Subcontracting and PM orders

Hello,
I have activated business function LOG_EAM_ROTSUB for subcontracting.
When trying to go through process where returned material is different then the one sent to subcontractor
Iu2019m getting following error message when trying to convert PR into P.O. : Material number 10000766 does not equal material number 10000170 of order item
Message no. AD_SUBCON013
In the maintenance order I have two materials assigned into subcontracting operation:
Material 10000170 with MPI Rework material to subcontractor
Material 10000766 with MPI Rework material from subcontractor (with negative value)
Do you have any suggestion what causes above mentioned error message?
Many thanks for your clues
Grzegorz

Hello Raj,
There is one thing which makes me wonderu2026
Do I understand you well? Do you mean that material with changed material number (with MPI u2013 u2018Xu2019) should have Item Category u2013 u2018Nu2019 u2013 why you are saying so?
When I try to maintain non stock material for subcontracted operation Iu2019m getting following: Item category N is not allowed for subcontracting Message no. AD_SUBCON097
My understanding isu2026 if subcontractor for some reason sends us material with changed material number then mentioned material with Material Provision Indicator u2013 u2018Xu2019 needs to be assigned into subcontracted operation in advance.
Also material which is about to be repair needs to be marked with indicator u2018Su2019.
Automatically created PReqs and then P.O. will have an item with material marked as X.
Then by calling MB1B we transfer material (with indicator S) which needs to be repair to subcontractor (movement type 541). When making GR via MB01 we receive given by vendor material with indicator X (movement type 101)
Please point out if my understanding is wrong.
Many thanks
Grzegorz

Similar Messages

  • Subcontracting scenario(Sale Order wise)

    Hi all
    We have requirement from our client to map subcontracting process Sale Order Line Item wise,
    I.e- instead of 541 we will use 311E and send components to vendor (which will create seperate storage location for each vendor).
    We will receive the Finished Material through 101E,we tested this process in Test client & found OK.
    Is This process Ok from accounting point of view.
    Thanks In advance
    Sandeep

    Hi
    I think it is not the right way...
    where you will book the Vendor service amount....
    also if you are sending the same material and getting back the same material....it may be OK....
    But for eg) you are sending product A and B  and assemble at SC-Place....getting back the FG as Product C....in this case it will not work out....
    Regards
    S.Baskaran

  • PPPI PI sheet to trigger HUM goods receipt and PI order confirmation

    Hi gurus,
    We're running into a problem when setting up our PI sheets.
    We're using Handling Unit Management for our finished products and would like to use the PI sheet to post both the goods receipt of handling units and the order confirmation. For now let's assume all activities and ingredients are backflushed.
    For the HUM section we've created a function module that combines transactions COWBPACK and COWBHUWE. When called by itself it works like a dream.
    For the order confirnation we've successfully used standard SAP message category PI13, but also only when called by itself.
    The problem is when we combine them:
    When combining the Z function module to contain both COCI_CONFIRM_ORDER (from the PI13 message) and our ZHUM function modules, it appears that the COCI_CONFIRM_ORDER blocks the process order so the COWBHUWE part of our function module cannot be executed. This has something to do with the way SAP handles the "commit" in the function module.
    Now, I noticed it's possible to include more than one message category in customizing for the PI sheet category (when configuring through the wizard).  The idea is then to process the messages with a background job, filtering through the message category so we do the HUM part immediately and the confirmation only at the end of the shift so they don't block each other.
    However, when I do this still only one message category is created after processing the PI sheet.
    Do you know how to create messages with multiple message categories from the same PI sheet? Or if that's not the way, is there a better way to set up this process?
    Sorry for the long text, just wanted to be precise.  Any help is, as usual, greatly appreciated.
    Kind regards,
    Elt

    Hi
    1. What is quantity of the waste material you get as by product? Do not you wan it to be handled as scrap? What is the %age of scrap you have defined in the BOM for the material? You wll have some data regarding this. Or else how do you arrive at decission that after subcontract processes the waste you are paying him, Is it umpsum basis or material quantity basis. The best way is to have a Subcontract PO, but for that even though you do not weigh the watse quanity you must be having so historical data for the waste quantity generated and the conversion of the sane to other SFG , definitely you can arrive that on a pro_rata basis. Have a Code for the waste mateial. Release Subcontract PO for SFG which is what you get back, and issue the components( waste) to subcontractor.
    Please remember your PO intially will be for Provisional quantity if you are unable to reach a fixed quantity. Amend the PO before GR as per the actual quanity for which you wish to pay the vendor.
    For the waste quanity stock updation you use 262(w/o refe to Prd order) after the FG is confirmed.
    Material price updation happens cirrectly in this process.
    2. You can pay the vendor as you wish by by this process but what about the price updation for the ordered material SFG. When you can receive by product in separate Txn againt FG then why can not you follow the proces no. 1?
    3. I would not liketo suggest 3 rd option as that becomes much comlicated for a simple operation.
    Best Regards

  • Tell me the link between Purchase Requisition and Sales Order Number

    tell me the link between Purchase Requisition(MEREQ_TOPLINE-BANFN_EXT) and Sales Order Number(COBL-KDAUF)

    Hi Puja,
    If you have created sales order  for matrial which has both procurement type,after MRP run you will get
    planned order.This planned order you can convert to purchase requisition for external procurement or
    subcontracting.
    You will find sales order number in details of purchase requisition ( ME52N) in Account assignment tab.
    Hope this help you.
    Regards,
    Raja

  • Diference between STO and Shipment order?

    Hi All ,
    There are two plants , one is manufacturing and other is sales .  In sales plant sales order is created and after MRP run Purchase requisition is created(for getting materisl from production plant) . In me59 we convert this Preq to shipment order.
    1)Can oyu please tell me whant is diference between STO and shipment order?
    2) Can you tell me what is the configuration to avoid creation of shipment order and system will only create the STO from Preq after executing Me59?
    Thanks
    Rohit Chavan

    Hi Chavan,
    Starting with "Shipmnt Order" definition => (from SAP Help):
       An order to a transportation service provider to ship goods from a shipper to a single consignee with agreed terms and conditions. The corresponding confirmation from the transportation service provider is also part of the business object.
       You can use this business object to subcontract the transportation of goods from a shipper to a single consignee if you cannot fulfill a shipment request yourself or if you regularly subcontract transportation services.
       You can also use this business object in the process of transportation service provider selection and tendering. The aim of both processes is to assign a suitable transportation service provider (TSP) to a shipment order.
    http://help.sap.com/saphelp_tm60/helpdata/en/66/dda98bb6b64c30b925f031bb0a2023/content.htm
    STO is just Stock Transport Order => functionality to move stock from one plant to another plant in two steps( inclidung GI in the sending plant and GR in the receiving plant).
    Usuall documnt flow in the STO process => PO(UB or NB order type), delivery, GI -> GR (done via migo for example).
    I believe that you can avoid cration of the Shipmnt order via correct selection on ME59 screen. Just something what is characteristic for STO and not for Shipmnt Orders.
    Best Regadrs,
    Tomek.

  • Using Subcontracting with Sales Order Stock

    Hi SDN Network,
    We use the made to order setup so run MRP with the Sales Order as the basis of the demand. After that, we avail the services of a subcontractor to assemble the finished goods although we supply the subassembly and raw matls.
    The PR generated during the MRP run has an account assignment of either M or E depending on the Item Cat in the sales order. From that PR, we create a subcon PO (item cat L). Problem is the PO generated is not showing up on the ME2O transaction. Does this mean that POs whose GR goes directly to Sales Order stock are not allowed in the system? I am able to post
    We would still want to retain the 'reservation' of the materials using the Sales Order stock. But does it follow that you cannot use Sales Order Stock with subcontracting?
    Did I miss out anything in the config? Is there another way to do this?
    Thanks in advance!

    Hi
    Subcontracting issue to subcontractor (special stock O) and sales order stock (special stock E) both have special stock indicators and hence not possible.
    The process can be done as explained in the link below:
    http://help.sap.com/saphelp_erp2005vp/helpdata/en/4d/2b90b043ad11d189410000e829fbbd/frameset.htm
    Best regards
    Ramki

  • Modeling dummy product and planned orders

    Hi SAP Gurus,
    I have requirement where i need to model particular business requirements on subcontracting and the same is resulting in need of modeling of dummy product and dummy planned orders. Please share your inputs on what would be impact of dummy product and dummy planned orders in ECC. and also how to make sure that it does cause any issues in costing.
    I am modeling subcontracting requirement and i need to create following master data.
    All the below products are at plant P.
    P has the components as Q_D
    Q_D has the components as Q
    Q has the components as R
    Where Q_D is the dummy product produced at plant P.
    P and Q are subcontracted items to the vendor V.
    P is the finished good, Q and Q_D are Semi finished goods, R is raw material.
    When we plan we are creating Purchase orders for P and Q. And Q_D is made inhouse and we need to create planned order for it. how do we handle the planned orders created for Q_D. we dont want them to convert to production orders. we want a way to clear off these dummy planned orders once we close the POs of P and Q.
    Please advise.
    Thanks.
    Jagadeesh

    Hi senthil,
    Check if the forecast date is beyond PPDS horizon.
    Also in product master on PPDS tab, you should maintain 4 in PP Planning procedure.
    Bye.
    Nitin

  • Subcontracting with slaes order

    hi i want to know
    how can we do the subcontracting with sales order
    i got a process using 311 e movemnt when i search on SDN
    plz let me know if this process is correct how can i  have subcon challan
    Subcontracting scenario(Sale Order wise)
    Subcontracting For Sales order.
    Subcontract Account assigned PO
    how can i create storage loc as vendor
    plz help
    regards
    raj

    Hi,
    Subcontracting for Project Stock: -
    Purpose: - Subcontracting is also possible in conjunction with Project stocks. The subcontracting orders are account-assigned to a Project. Thus, the components are not transferred (using a transfer posting) to the "stock of material provided to vendor" but are directly withdrawn from the Project stock the time of the goods receipt. The material manufactured is also posted to the Project stock.
    The cost of subcontracting is then debited to the Project.
    Since the components are not transferred to the "stock of material provided to vendor", it is recommended that you use a transfer posting to transfer the provided components to a new storage location (for example, 9999). This enables you to obtain an overview of those stocks that are physically located at the subcontractor. This information is particularly important when you carry out a physical inventory of the Project stocks.
    Features: -
    Withdrawal from Stock of Mat. Provided for Project: -
    For components that are managed in Project stock, you can define whether the components are to be withdrawn directly from each Project or from the stock of material provided to vendor. You manage this via the dependent requirements indicator for individual customer requirements and collective requirements (MARC-SBDKZ).
    You can maintain this indicator in the following places:
    In the MRP view of the material master record (MRP 4)
    In the explosion types for the BOM item (in Customizing for Production in the step Basic Data -> Bill of Material -> Item Data -> Define explosion types)
    Configuring the explosion types has priority over the configuration in Inventory Management.
    If the indicator is set at Collective requirements only (2), the materials are withdrawn from the stock of material provided to vendor. If this indicator is set any other way, the system withdraws materials from Project stock.
    Regarding Subcontracting Challan: -
    Go to OMJJ, select the field "movement type" and press enter
    Enter movement type "311" and double click on "Field selection (Enjoy)" under Dialog Structure on left side.
    here "New Entries" and add field "LIFNR" (Vendor)
    Now in MIGO, at the time of transfer posting of components using movement type "311 Q", specify the vendor code of the Subcontracting PO (i.e. Subcontractor)
    Now create Subcontracting Challan in J1IF01 for material document of 311 Q movement type.
    Also check in SPRO > Logistics - General > Tax on Goods Movements > India > Business Transactions > Subcontracting > Maintain Movement Type Groups > here for Movement Type Group "0001", Movement Type "311 Q" should be maintained.
    Then do GR against PO and refer the Subcontracting Challan here.
    And then do reconciliation in J1IFQ for the GR Document against Subcontracting Challan.
    Also check in SPRO > Logistics - General > Tax on Goods Movements > India > Business Transactions > Subcontracting > Maintain Movement Type Groups > here for Movement Type Group "0002", Movement Type "543 Q" should be maintained.
    Follow the below mentioned process;
    Process Steps: -
    1. OX09 - Create Storage Location as "9999" for Subcontractor Location
    2. MB1B - Do Transfer Posting of material from RM Warehouse to this Storage Location via movement type "311 Q" (Instead of doing 541)
    3. Now go to J1IF01 - here use material document of movement type "311 Q" and create Subcontracting challan. (If required)
    Prerequisite: - In SPRO > Logistics - General > Tax on Goods Movements > India > Business Transactions > Subcontracting > Maintain Movement Type Groups > Here for Movement Type Group "0001" (For issues), maintain movement type "311 Q" also along with 541.
    Rest all, refer subcontracting challan during GR and then reconciliation and completion, etc... will be same as usual.
    Note: - At the time of GR, consume components from storage location "9999" (for 543 movement type)

  • Need help to find out link between process order and purchase order.

    Hi All,
    Need help to find out link between process order and purchase order.
    We have purchase order, we can find out associated process order in MD09 (No Purchase Requisition found in Purchase order). When I tired to replicate this scenario with same material in system but not able to do.
    Please suggest me what needs to check to get purchase order link to process order.. (this is not subcontracting )
    Edited by: SAP PQ on Sep 26, 2011 5:24 PM
    Thanks,
    SAP PQ
    Edited by: SAP PQ on Sep 26, 2011 5:24 PM

    MD09 is pegging. In SAP pegging is dynamic, meaning that there's no fixed link between purchase order and process order in your case.
    This is why you did not get the same result when you tried again later.
    Such a link can exist only if you do direct procurement for the order.

  • Serial Number in subcontract or refurbishment order

    I am trying to get more information on using the same serial number in a subcontract or refurbishment order using split valuation. We  have a component we want to send out for refurbishment  and it is split valued CORE and REPAIRED. We send the Vendor the component with a valuation type CORE and the s/n X. The vendor does his thing and returns it as REPAIRED with same s/n X Since it is in reality the same part. Currently SAP will NOT let you receive the part back in with a different valuation type, but same s/n. If Iu2019m remembering correctly this was supposed to be addressed in ECC 6.0 enhancement pack 4, but the documentation Iu2019m finding doesnu2019t address this at all. Iu2019ve also been looking on line, OSS notes etc. to no avail.
    Any advice?

    Hi ,
    Yes you can do it is possible during purchase order creation for the components level serial number
    gets generated .
    If you have Product group and for members you can have serial number
    create number range in serail number object ( eacc/seri ) and assign in the Table of serail number you are
    linking  so whenever PO is generated for the components serail number is generated
    balaji
    Edited by: balaji on Sep 26, 2008 2:56 PM

  • Subcontracting and inhouse

    Dear sir
    this is mto scenaoir. first we produce fabricated structure(box) like  electrical  panel . after manufacturing the box, i  have to do painting  and final box manufactured i will started  assembly with different components . and finally it become  say a panel.
    i have only simple bom. and only one final operation in routing . first  i will issue the material to order , when complete the finished product , i will do conformation , and goods receipt for that order.
    if iwant to give subcontracting forcomplite  fabricated structure like box i will assigned the exteranal operation , the pr will creates for subcontracting operation , i will provide material to vendor by mb51 for manicuring box. when i do gr for sub contracting
    this box will be posted against order. this is ok
    but i will give 50% order qty to subcontracting and remaing 50% i will manufacure in house. for box manufacture.for inhouse
    manufactuoreed fabricated box i will send for painting to  subcontracting vendor for painting operation . for this i will send the box and paint .
    pl tell me how to map in the system.
    regards
    Baswaraj

    Hi,
    First I suggest that for the entire subcontracting you use the other business process, with purchasing and item category "L" for subcontracting in the purchase order.
    Then you can use the quota arrangement definition to split 50% of the orders to that, and the other 50% to inhouse production. If you have an external operation in the inhouse production routing it's OK, it is still considered as an overall internal production process, since it is done within the framework of a production order.
    Regards,
    Mario

  • Open and closed order reports

    Hi,
    Please anyone tell me how we can find which orders are open order & which are closed orders??
    Also the difference in the recognition between WIP Sales order and Closed Sales order??
    Regards,
    Roma

    Hey,
    I know about open and sales order. Actually i have to make an open order report, a WIP order report and a closed order report. And i know we can make these reports from the following:-
    CHARACTERISTICS: Bill-to-party,Ship to party, sold to party, Company code,Plant,Sales organization ,Sales Office,Material Number,Deliver block
    KEY FIGURES:orders,Open Orders,Order items,Subtotal,Net weight, open Quantity,Gross weight
    But i dont know which characteristics and key figures we will use for open order report, which one are for WIP order report and also for closed order report.
    Please do tell me how can i make these three reports.
    Regards,
    Roma

  • Link between Delivery and Sales Order Schedule Line

    Hi Gurus,
    I have a requirement in which i need to display quantity and amount at schedule line level and also the delivery and delivery item for each schedule line.
    For example, if there is a sales order O1 and item 10 for which we have 3 schedule lines and 3 deliveries as well say D1, D2 and D3.
    Report should be something like this
    Sales Order    Item   Schedule Line    Delivery    Del Item   Confirmed Order Qty
    O1                 10      1                       D1           10            5
    O1                 10       2                      D2            10            5
    O1                 10       3                      D3            10            4
    How can i determine that a particular delivery corresponds to which schedule line of that saler order-item?
    We have the link between delivery and sales order but is there any way that we can get the link of delivery at schedule line level?
    Please help.
    Regards,
    Gaurav

    Hi,
    I suppose you must check with SD functional consultant and the post should also be in the logistics SD forum and not BI. But I suppose there is know specific link between the schedule line of SO to the Delivery. It is more like a bucket flow for ex.
    Sale order   Item    Schedule line  qty
    SO1            Item1     Sch1            10
    SO2            Item1      Sch2           10
    Delivery Item QTy
    DO1       IT1   15
    DO2       IT1    5
    In this case qty 15 is distributed over both SO1 and SO2, and SO2 ITem1 Sch2 has link to both the DOs
    So I am not sure if you can establish a one to one link, please check with your SD consultants.
    Regards,
    Ashwin G

  • Purchase order and sales order table name

    hi al,
    i want to know purchase order and sales order table name in abap.
    thanks
    varun
    Moderator message: please do some own research, this should not take too long.
    Edited by: Thomas Zloch on Jan 27, 2012

    Hi Sunrag......
    If your PO is linked with SO. Then you can fetch customer name easily by FMS in PO.
    From there you ca gte the Customer Name into your PLD and it wont hang also.....
    Regards,
    Rahul

  • Production order and planned order qty should not consider in MRP

    Dear All,
    i do not want to consider the previous month production order qty and plenned order qty (Nothing but WIP qty) in the current momth MRP, but the stock has to consider in MRP.
    Example,
    Before MRP,
    material : XYZ
    Stock : 1000
    Prod Qty : 500 for 02.04.2008
    PIR Qty : 2000 for 02.05.2008
    After MRP, the requirement should be as below said,
    material : XYZ
    Stock : 1000
    Prod Qty : 500 for 02.04.2008
    PIR Qty : 2000 for 02.05.2008
    Pld OrdQty : 1000 for 02.05.2008
    For the above requirement ,i have done settings in the availabilty check like , for include planned order and include production order are "DO NOT TAKE IN ACCOUNT".
    Even then also the planned order qty is generating for the "500" only.
    please give the solution for the above said requirement.
    thanx in advance
    Regards
    Srinivas

    hi
    MRP will always consider the prod order qty while doing nert req calculation.One thing u can do is TECo the prod orders and un MRP then it wont consider prod order qty.
    The Availability check will check whether the components r avalaible or not based on ur scope of check
    Reward points if useful
    Amit

Maybe you are looking for

  • Setting Date value in stored procedure via jdbc

    I have a stored procedure where one of the parameters is a date value. I am trying to invoke this through jdbc with a CallableStatement. I am creating a java.sql.Date object and passing that to setDate() on the CallableStatement. When I execute the s

  • Dispatch Instructions for Direct Supply from Vendor to Customer.

    Dear Experts, Our Company is Project Industry. We have implmented SAP ECC 6.0 in 2008 with SD, FI, MM, PP, QM, PS, DMS modules. In our case 70% Deliveries to customer are from direct dispatch from our vendor to Client. Steps are as follows. 1. Buyer

  • Message split without BPM?

    Can we do correlation (message merge) without bpm. I mean Is there any adwanced service pack which support this,so that we can avoid bpm?

  • Settings problem of range of 2nd gen. not as good as 1st gen.?

    My original Aiport Express stopped working this week, just went dead, replaced it with a new 2nd gen. one .... Wheras the original extended the signal through the house particularly to the living room, with this one, there is no signal at all. It's j

  • How do I transfer files from my PC to my mac on an external hard drive?

    I have an HP external hard drive that I have put all of my files from my PC on. I am trying to move them onto my Mac, but I have absolutely no idea what to do. As a warning, I am kind of computer illiterate.