Subcontract GI with account assignment Q

hi guys,
I have a problem in subcon GI to vendor with account assignment Q (project specific).if i am raising a PO with item category L and with out any account assignment, i this case i am able to do GI in ME2O.
But, with account assignment Q, It is not appearing In ME2O.
thanks in advance
vikram

You cannot do hat because subcontacting itself is a special stock(when you do GI), hence you can have two specila stock indicator for the same stock( Q and subcontracting)
If you want to send it to vendor then you need to release the stock from Q stock to unresticted then go GI-541(o),, then if you Do GI then system will transfer from UN stock to specila stock i.e. subcontactor stock)
please come back if you need furthur information

Similar Messages

  • Subcontracting PO for account assignment M & E

    Need Urgent help....
    Dear Gurus,
    Require your expertise for the following senario:-
    While running MRP for MTO sale order , The planned orders created with account assignment category M.
    We do have one Planned order for Subcontracting as well and is created with Account assignment category M and Item Category L .
    The combination of M & L is alreday defined in SPRO .
    Now while creating PO with M & L for subcontracting , its creates subcontracting PO for sales order reference .
    After creating PO , there is no requirements gte generated for trasferring componenets to sub-contacting Vendor , as the components also shows special stock indicator E,
    And even after transferring Componenets to Vendor manually through MType- 541, while doinh GR against PO ....the Consumption of components is shown with 543-E , and not 543-O.....and which in turn...doesn't really complete the subcontracting cycle......
    So....Combination of M & L is possible or not and if yes what settings need to be done and where ?
    Will appreciate your advise
    Thanks & Regards
    Ashwin Jain

    Dear Baskaran,
    Thanks a lot for your update ...The senario is like this :-
    The sales order is for Finish goods as MTO and under this Finish good in BOM we have one Semi Finish item which we are getting processed through subcontracting.
    And under the semi finish we have one raw material which is acting as component for Semi finish item.
    The Account assignment category is "M" and Item Category is "L"
    The PO for Semifinish Subcontracting is having reference of sales Order and the components for this semi finish is also having the reference of same sales order .
    Now while doing GR components gets consumed from  sale order stock from our own stock ....and not from Stcok provided to vendor....Actually after creating PO with M & L it doesn't creates any requirements for Transferring components to Subcontracting Vendor ....and in this case how can we trace the Subcontracting Process.
    As you said threre is no need to send components to Subcontracting Vendor if PO & Components are having the same Sales order no reference  ....Need more clarification on this and then in this case how we will trace the cycle as we r not sending any componenets to Vendor through system but in Actual we need to send the componenets to Vendor to convert them in to Semi Finish Goods .....
    Please advise at your earliest ...
    Regards
    Ashwin Jain

  • Error while creating  a PO with Account assignment

    HI MM Gurus
    In our case, we need to create the STO for account assignment cat `Unknown`.
    In SPRO I maintained combination of account assign cat and item cat.
    Now, while creating  a PO with Account assign U we get Error message -  ME069 :Unknown account assignment not defined for use here.
    Please advise how to resolve this issue.

    Hi
    When you are posting actuals, you need to give true account assignment object. With U (unknown), system cannot identify which account to be posted. Change account assignment in PO to another.
    In standard SAP Unknown account assignment is not allowed in PO's. Only exception is Blanket PO.
    Unknown is allowed only in PR and Blanket PO.
    The reason is logically you are releasing the PO to the external vendor or Plant in this case you must know the account assignment.
    Regards,
    Ninad Kshirsagar

  • Exchange rate problem between GR&IR for PO with account assignment category

    ear SAP experts.
    We have used expense puchase order through account assignment category.
    the cost object include cost center,sale order,order.because we don’t use Fixed assets module in SAP,when purchase fixed assets,we also use account assignment category but no need to fill assets number(Not use account assignment category A).
    the processing in current system when there is exchange rate difference between GR&IR  as follows.
    purchase order Currency :USD  company code currency:HKD
    example 1-- when something purchased into expense account,
    Good receipt  (1USD=7.75HKD)
    Dr :expense account  100USD    775HKD
      Cr: GR/IR        100USD    775HKD
    Invoice receipt
    Dr : GR/IR         100USD    775HKD
        Expense account            25HKD
    CR: Vendor        100USD    800HKD
    Example 2-- when something purchased into Fixed assets account,
    purchase order :USD  company code currency:HKD
    Good receipt on Oct .01. 2007  (1USD=7.75HKD)
    Dr :Fixed assets account  100USD    775HKD
      Cr: GR/IR           100USD    775HKD
    Invoice receipt on Dec.01.2007  (1USD= 8HKD)
    Dr: GR/IR              100USD     775HKD
       Fixed assets account                25HKD
      Cr: Vendor            100USD     780HKD     
    The fixed assets is depreciated from Nov,2007.
    There is one problem that after the fixed assets is depreciated, the value for the fixed assets is added , the finance clerk have to adjust the added value from fixed assets account to Exchange Difference-Gain/Loss account by manual.
    Our problem is
    How to configure in order to make  the exchage rate difference into Exchange Difference-Gain/Loss account for purchase order with account assignment category,not the original assigned account in purchase order item.
    Many thanks
    Fanny

    Hi Fanny
    Even though the question is bit unclear, I guess you are looking for the T-Code OBYC. Use transaction key KDM for configuring the exchange gain/loss
    S Jayaram

  • PO with account assignment category F

    Hi Gurus,
    For PO with account assignment category F, the system is creating aaccounting documents during GRN for some POs & for some pOs it is not . What could be the reason.
    Regards,
    Kumar

    Hi SAPMM6,
    Check details of account category refernce 'F' whether tick is there for GR Valuated.
    Also when you are creating PO with multi-account assignment then also GR is non-valuated as per SAP standerds.
    Also check the both POs for material code and there valuation classes.
    Hope your problem gets resoled.
    Regards,
    Gitesh

  • Po with account assignment cost centre

    dear friends,
    When creating PO with account assignment cost centre, system should default GL account (i.e G/L will be picked automatically instead of entering manually.
    How this can be customized?
    regards, thanks

    The following configs are required.
    1. SPRO -> MM -> Purchase -> Material Master -> Entry aids -> here you maintain all relevant material groups, corresponding valuation class and Purchasing valuation key
    2. Then in OKB9, you will maintain company code, cost element, and cost center
    3. THen in OBYC, Valuation group code, valuation class and GL account.
    With the above settings, the system will automatically detemine the GL account.
    Thanks and warm regards,
    Jagadeesh

  • PO with account assignment Category M

    Hi Friends,
    In an intercompany stock transer scenario for a PO with account assignment category M, can the receiving plant receive the goods before the supplyig plant issues it? In my case it's happening only for POs with account assignment category M, so I wanted to consult you all if this is possible per standard SAP functionality.
    Thanks for your help.
    Rana

    Hi
    Yes this is  standard functionality only. and this is not an intercompany procurement.
    This is something like a Individual purchase order process. Using Item category TAB in the sales order.
    In this process Goods receipt is done before you perform the goods issue to the customer.
    In an inter compnay PO process the process starts with creation of a PO and not SO. where as you are creating a SO beofre the PO, and using the SO as an account assignment object.
    Thanks & Regards
    Kishore

  • PO with Account Assignment P and NON Valuated Material

    Hi ,
    As per my undersatnding if I create a PO with Account Assignment "P" , system consumes it immediately and stock doesn;t get updated in any storage location.
    But
    If I use Account Assignment "P" with "NON valuated" stock , system is asking for Slocation at the time of MIGO and also updates Qtys in Storage location , although cost is being booked to consumption account.
    Could u pls help to understand the logic for this ?
    Regards
    Shrey

    Hi,
    PLease read this para from SAP help .. it is useful to undestand your scenarion
    Goods Receipt of Non-Valuated Materials  
    Use
    If the stock of a given material is only managed on a quantity basis, an account assignment must be defined in the purchase order. However, this account assignment does not result in the goods receipt being posted to consumption/usage. Instead, it results in the costs being debited to the account assignment object.
    The goods receipt is posted to the warehouse stock, thus increasing the unrestricted-use stock of the material.
    *It is not possible to post goods receipts of non-valuated materials directly into consumption/usage. You have to post the goods receipt into the warehouse first and then enter a goods issue.*
    Regards
    Krishna

  • PO with account assignment category K and use two cost center

    Dear Experts
    When I create a PO with account assignment category K and use two cost center in the account assigment tab of PO with the same GL or with different GL in the both line item, The FI document does not get posted.
    Any input on this please.
    Regards
    Paul

    Hi,
    Check in the PO document - Item level - Delivery tab
    There are two indicators
    1. Good receipt
    2. GR non-valuated.
    If you are giving only one cost centre, only GR check box active and  GR non-valuated check box is in-active. That's why System creating FI document during GR.
    If you are giving two cost centres, Both GR check box and  GR non-valuated check box are active. That's why System is not creating any FI documents during GR.
    Regards
    Ravi

  • How to remove a PO with account assignment K from MD04

    Hi guys
    I have create a Purchase Order in ME21N with account assignment K and removed the Goods receipt mark in delivery tab.
    Will this PO be removed from MD04 and when?

    Hi
    My requirement is the following: My company have some suppliers which holds inventory for us. My company controlled that with contracts in SAP.
    Som parts of this inventory must be scrapped if demand changes. Therefore we need to create a PO, where my compagny buy the materiels. We will never use these materials so the supplier can just scappe them at his site and there we unmark the Goods receipt mark and use account asignment K.
    But the buyer will see the PO in MD04 and this create confusion, so I would like to be able to remove this from MD04.
    Thanks!
    Sune

  • Error while creating purchase order with account assignment category "A"

    Dear All,
                      At the time of creating purchase order with account assignment category A - Asset its throwing error as " GL Account 123400 can not be used"
    how to resolve this  issue"
    Edited by: Matt on Sep 16, 2010 10:09 AM - removed bold tags

    HI,
    Assign all assets GL to Asset Class
    spro --> financial accounting new -->assets accounting --> assets accounting (lean Implementation) --> organization structures --> Assign GL
    Hope Help U !
    Regards,
    Pardeep Malik

  • Creation of PO with account assignment:Q

    Hi,
    During creation of purchase order with account assignment category: Q, consumption GL account is getting triggered instead of Project Stock GL Account. What could be the reason for this?
    Regards,
    Srinivas.

    Check what account modification key is assigned to account assignment category 'Q'.
    T-code: OLME
    Purchasing --> Account Assignment --> Maintain Account Assignment Category
    Select the Account Assignment Category 'Q' and click on the details button.
    Check the Consumption Posting (P) , Account Modification key (VBR)  and the Special Stock field (Q).
    Depending upon the Account Modification Key, System picks the G/L from the OBYC (GBB) Setting (Tcode - OBYC).
    Regards,
    S Anand

  • Default a gl account in account in a purchase order with account assignment

    Hi all
    I need default a gl account in account in a purchase order with account assignment P. can somebody help me. They have used a gl account which is not correct.
    Thanks

    Hi,
    Please refer posted tread in the forum
    default G/L account for purchasing documents
    Regards,
    Santosh

  • Check while creating PR with account assignment K

    Hi Gurus,
    Can I put a check while creating PRs for account assignment category K, that only statistical order number range is allowed.
    In other words, user should not be allowed to put any internal order other than statistical order in PR, while creating it with account assignment category K..
    Thanks in Advance,
    Vikash

    Hi,
    You can check on business transaction RMBA - it's the purchase requisition. Set it to prerequisites and for the validation select the order type (it's better than a number range - I believe you use different order types for real/statistical I/O) from AUFK (you will see this structure as available, when creating a validation). If you do use the same order type, then check on I/O itself COBL-AUFNR.
    Regards,
    Eli

  • Budgeting thru Internal Order with Account assignment category 'A'

    Dear All
    I want Budgeting thru Internal Order with Account assignment category 'A'
    i.e
    Created Assets with Tcode As01
    Created Internal Order and assigned budget amount to IO with Tcode KO01 and KO22
    Created Purhcase Requisition with Account assignment catg as 'A' i.e asstes. Also given Internal Order No and Asset code in PR.
    Releases PR with ME54N
    Created Purchase Order with Account assignemnt catg as 'A' i.e asstes.  In Purchase Order it displays Internal Order No. and Asset code which i have given in PR in Account assignemnt tab on Item level
    Released Purchase Order.
    Now i am checking budget detail in Tcode : S_ALR_87013019  -> List: Budget/Actual/Commitments ,  Here it gives message , "No line item were selected " in Commitment line items.
    Actually  my requirement is , i want budgeting thru internal order and want to use Account assignment category as 'A' (Assets) in PR and PO.
    Why it's not showing detail in report S_ALR_87013019  .
    What is solution for my requirement. Is it possible with some configuration or by other options.
    Thanx & Regards
    Swati Shah

    Hi Swati,
    You can do this in Asset Accounting. By standard MIGO Posting Date is taken as capitalization date for asset. You can configure to make it 'Document Date'.
    So, whenever user is posting thru MIGO, he will have better control on deciding capitalization date by inputting appropriate date in Document Date Field in MIGO.
    Check this thread..
    Re: Depreciation start date for asset thru MIGO
    Regards,
    Sayujya