Frame work order - Process

Hi Friends,
We are using Blanket Purchase order(Order type- FO) for purchasing materials and services for the period of 2 years.
We have one scenario, i don't know, how it will affect the Frame work Order.
The scenario is,We have FO for the quantity of 10000 Materials in the period of Nov 2008 to Nov 2010. And every month, we are calling vendor and tell him  to send the material for the quantity of 100.
First situation, we need more materials i.e 500 during Nov 2009 due to market demand in that case how Frame work order works, do we need to change Frame work order?. is it possible?.
Second situation, During the month of Sep 2009, vendor is informing us that he can not give the same materials for same price due to increase in cost of materials. How Frame work order works, do we need to create new Frame work order or FO can be changed?.
Appreciate your help.
Thanks

First situation: not possible,  you can not change the frame work order, you have to create new purchase order for 500 qty
Second situation: also not possible, for the changed price,   create purchase order for the new price for the excess qty.
thanks,
SGR.

Similar Messages

  • Frame work order po issue

    Hi
    I have created  frame work order purchase order, service entry sheet and invoice also completed then i reverse the invoice
    and reverse service entry sheet then i delete serve entry sheet also.so i need to delete po in me22n t.code during deletion
    that time showing error  Purchase Order item can not be deleted, Message no. ME303 there is no pending for release approval
    also.plz suggest.
    Regards
    Sam

    Hi,
    Why did you create a SES for a Framework Order, SAP Framework order does not need any GR/SES.
    Process is Framework Order > Invoices.
    Two way match.
    Thanks

  • Frame work order in PM order

    Hi all,
    While creating PM order, for service, purchasing data, we can use Frame work order. If we use frame work order as source of supply, it is creating PR.
    You can do service entry sheet basing on PR, but while creating service entry sheet basing on PR is giving an error saying GR is not allowed for Order (PM) order. It is trying to do GR for service entry sheet against the PM order.
    Please give the settings needs to done to use Frame work order functionality in PM order? What are the subsequent process steps needs to be done? How can we settle the vendor and how can we close the PM order.
    Thanks in advance
    Regards
    krishna Prasad

    Hi,
    Framework order: -
    Purchasing document used to procure materials or external services. Instead of stipulating a specific delivery date, this type of purchase order has an extended validity period.
    Framework orders are defined via the document type FO. They are used in accelerated procurement processes in connection with maintenance/ servicing plans or invoicing plans, and for blanket purchase orders (purchase orders with limits).
    A framework order covers multiple procurement transactions over a longer period in cases where the administrative costs of processing discrete POs would be disproportionately high.

  • Standard to item caregory B or Frame work order

    Hello All
    What are the impacts are there when i change the standard PO to item category B or frame work order.
    Assume that one of the external system creates a PO in ECC system and i am trying to change the item category B or frame work order of the docuement type?
    what impacts in the system?
    one benifit, i need not do good receipt or any other benifts/ impacts?
    any help  is appreciated.
    Muthu

    Hi,
    Whether you trying to create the PO with Item Cat B you will need to worry about the consumption as with Cat. B you need to mention the Account assignment cat. whether its K or U or M any thing but your material will go in consumption directly for that specified account and not to the accounts you maintained for that material.
    this will impact you on your monthly report's or the Yearly reports as if you have changed  tha account for consumption.
    as well if you have consumed that material you need to put the Material Valuation as Moving only as the price of all the PO will be differed and the material in PO will need to monitor for MAP change by M1EP TCode.
    see if you want to consume all the materials for specified accounts other than what you maintaining now, is very much helpful for you but not to maintain your Price. as well if you gonna sale that material how you going to rectify the price is a big problem so there will be a difference in Profit analysis also.
    Try do Confirmatory test in DEV(i think you have done that) still i suggest not to go for B other than Standard one.
    Regards,
    Ninad Kshirsagar

  • Purchase Info Record for Frame work Order

    Hi Friends,
    Do we have Purchase info record for Frame work Order(FO) ?. If yes, Please tell me which info category should i need to select to create a Purchase Info Record.
    Thanks

    Hi
    Is that means, Framework  PO will also use the same standard Purchase info record ?
    Thanks

  • Item category limit (B) in frame work order

    Is it that item category B (limit) is mandetory in frame work order ? In that case it should appear by default. Can we use any other item category with frame work order logically?

    first the question is why do we use frame work order when we already have other document ype avilable
    answer is when ever we need to create a po for a validity period then frame work order is used
    next thing why do we use u=item category B or limit
    answer genrally frame. work order is used as blanket po means for those comodities which r procured very frequently but there monetrey value is very less
    and ur not intersted in doing there godd reciept u will be directly going for invoice reciept

  • Error in Frame Work Order

    Hi SAP Gurus
    While creating a frame work order system is providing an error "Enter free of Charge" and message number ME083. The material in concern is procured against cost center and it is not FOC material.
    I've checked in "Invoice Tab" the selection is there for Inv. receipt and in field selection for "FOF" there is no mandatory
    field selection GR/IR control. Pls help me solve this error.
    Thanks
    Rajesh

    Rajesh,
    See OSS note 167535.
    Symptom
    In Customizing, field "GR/GI indicator" is set as a required field. If you create a purchase order and enter an item on the table control overview screen and subsequently choose 'Enter', the system generates error message ME083 "Please enter free of charge". The cursor is placed on checkbox "Free item" in this case.
    Cause and prerequisites
    Field "Free item" has the same modification group as the GR/IR indicator.
    Regards,
    Nick

  • Digital signature for work order processing

    Hi,
    Have anybody implemented digital signature for work order processing? Can you throw some lights,  what are the steps involved?
    Requirement is when work order reach certain status, like on order release, on partial confirmation, on final confirmation or on Technical completion, digital signature needs to be captured. This is a regulatory requirement.
    I read some threads that explains digital signature can be assigned to plant and order type combination, but i couldn't find this specifc config step, we are using ECC 6.0. Is anything needs to be activated before I can see these configuration steps.
    With ABAP help I was able link digital signature tool to work order, but was wondering if this can be achieved through configuration as mentioned in some of the threads.
    Also I have another requirement, like if you are doing a mass TECO using IW38 transaction, capture digital signature once and the same should be applied for all the selected work orders. Otherwise you have to enter your password as many time as the number of work order selected.
    Jaison

    Hi,
    Some information on operation sign-off available in [help|http://help.sap.com/erp2005_ehp_03/helpdata/EN/da/49d9c433ff4985b2484b7b911123cf/frameset.htm]
    -Paul

  • Can we use contract or Frame work order or any other?

    Dear Experts,
    We want to create a purchase order for our new plant which is being developed.
    We would like to give this contract to a Foreign Vendor, for which final value is fixed. Say, for example 1000 USD. The time limit would be say, for example, 6 months.
    So they will be sending the parts in several consignments. So, also, payment to vendor is will be done at various steps.
    As on when they make ready the parts for dispatch, they can send a list of items, along with prices. 
    Then we want to make a PO to them with reference to main contract, for each of the consignment which they ship.
    Finally we want to track,
    - the total value of the consignment as per this contract, so far...
    - the total payment done to the vendor as per this contract, so far...
    etc...
    Please suggest, which arrangement is correct.
    My contact number is 96111 01459 (Karnataka Mobile).
    Ganapathi

    We had a similar requirement in one of my older implementations. The solution we implemented is as follows:
    PO issued for 1 account assigned line item - Installation of plant - $1000.
    On receipt of details of first consignment, the PO is amended. The items are added in the PO and the value of the first line item is reduced.
    This helps track all the things you want to track.
    Hope this answers,
    Lakshman

  • Issue of invoice with reference to service frame work order

    Hi Gurus,
    i am creating service framework purchase order for a service material. in item detail of service framework po  in condition tab i maintain vat %  condition. then i create service entry sheet with reference to that po and post the entry. when i go to maintain invoice for that material  with ref to po the system shows two line items first line item shows amount and quantity to be invoice and second line item shows no amount or quantity but shows po number and po text  which mentions vat% .
    please tell me what customizing mistake has taken place
    regards

    Hi Suresh
    go to OLMSRV > taxes at individual service level
    then check box against country code.
    Best Regards
    Nishant Shende

  • Error while creating Frame work Purchase order

    Hi Gurus,
    We are trying to implement Frame work order process with following configurations.
    1)Item cat  B for acc assingment Y
    2)Allow  item catg B with acc *** K and Y.(How to config this in SPRO)
    So when i am creating a PO adopted through Purchase Req (account ***  K and item cat B) i am getting error message "Pricing Error :Mandatory condition NAVS is Missing".So how do i configure this pricing process.
    Also when i am creating a Frame work order do i need to select the document type both in PO and PR as frame work order or NB order type will work with these config of Item cat B and acc *** Y?
    When i am creating a PR or PO with doc type frame work order the order unit is automatically populating as "AU" is this something std or do i have to do anything in configuration?
    When i created a PO with ref to PR aith account *** K into the PO and add the item category B the charging information was not maintained so how to maintian this?
    How to maintain the accounting info from PR?
    Also if there is a complete process link releated to config of frame work order that will be great.
    Thanks in Advance.

    Hi
    We are trying to implement Frame work order process with following configurations.
    Item cat B for acc assingment Y
    Create new acct assignment category in IMG -MM - Purchasing -Account Assignment - Maintain Account Assignment Categories (If you are sure of fields to be used then you can directly create Y, if not then copy existing category say K to new one and choose required fields)
    Allow item catg B with acc *** K and Y.(How to config this in SPRO)
    In Purchasing - account assignment - Define Combination of Item Categories/Account Assignment Categories - set combination for Y and B.
    Hope your documement types (PO & PR) allows item category B.
    So when i am creating a PO adopted through Purchase Req (account *** K and item cat B) i am getting error message "Pricing Error :Mandatory condition NAVS is Missing".So how do i configure this pricing process.
    Check the pricing procedure in IMG - Purchasing - Conditions - Define Price Determination Process - Define Calculation Schema - Check for calculation schema - NAVS has been maintained.
    Also when i am creating a Frame work order do i need to select the document type both in PO and PR as frame work order or NB order type will work with these config of Item cat B and acc *** Y?
    You need to choose document types while creating purchase transactions. If that document type doesnt support item category B- then you will get an error message.
    When i am creating a PR or PO with doc type frame work order the order unit is automatically populating as "AU" is this something std or do i have to do anything in configuration?
    For services (D category) we define AU as default unit (IMG - MM - External Services Management - Source Determination and Default Values - for Client/for Purchasing Organizations)
    When i created a PO with ref to PR aith account *** K into the PO and add the item category B the charging information was not maintained so how to maintian this?
    How to maintain the accounting info from PR?
    create Framework requisition and then copy it to a PO.
    Thanks

  • PR Created with reference to Work Order

    Dear Experts,
    We have Work Order Process where Purchase Requisition for Material & Services are created with reference to Work Order . We have chosen the Option (from release), which means PR is created once the Order is released.
    Our requirement is always from release and when the work order released, system to pick the user details of Work Order Creator (not Work Order Release).
    Hope to get the details on the issue.
    Regards,
    Sahu

    Dear Chaitanya,
    When the work Order is released, system creates the Purchase Requisition and in this case PR Creator is the person who has released the Work Order.
    In Work Order log, we know the details  such as, who has created the Work Order and who has released. As SAP standard, Work Order release person is the PR Creator as we have made the setting with From Release.
    Our Requirement is on PR creation, system to take the user details of Work Order Creator. This would help to determine the PR approval process in a better way.
    Regards,
    Sahu

  • Steps to create Work Order

    Hi,
    Could you tell about What is work order creations & steps to create.
    Not sure if below steps are right.
    work order process -->to create work oder---> work request ----> bom ----> routing -->
    Thanks

    Hi,
    you can visit the following links.
    http://oracleappscommunity.com/oracle/blog/365/discrete-job-creation/
    http://oracleappscommunity.com/oracle/blog/38/oracle-work-in-process-overview/
    http://www.youtube.com/watch?v=k6XjVjoLgmo
    http://egeapp.egeseramik.com:8000/pls/prod/fndgfm/fnd_help.get/US/eam/@SelfService1010562
    HTH
    Sanjay

  • Frame work Purchase Order Plus Service entry sheet

    Hello,
    We are having the issue of defining this Purchase order process for Non receivable items i:e items which are non goods receipt like PO for services.When we create a PO with one line item and quantity of 5 and total value of PO is 500 .So after the first invoice the system is closing the PO .System is not looking at the quantity and just closing out the PO .So we have to design a process in which we need to create multiple invoice for a Po(Non GR) also we need to set the tolerence limit for the PO which i thing will be set in OMR6 (PP) and also regardless on quantity the system can create multiple invoices .So what is a good process to drive this.Either Frame work PO or service entry sheet??
    Also is there a way in config we can set tolerence limit for the whole amount of PO .Like in OMR6 we define the upper and lower limit of PO .So if the total value of PO is 1000 ,while creating the invoice it vont allow us to create invoices for more than 1050 .can we set the tolerence for the whole amount of PO ?? Regardless of how many invoices we create.

    Thanks Andra,
    The problem is the multiple invoices is for non goods receipt item so there will be no delivery.At the time of creating a PO the GR is not checked so there will be no delivery .
    Also this setting is for invoices which are comming from Vendors.But if we are genrating the invoices manually it is not blocking those invoices.Also i there is nowhere mentioned in Incomming invoice to set tolerence for incomming invoice.Are you talking about Vendor tolerences?
    Thanks in advance
    Edited by: Metroid01 on May 14, 2009 6:52 PM

  • WIP work in process in PM/CS orders

    Hi everybody,
    Reading the concepts of the use of WIP, is mentioned that it can be applied also in services:
    http://help.sap.com/saphelp_40b/helpdata/es/89/a42c7a461e11d182b50000e829fbfe/content.htm
    I have been working with PM/CS, and the cycle ends with the billing of the sales document that is generated from the service order, but i have problems applying the settelment rule, because i only use one G/L account and Financial area teold me that i must be work with 2 G/L accounts, one for the service in process and the other when the service finishes.
    By the other hand, also they mentioned that i have to determine the sales cost from the settlement of the general order.
    Can somebody help me?

    Dear,
    WIP means work in process material..
    WIP Calculation --- difference between the debits and credits of an order as at the period end when you calculate WIP.. in other words, it is the value of undelivered stock from an order. It is always calcualted in term of currency not in term of quantity.
    When you need to display the value you can use transaction KKAY orKKAQ.
    When you WIP calculation system will calculate the production cost incurred till that time w.r.t. different cost element(direct cost indiredt cost/material and activity) and updated to different accounts.
    Hope clear to you.
    Regards,
    R.Brahmankar