in standard SAP?
    Thanks,
    MZ

    have a look into OSS  Note 842829 - Characteristics of replenishment deliveries from STOs
    among others info there is following statement:
    In replenishment deliveries, the system does not read the purchase order (PO) history. Furthermore, you do not know which other replenishment deliveries exist for the same underlying STO and STO item, or what quantity they contain. Therefore, there is no equivalent for open order quantities (LIPSD-OFMNG) in deliveries for sales orders. As a result, the following fields are not transferred because they are irrelevant, and the following functions are not developed for replenishment deliveries:
    a) Underdelivery tolerance and overdelivery tolerance, UEBTO, UNTTO, UEBTK, TVLP-UEBPR
    b) Complete delivery AUTLF and the number of partial deliveries ANTLF
    c) KZTLF is active for the characteristic values A and B only.

  • STO HU Shipment

    Hello experts,
    I have the following scenario:
    1. STO from plant A to plant B
    2. Plant A creates deliveries for STO.
    3. We pick HUs in the delivery.
    4. We create a shipment
    5. In the shipment we create a shipment HU (truck) and we pack the delivery's HUs
    6. We make de goods issue
    7. SPED message creates the Inbound delivery for plant B
    8. We make the putaway
    9. We make the goods receipt.
    The problem here is that HUs arrive to plant B as hierarchical because they are keeping the shipment HU, we notice that the only posibility is to unpack the shipment before Inbound delivery is created or des-assing HU from Inbound delivery, unpack the shipment and re-assing the HUs to the inbound however our customer is not ok with this. Do you know any other option?
    We use Hu in the shipment to control double trailer to identify the what is in each one.
    Thx.

    Hi
    ========================================================
    As far as I understand your description, the scenario you
    want to carry out (pack stock transfer deliveries both in shipment and
    in delivery) is not supported or at least, an extra step should be
    performed.
    The fact that TO creation does not work is not the main problem to me.
    More important is that after the GR posting, HUs could not be further
    used as they would still be packed in the shipment HU. You can test thi
    easily using a receiving storage location without WM.
    Therefore, I would say the delivery HU should be unpacked from the
    shipment before it is assigned to the delivery because after the
    assignment, the HUs won't be visible anymore ('delivery-HU' will be
    displayed instead) from the shipment.
    ========================================================
    Here are two notes 1025090 and 1029324. Please apply them if they are
    not in your system yet. These two notes are to prevent some other error
    in your scenario, but not solve the current problem.
    Kind regards,
    Ramana

Maybe you are looking for

  • No data in reports after upgrade to CRJ

    After upgrading from Crystal Reports 10 JRC to Crystal for Eclipse CRJ, we have a few of reports that are returning no data. Out of 50 reports only 3 do not return data the rest are fine. We have a jsp page which passes a couple parameters to the cry

  • Post Creation/Installation Document.

    Hello, Is there any formal template for a document, Post Creation/Installation of Oracle Database? As in Control File Locations, Log File location, Environment settings, etc. etc. that is required to be maintained after installing the Oracle Server o

  • How to create 3 levels of Top Level Navigation?

    Hi I have a requirement to create 3 levels of TLN in this manner: Role A RoleAFolderA   |   RoleAFolderB RoleAFolderAViewA   |   RoleAFolderBViewB In the help, it says I can have only 2 levels max. How can I configure the TLN to display the third lev

  • Email in Inbox keeps dropping off.

    EMail in Inbox keeps dropping off.

  • CLIENT-CERT - UserNameMapper problem

    Hi, I have a client, wich sends a soap-message, containing a username, to a webservice, that responds with "hello, <username>". The communication is over ssl. The webservice is running in a weblogic server 7.0 sp1. I have 2-way ssl working. Now I'm t