SLED for different vendors

All,
I m doing project for a food industry and we are using batch management here.
They have some materials which are having different vendors and differnet vendors have different Shelf life expiration days .
So in that case normally what we used to do ?
How to enter SLED in material master ?
rfegards

Hello Sandeep,
I got your problem.
- Pl. maintain the min/max shelf life period in mat mater, it does not matter.
- Create batch record where you maintain actual self life period
- Use this batch in PO or GR so all the SL expiration data will be copied to GR.
Again, I suggest you to carry out this scenario in testiing environment becuase when you will carry out this transaction you will have better understanding
Regards
Arif Mansuri
still you need more info, pl. give me call to my cell +1 630 935 2372.

Similar Messages

  • Unplanned Delivery costs in MIRO for different Vendor

    I have an annual PO and I invoice it with normal MIRO transaction.
    At the same time I have one service which I want to be a unplanned delivery cost for this PO. This service will be assigned to the material account and it is for a different vendor.
    Can I do it in MIRO creating only the value in the unplanned delivery cost and insert a different vendor? In OBYC this is assigned to UPF category.
    Can you please help me?

    Hello,
    You can use transaction MIRO to do unplanned delivery costs.
    You use "Subsequent Debit" and insert the PO number (equal to invoice). The system will show the lines of the PO that were already invoiced and in the tab "Details" you should change the Invoice Party and inser the value of the unplanned delivery costs in the field "Unpl. Del. Csts".
    If you don't have the costs in the PO for different vendor you must create like this...with Subsequent Debit. Only if you have planned costs in the PO it is possible to do it invoice and costs in the same document for different vendors otherwise you must have 2 documents (invoice for the material vendor and subsequent debit for the other unplanned costs vendor).

  • How to track cost for different Vendors through SAP PM

    Hi
    Maintenance needs to discuss with SAP PM Consultant for tracking the different vendor for civil, painting and external services jobs from asset locations and class. It means that total expenses of Civil, Painting and external services jobs for different locations should be easily gathered.
    Also ,As temporary solution of identifying posting for different vendors, how maintenance will be able to find actual amount posted for different vendors
    Regards
    chand

    Hi
    can you tell me where we can make control
    When RFQ is created the PR is not allowed to change when the PR is manually created & it is working perfectly.
    but when PR is created thorugh work order then even if RFQ is created/released  it is allowing to change PR when created throogh work order
    Please tell me where is control
    Regards
    chand

  • Different MIC,s for different vendor.

    Hi,
    My client has a business sceenario like this...
    they procure same material from 2 different vendors.for one vendor they want simple MIC's to be inspected and for other they want some more characteristics to be checked. I can use two IP but they dont want it.
    Plz give some solution for this.
    Thanks

    create a inspection plan for the material.
    Create 2 group counter and assign different MIC's.
    Goto header and select material assignment tab. in that you will see the group counters and also a field for vendor. you can fill the vendor no there.
    in this way you can create  combination of material, group counter and vendor.
    during GR, system will select MIC based on the above combination

  • Invoice for different vendor

    Hi,
    I have created PO for XYZ vendor and when I create Invoice it goes on different vendor as ABC. and it is not regular its happening some time.
    please suggest me why it is happening.
    Thanks
    Shital

    Hi
    check your vendor account group for  both vendor number for which its  happening  and vendor for which its not happening
    it might be you have took different  account,than regular ,for which vendor partner function active
    If its active for all account group the, check in vendor master record you have assign any invoicing party vendor in partner function
    if its correct
    then check you Po header partner tab,user might  change it in PO
    Regards
    Kailas  ugale

  • Customization for create 2 Work orders for different vendors against 1 PR

    Hi,
    What are the customization settings  to create 2 work orders for 2 different vendors against 1 PR with half-half quantity?

    thank you Mario.
    Actuly its infrastructure cmpany & user wants create Purchase order(service work order) for two different vendors with reference to single PR with alocating 60% quantity to 1st vendor & remaining 40% to another vendor.
    user allready created Po for 1st vendor (60% Quantity).
    Now system showing error " Quantity is allready full for reference PR"
    I want to know what is the procedue to solve this issue & customization.

  • Regarding BP tcode and MK03 for updating payment terms for different vendor

    My requirement was to update the payment terms in to MK03.
    Our business useseres will give the payment terms for FI Vendores in BP tcode and save payment terms for FI Vendores in BP TCODE and this payment terms shoule updated ditrectly in to MK03 for every FI Vendor .
    How we will update the payment frome BP to MK03 directly. In BP the technical name for payment terms was LFB1-ZTERM and in MK03 the technical name was LFM1-ZTERM .
    I want to update payment for single company code only. In mk01, we creating vendors for purchase org level how we will update payment to mk01 from BP TCODE pls give how i have to update this payment terms from BP to MK01.

    My requirement  was to update the payment terms in to MK03.
    Our business useseres will give the payment terms for FI Vendores in BP tcode and save payment terms for FI Vendores in BP TCODE  and this payment terms shoule updated ditrectly in to MK03 for every FI Vendor .
    How we will update the payment frome BP to MK03 directly. In BP  the technical name for payment terms was LFB1-ZTERM and in MK03 the technical name was LFM1-ZTERM .
    I want to update payment for single company code only.  In mk01, we  creating vendors for purchase org level how we will update payment to mk01 from BP TCODE pls give how i have to update this payment terms from BP to MK01.

  • Unplanned delivery cost for different Vendor

    Hi,
       For a import PO we need to pay OCTOI to Municipal corporation.
    Unfortunately while PO creation the octroi condition was not entered.
    Now we need to post a invoice for this and the condition is, we must post this to material.
    We dont want to do direct FI entry as then this will not load on material.
    Entring Unplanned delivery cost at the time of invoice will not be possible is the Vendor is different.
    Any suggestions please...
    Rajesh

    Dear Rajesh,
    unplanned delivery cost is basically which not plan at the time of PO and it will be expected at the time of invoice.
    you can enter extra amount in unplanned delivery cost, but check at the time of Stimulate which a/c is being captured.
    The Unplanned Delivery cost is default in separate GL or in Stock Account depends upon the configuration.
    check In SPRO ,Maintain settings as shown
    MM---> Logistic Invoice Verification -->Incoming Invoice --> Configure How unplanned delivery costs are posted
    Please check the below link for more information
    http://www.sap-img.com/financial/unplanned-and-plan-delivery-costs-in-stock-and-gl-account.htm
    Unplanned delivery costs in MIRO
    Regards,
    PK.

  • Re: Excise for For different vendor batches

    Import Purchases are there and the quantity is coming in two different batches, while doing the goods receipt the excise invoice is getting doubled if we split in to batches, which should not happen.How to tackle this issue

    Hi,
    This should not happen because system also splits the EI quantity in Excise Tab at Item details level when you split GR qty in MIGO.
    Are you splitting GR qty manually in MIGO or using "Distribute qty" button in MIGO for this. Once you click on this button, system gives a pop-up, here split qty and then adopt, and then check the excise qty and value. It should not get doubled.
    Note: - "Distribute qty" button is after Delete and Contents buttons. It is like X
    Just try this.

  • Production order usage for external vendors

    Hi Guys,
    I am working on a scenario where the company is orderiing to manufacture from external vendors involving different stages. There is no material sent to the vendor and the vendor manufactures the first stage and sends to next vendor, there are four stages involved.
    We are planning to use production order for the purpose and 4 operations thorugh which 4 purchase orders will be sent to four vendors and services or materials will be posted. I am just thinking how the final GR for finished product will be posted to the inventory. The requirement is track the cost at each stage...
    Please let me know of your thoughts on this...
    Thanks and regards,
    Sid

    Hi
    I dont think you will have any issues with the tracking of the cost and GR of the finished product.
    You have 4 operations each resulting into a PO for different Vendors each component/service of the opertaion will be received against each PO that you might have issued and so will be the cost collected actual cost for each operation.
    Final GR can be posted for the header material against the Production order. I would request you to complete a full scenario and review it with your FI/CO team for any issues. I dont think you will have any.
    Please let us know if you need any more info
    Thanks

  • PO issued for one vendor and GRPO another for the same

    Hai members,
                      I have a problem, is it possible , to select a different vendor for the PO reaised for different vendor,
    i.e.,
    Po raised  for 20 items against the Vendor   XYZ
    But goods received
    XYZ-   10
    ABC-   10

    Suda,
               At us the criteria  is
    One Vendor may have  several companies
    Once we produce order to him , he will dispatch the goods from either of the companies he had or from the both
    but the PO purchase order comes from only in one name of the vendor
    Suppose i had produced
    100 Pcs order for  Some  Vendor -
       XYZ
    But he may dispatch the same goods that we have ordered
    from either of the comapnies he had i.e., XYZ, 123, ABC
    but the PO is same
    I think you got it Suda, please help me........ Thanks in advance

  • ME05 : Generate Source List only for regular vendor

    Dear guru ,
    I use ME05 for the mass generation of source list.
    For one material i have two info-records for different vendors.
    If i run ME05 the system send this message u201CSeveral sources MRP-relevant on one dateu201D
    and create two records in the source list for the same material.
    Can i automatically create the source list only for the regular vendor fill for one of the info-record ?
    Thanks in advance.

    not answered

  • PO Group for different Purchasing Groups of SC Items

    Hi ,
    I want to create a single PO if 2 different PO Groups are available for items in SC.
    I could see that standard code is splitting PO for different vendors different Purchasing Groups contracts and soo on.
    is it possible to create a single PO for my case mentioned above.
    I am using BADI  BBP_BS_GROUP_BE for this but don't understand how to go about it.
    Please help with your useful suggestions.
    Thanks.

    Hi
    PO can be splitted based on Header Data
    Company Code
    Purchasing Organization,
    Purchase Group
    Vendor
    It also depends upon the backend customizing for assignmnet of plant to Purchasing Organization
    Thanks
    Trinath

  • Vendor Name Appearing Different for Different Line Items in FBL1N

    Hi,
    I am executing FBL1N and changing the layout to include the Vendor Name in the line items. But when the line items are appearing, the Vendor Name is appearing different for different documents. I wish to see from where the system is picking up the name, so that I can rectify this. But since the layout is being changed after the report is executed, the debug window is taking me in this. Can someone help me please how to debug so that I can see from where the name is coming?
    Thanks and Regards,
    Sameer Joshi

    Hi Raymond,
    Yes it was due to the BADI.
    Thanks for your reply.
    Thanks and Regards,
    Sameer Joshi

  • One MIRO document with two different vendors for two different line items

    Can it possible to make MIRO for a PO which is having two conditions(Basic price+Freight) with two different vendors.
    MIRO document needs:
    GR/IR Clearing    Dr.
    Freight Clearing  Dr.
    Vendor RM(X)         Cr.
    Vendor Freight(Y)   Cr.
    Is it possible to post the above document at a time not individually for each condition.

    Hi,
    Yes, It is possible to post Material and delivery cost in one document.where in material supplier is different than the Frieght vendor.
    Itm PK  BusA Acct no.   Description                    Tx     Amount in   USD   
    001 89       130001     Stock-Ingredients               244 0            880.00 
    002 96       320001     GR/IR Account - Ing.            244 0          1,200.00-
    003 86       520002     Ingredients - PPV               244 0          3,297.87 
    004 50       320008     GR/IR Account - Duty            244 0            797.87-
    005 50       320009     GR/IR Account - Fre.            244 0          2,180.00-
    Thanks
    Dinabandhu