Standard to item caregory B or Frame work order

Hello All
What are the impacts are there when i change the standard PO to item category B or frame work order.
Assume that one of the external system creates a PO in ECC system and i am trying to change the item category B or frame work order of the docuement type?
what impacts in the system?
one benifit, i need not do good receipt or any other benifts/ impacts?
any help  is appreciated.
Muthu

Hi,
Whether you trying to create the PO with Item Cat B you will need to worry about the consumption as with Cat. B you need to mention the Account assignment cat. whether its K or U or M any thing but your material will go in consumption directly for that specified account and not to the accounts you maintained for that material.
this will impact you on your monthly report's or the Yearly reports as if you have changed  tha account for consumption.
as well if you have consumed that material you need to put the Material Valuation as Moving only as the price of all the PO will be differed and the material in PO will need to monitor for MAP change by M1EP TCode.
see if you want to consume all the materials for specified accounts other than what you maintaining now, is very much helpful for you but not to maintain your Price. as well if you gonna sale that material how you going to rectify the price is a big problem so there will be a difference in Profit analysis also.
Try do Confirmatory test in DEV(i think you have done that) still i suggest not to go for B other than Standard one.
Regards,
Ninad Kshirsagar

Similar Messages

  • Item category limit (B) in frame work order

    Is it that item category B (limit) is mandetory in frame work order ? In that case it should appear by default. Can we use any other item category with frame work order logically?

    first the question is why do we use frame work order when we already have other document ype avilable
    answer is when ever we need to create a po for a validity period then frame work order is used
    next thing why do we use u=item category B or limit
    answer genrally frame. work order is used as blanket po means for those comodities which r procured very frequently but there monetrey value is very less
    and ur not intersted in doing there godd reciept u will be directly going for invoice reciept

  • Purchase Info Record for Frame work Order

    Hi Friends,
    Do we have Purchase info record for Frame work Order(FO) ?. If yes, Please tell me which info category should i need to select to create a Purchase Info Record.
    Thanks

    Hi
    Is that means, Framework  PO will also use the same standard Purchase info record ?
    Thanks

  • Frame work order po issue

    Hi
    I have created  frame work order purchase order, service entry sheet and invoice also completed then i reverse the invoice
    and reverse service entry sheet then i delete serve entry sheet also.so i need to delete po in me22n t.code during deletion
    that time showing error  Purchase Order item can not be deleted, Message no. ME303 there is no pending for release approval
    also.plz suggest.
    Regards
    Sam

    Hi,
    Why did you create a SES for a Framework Order, SAP Framework order does not need any GR/SES.
    Process is Framework Order > Invoices.
    Two way match.
    Thanks

  • Error in Frame Work Order

    Hi SAP Gurus
    While creating a frame work order system is providing an error "Enter free of Charge" and message number ME083. The material in concern is procured against cost center and it is not FOC material.
    I've checked in "Invoice Tab" the selection is there for Inv. receipt and in field selection for "FOF" there is no mandatory
    field selection GR/IR control. Pls help me solve this error.
    Thanks
    Rajesh

    Rajesh,
    See OSS note 167535.
    Symptom
    In Customizing, field "GR/GI indicator" is set as a required field. If you create a purchase order and enter an item on the table control overview screen and subsequently choose 'Enter', the system generates error message ME083 "Please enter free of charge". The cursor is placed on checkbox "Free item" in this case.
    Cause and prerequisites
    Field "Free item" has the same modification group as the GR/IR indicator.
    Regards,
    Nick

  • Frame work order - Process

    Hi Friends,
    We are using Blanket Purchase order(Order type- FO) for purchasing materials and services for the period of 2 years.
    We have one scenario, i don't know, how it will affect the Frame work Order.
    The scenario is,We have FO for the quantity of 10000 Materials in the period of Nov 2008 to Nov 2010. And every month, we are calling vendor and tell him  to send the material for the quantity of 100.
    First situation, we need more materials i.e 500 during Nov 2009 due to market demand in that case how Frame work order works, do we need to change Frame work order?. is it possible?.
    Second situation, During the month of Sep 2009, vendor is informing us that he can not give the same materials for same price due to increase in cost of materials. How Frame work order works, do we need to create new Frame work order or FO can be changed?.
    Appreciate your help.
    Thanks

    First situation: not possible,  you can not change the frame work order, you have to create new purchase order for 500 qty
    Second situation: also not possible, for the changed price,   create purchase order for the new price for the excess qty.
    thanks,
    SGR.

  • Frame work order in PM order

    Hi all,
    While creating PM order, for service, purchasing data, we can use Frame work order. If we use frame work order as source of supply, it is creating PR.
    You can do service entry sheet basing on PR, but while creating service entry sheet basing on PR is giving an error saying GR is not allowed for Order (PM) order. It is trying to do GR for service entry sheet against the PM order.
    Please give the settings needs to done to use Frame work order functionality in PM order? What are the subsequent process steps needs to be done? How can we settle the vendor and how can we close the PM order.
    Thanks in advance
    Regards
    krishna Prasad

    Hi,
    Framework order: -
    Purchasing document used to procure materials or external services. Instead of stipulating a specific delivery date, this type of purchase order has an extended validity period.
    Framework orders are defined via the document type FO. They are used in accelerated procurement processes in connection with maintenance/ servicing plans or invoicing plans, and for blanket purchase orders (purchase orders with limits).
    A framework order covers multiple procurement transactions over a longer period in cases where the administrative costs of processing discrete POs would be disproportionately high.

  • Can we use contract or Frame work order or any other?

    Dear Experts,
    We want to create a purchase order for our new plant which is being developed.
    We would like to give this contract to a Foreign Vendor, for which final value is fixed. Say, for example 1000 USD. The time limit would be say, for example, 6 months.
    So they will be sending the parts in several consignments. So, also, payment to vendor is will be done at various steps.
    As on when they make ready the parts for dispatch, they can send a list of items, along with prices. 
    Then we want to make a PO to them with reference to main contract, for each of the consignment which they ship.
    Finally we want to track,
    - the total value of the consignment as per this contract, so far...
    - the total payment done to the vendor as per this contract, so far...
    etc...
    Please suggest, which arrangement is correct.
    My contact number is 96111 01459 (Karnataka Mobile).
    Ganapathi

    We had a similar requirement in one of my older implementations. The solution we implemented is as follows:
    PO issued for 1 account assigned line item - Installation of plant - $1000.
    On receipt of details of first consignment, the PO is amended. The items are added in the PO and the value of the first line item is reduced.
    This helps track all the things you want to track.
    Hope this answers,
    Lakshman

  • Issue of invoice with reference to service frame work order

    Hi Gurus,
    i am creating service framework purchase order for a service material. in item detail of service framework po  in condition tab i maintain vat %  condition. then i create service entry sheet with reference to that po and post the entry. when i go to maintain invoice for that material  with ref to po the system shows two line items first line item shows amount and quantity to be invoice and second line item shows no amount or quantity but shows po number and po text  which mentions vat% .
    please tell me what customizing mistake has taken place
    regards

    Hi Suresh
    go to OLMSRV > taxes at individual service level
    then check box against country code.
    Best Regards
    Nishant Shende

  • Error while creating Frame work Purchase order

    Hi Gurus,
    We are trying to implement Frame work order process with following configurations.
    1)Item cat  B for acc assingment Y
    2)Allow  item catg B with acc *** K and Y.(How to config this in SPRO)
    So when i am creating a PO adopted through Purchase Req (account ***  K and item cat B) i am getting error message "Pricing Error :Mandatory condition NAVS is Missing".So how do i configure this pricing process.
    Also when i am creating a Frame work order do i need to select the document type both in PO and PR as frame work order or NB order type will work with these config of Item cat B and acc *** Y?
    When i am creating a PR or PO with doc type frame work order the order unit is automatically populating as "AU" is this something std or do i have to do anything in configuration?
    When i created a PO with ref to PR aith account *** K into the PO and add the item category B the charging information was not maintained so how to maintian this?
    How to maintain the accounting info from PR?
    Also if there is a complete process link releated to config of frame work order that will be great.
    Thanks in Advance.

    Hi
    We are trying to implement Frame work order process with following configurations.
    Item cat B for acc assingment Y
    Create new acct assignment category in IMG -MM - Purchasing -Account Assignment - Maintain Account Assignment Categories (If you are sure of fields to be used then you can directly create Y, if not then copy existing category say K to new one and choose required fields)
    Allow item catg B with acc *** K and Y.(How to config this in SPRO)
    In Purchasing - account assignment - Define Combination of Item Categories/Account Assignment Categories - set combination for Y and B.
    Hope your documement types (PO & PR) allows item category B.
    So when i am creating a PO adopted through Purchase Req (account *** K and item cat B) i am getting error message "Pricing Error :Mandatory condition NAVS is Missing".So how do i configure this pricing process.
    Check the pricing procedure in IMG - Purchasing - Conditions - Define Price Determination Process - Define Calculation Schema - Check for calculation schema - NAVS has been maintained.
    Also when i am creating a Frame work order do i need to select the document type both in PO and PR as frame work order or NB order type will work with these config of Item cat B and acc *** Y?
    You need to choose document types while creating purchase transactions. If that document type doesnt support item category B- then you will get an error message.
    When i am creating a PR or PO with doc type frame work order the order unit is automatically populating as "AU" is this something std or do i have to do anything in configuration?
    For services (D category) we define AU as default unit (IMG - MM - External Services Management - Source Determination and Default Values - for Client/for Purchasing Organizations)
    When i created a PO with ref to PR aith account *** K into the PO and add the item category B the charging information was not maintained so how to maintian this?
    How to maintain the accounting info from PR?
    create Framework requisition and then copy it to a PO.
    Thanks

  • Adding work order short text to KSBB report

    Presently, our budget administrator runs various KSBB reports for showing budget/actuals. For instance, you run the report <i>Plan/Actual Comparisons -> Additional Ratios -> Cost Centers: Act./Plan/Commitments</i>.  Then you drill down into the actual line items for the one of the material settlement cost centers. One of the fields in the resulting report is called "Partner Order" and it shows the work order associated with the line item.  Of course, the work order can be displayed in IW33.
    What I would like to do is show the work order number short text [description] either along with the work order number or instead of it.  I know the work order number ties back to the AUFNR field in the view CAUFV, and the short text goes back to the field CAUFV-KTEXT.  What I don't know is how to get KTEXT onto the KSBB report.  I'm sure I will have to customize the report, but I don't know where to start.
    Anybody have any ideas?  Thanks in advance.
    We are running 4.7 Enterprise (Basis 620) with FI, CO, MM, PM, PS, and HR/PY.

    Hi!
    After you have chosen the report and you are on the selection screen, you have to determine its technikal name. For this, choose environment - techikal information menu.
    Report group is what you need.
    Then go to GR55 transaction to modify the report group.
    Because these are not exact ABAP program, I don't know how can you read (select) data from caufv, but you might try it.
    OR! You can copy the program. The program name is also in the technikal data panel, its like this: GPC3IL91J3FDQJFRDFHTFNJSIKF040
    Give more human name to it and you can write your ABAP code into it.
    Regards
    Tamá

  • Goods issue wrf to work order (ESM)

    Dear All,
    External Service Management.
    my client had new scenerio.
    if a work order is issued for Rs.10,000/-  conditon that consumables / any spares required to complete the job should born by contractor.
    means : during the work if contractor need "gloves"  he should bring the gloves at his cost.
    but, the scenerio is
    my client is issuing those items with reference to that work order and at the time of billing he is deducting those cost and settling the bill.
    kindly advise how to map this please.
    Regards,
    Adi

    Dear Arul,
    Kindly be clear, and advise how to mark the issue while migo with reference to Work order please.
    regards
    Adi

  • The additive cost can not display on the work order plan cost

    dear friends
    first i run the ck74n for the additive cost ,second i run the ck11n for cost estimate ,i can see that the additive cost update to the standard cost successfully ,at last i run the ck24 mark and release the standard cost,but when i raise a work order ,i can  not see the additive cost in the plan cost ,i do not know the reason ,do you have some suggestion
    thanks

    Hi
    This behaviour is expected and standard...
    In Std cost estimate, you have the option of inputting components manually in CK74N... But the actual costs in Prod order will come either from Material issues/Activity Confirmations or manual postings from FI... There is no option to enter additive costs in actuals.. Hence, there is no option of "additive costs" in the Planned costng variant of Prod order
    If you enter any additive costs in CK11N, It is done because you cant estimate it through Qty Structure.. But, during actuals, the actual costs are all available through Material issues/Activity Confirmations.. hence, the additive costs does not apply here
    BR,Ajay M

  • Blanket and Frame work PO

    Hi,
    Can u explain what is blanket and frame work PO  , when we required this type of PO  and how to process it.
    regards,
    zafar

    HI,
    In general the Blanket POs are used for consumable materials such as Xerorx papers with a short text (does not need to have Master Record) with Item Category ' B' i.e.limit, where in the PO validity period as well as the limits are to be mentioned for the simplicity of procurement.
    The doc type is 'FO' (Framework Order). The GR or Service Entry for the PO are not necessary in case of Blanket POs as well as one need not to mention the account assignment category during creation of PO it can be 'U'-unknown & can be changed at the time of IR.
    Order type FO (framework order)
    1. Validity period in header of purchase order (field selection)
    2. Item category B (limit)
    A.. Limit in the item
    B. No material number
    C. Account assignment category U (unknown) is allowed
    D. No goods receipt or service entry
    3. Accounting data for the item suggested in invoices
    4. Additional or multiple account assignment possible in invoice verification
    5. Check of validity period and limit in invoice verification
    To be able to work with validity periods and limits in a purchase order, you must
    use document type FO (framework order) and item category B (limit). In the
    standard system, document type FO enables you to specify the validity period at
    PO header data level and use the item category B for limit items. (Limit items are
    sometimes referred to as blanket items.)
    Because you can only use a blanket order to procure consumable materials or
    services, you must enter an account assignment for PO items with the item
    category B. However, you need not specify the precise account assignment at the
    time you create the blanket PO. Instead, you can use the account assignment
    category U (unknown).
    You cannot specify a material number in a PO item with item category B. You
    have to describe the materials or services that are to be procured (such as office
    materials) using a short text. You also have to specify a material/service group.
    Regards,
    Pardeep Malik

  • Frame work Purchase Order Plus Service entry sheet

    Hello,
    We are having the issue of defining this Purchase order process for Non receivable items i:e items which are non goods receipt like PO for services.When we create a PO with one line item and quantity of 5 and total value of PO is 500 .So after the first invoice the system is closing the PO .System is not looking at the quantity and just closing out the PO .So we have to design a process in which we need to create multiple invoice for a Po(Non GR) also we need to set the tolerence limit for the PO which i thing will be set in OMR6 (PP) and also regardless on quantity the system can create multiple invoices .So what is a good process to drive this.Either Frame work PO or service entry sheet??
    Also is there a way in config we can set tolerence limit for the whole amount of PO .Like in OMR6 we define the upper and lower limit of PO .So if the total value of PO is 1000 ,while creating the invoice it vont allow us to create invoices for more than 1050 .can we set the tolerence for the whole amount of PO ?? Regardless of how many invoices we create.

    Thanks Andra,
    The problem is the multiple invoices is for non goods receipt item so there will be no delivery.At the time of creating a PO the GR is not checked so there will be no delivery .
    Also this setting is for invoices which are comming from Vendors.But if we are genrating the invoices manually it is not blocking those invoices.Also i there is nowhere mentioned in Incomming invoice to set tolerence for incomming invoice.Are you talking about Vendor tolerences?
    Thanks in advance
    Edited by: Metroid01 on May 14, 2009 6:52 PM

Maybe you are looking for

  • How can I delete local schedule tasks, if they do not show up in the left ARD pain

    In ARD you can schedule task on the local machine. Usually you can see the scheduled task in the left pain of the main window. I deleated some schedules tasks, but the tasks continue excute every morning. Is the a way to find these invisable schedule

  • How to catch a SOAP fault

    Hi All, I have a ISU to web service, PROXY to SOAP sync interface. I am getting following as response. How can I get this into Fault message mapping? I have followed these blogs: Fault Message Types - A Demo (Part 1) Handling Web Service SOAP Fault R

  • Why can't I install software as an administrator when I'm signed in as administrator?

    I just bought some software (Spector Pro), dowloaded it and am trying to install it on my MacBook Air. I get the message that I need to be an administrator to install it. But I checked in System Preferences and I am signed in as Admin. I have already

  • Driving me nutz!!!

    I have an ipad 4th gen and i went to do a full reset of media and data last night and once i startd it the screen went black and the little circle syarted goin round n round and its been doin so for 21 hours as of right now any idea what i should do?

  • Reg: OKEM

    Experts, There's a requirement to have Sales Order type(AUART) in the structure PCASUB for the transaction OKEM. For this, I have added AUART in PCASUB structure in SE11 tcode. But, the same is not appearing in PCASUB when i check that in OKEM. Requi