Subcontracting within company code

Hi
We have scenario of subcontracting as follows
We have two plants in SAP one is  Manufacturing Plant (1001) &
other is Power Plant (1009)
Plant 1001 is having excise registration & 1009 is not excise
registered. We are supplying coal which is excisable from 1001 to
1009 as a raw material & receiving power from Power plant as finish
product. But in SAP how can we achieve this. Following are some doubt
regarding the same
1. Subcontracting from one plant to another plant is not accepting
in PO
(Massage is coming: Subcontracting as stock transfer within a company
code not possible
Message no. ME645)
2. How we can send material from one plant to another plant fro
subcontracting
3. What will be the behavior of inventory of COAL in power plant
in case of Valuation & Costing of Power?
4. How the costing of Power will be done
5. If we create Power plant as different vendor rather than plant
vendor , how power plant will receive material & effect of the same
in inventory & costing of power
6. Also business want to create subcontracting challan & other
legal documents
Is there in other Work around solution for the same
Please provide suggestions on the same
Regards

Hi Advait,
I have the following to share regarding your scenerio.
1] Create the power plant as Jobwork Vendor.
2] You will supply the coal to this Jobwork vendor against 57f4 document(Jobwork basis).
You can also use MoT 541 and 542
3] Power plant(Jobwork vendor) will receive this coal as a Non-Valuated materail. He will receive the coal on a UNBW material code.
4] Power plant can easily consume this coal against the power generated.
5] Definitely there will be a mechanism with you to measure how many power you have received from the power plant.
6] Power plant will charge only labour charges against the power provided to your plant as he has already consumed your coal to generate this power.
7] In this way the coal at your end will be valuated for you but simultaneously non-valued for power plant.
I think this is what your management requires.
Hope this will help you.
Best Regards,
Amol

Similar Messages

  • Subcontracting cross company code

    Hello,
    I didn´t find a standard way to handle the following scenario:
    Plant A creates an intercompany purchasing document item category L for subcontracting with header material S and supplier 1 which is intercompany for Plant B (another company code).
    Plant A provides material P to Plant B with transaction ME2O and delivery.
    The goods issue with reference to delivery creates special stock material provided to supplier on plant level for plant level (quantity and value).
    Works all fine so far -->standard subcontracting procedure
    My Question:
    How should Plant B post goods receipt:
    Background:
    The goods receipt would lead to doubling material quantity (stock available in Plant A and in Plant B) and double valuation.
    Plant B needs to create production order to produce S and P as component.
    Any Ideas ?
    Your help is very apreciated
    Cheers
    Thomas

    Hi,
    But if the two plants are in different company codes then the STO can use Billing and profits etc. so that the revenue can be managed as you need it.
    By using STOs with billing, the system treats the supplying plant as a vendor and the reciving plant as a customer anyway. But the whole process is much easier because you treat them as stock transafers and yet get the benefit of the profit / loss and billing functions.
    You rellay do need to read up on the use of STOs cross-company (too much detail for this thread). There may even be some help on the first thread on this forum.
    I think that you will be pleasantly surprised at the benefits to the whole process if you explore this option fully. The STOs are "easy" to maintain, the movements and consumptions etc. also follow basic real-world logic and the accounting is DEFINITELY as the auditors would want to see it.
    If your plants were set up incorrectly and were within the same company code, then these options would not be available to you (because the SAP system does not allow you to break financial rules and cause audit problems, you cannot have a profit from a transfer within the same legal entity). But is your case you have got the structure correct (many people don't) and so I would recommend that you exploit this standard SAP functionality to your benefit.
    Short or long-term, you will realise the benefits, go down the suncontracting route for this solution and your users will have messy functions and will not have the kind of reporting and exnquiries that they will definitely need.
    It is up to you, subcontracting is not "wrong" as such and you could get it to work, but it will certainly not be the best solution (by far)
    Steve B

  • Error in Return STO Process(Plant to Plant within company code)

    Hi All,
    I am doing the return STO Process(Plant to Plant within same company code) .
    Scenario:
    STO from Plant 1300 to 1400
    STO Process: ME21N->VL10B->PGI-> VF01(Proforma)->MIGO
    Return STO from Plant 1400 to 1300
    STO Return Process: ME21N(item with return indicator)->MB01(MT 101 w.r.t Return STO PO)->VL10B->PGR(Error)
    It is giving me the following error.
    Deficit of PU GR quantity 5 KG : 20027183 1330 2000 16
    Message no. M7021
    Kindly help me
    with regards
    Azeez.Mohd

    Dear,
       Please go through this link,
        [Deficit of PL Stock in transfer 10 EA : 100100051 IBM2;
        [Accept material in MIRO without any limitation?;
        [migo-return delivery-credit memo;
    Regards,
    Sandip

  • : Role Security within Company Code at Profit Center Level

    Can someone explain how to restrict GL transaction processing within a company code, below the company code level, at a Divsion / Branch level at the profit center level for ECC6 via user authorizations in FI GL roel security?

    Hi,
    Create Authorization Objects for the branch/ division containing the User ids and mention in the role.
    Thanks
    VK

  • Inter-Unit transactions within Company Code

    Hi,
    Business Scenario: There are various units within a Company Code. Each unit is a Profit Center. There are lot's of transactions that happens between units. For example, for expenses of Unit A, Unit B makes the makes the payment. There would be thousands of such transactions and there are more than 100 units. My query is, at the end of a period, how would Unit A would come to know that how much they have to pay to Unit B or Unit C or Unit D etc.
    Can someone please guide how to achieve this?
    Regards,
    Sanjay

    Hi
    You can get this reports by following T.Codes:
    1. S_ALR_87013343    :  Profit Center Receivables
    2. S-ALR_87013344     :  Profit Center Payables
    3. S_ALR_87013336    :   Profit Center Group: Balance Sheet Accounts

  • Within Company Code Material transaction

    Hi All,
    We are making a Stock Transfer betweeen 2 plants( A to B) WITHIN a company code.
    Here we have maintained the cost of material in Plant A as USD100. Now when this material from plant A is transferred to plant B the cost of this material in B should automatically increase by 4% i.e. it should become USD104.
    Can somebody tell us how this can be done.
    Regards,
    Jn.
    Edited by: terrence jn on Mar 10, 2008 10:36 AM

    See thread:
    Re: BAPIs for asset transfer
    Regards.

  • Stock Transfer Report from Plants within company code

    Dear SAP Experts,
    We have posted nearly 50 MIGO of stock transfer from our different plants within the same co. code since last 45 days. Now we want to take report of all stock tranfer receipt in our plant. (Like MIGO No. date, material code qty supplying plant etc.)
    Is there any standard T-code like MB51 which can give us the desired information. As in T-code MB51 there is no option to select supplying plant.
    Full Points if helped.
    Thanks in Advance.
    Ishu

    Hi Ishu,
              Go to SE16 enter the table EKKO or EKPO press enter it will take you to selection screen there you click on settings --> Format list --> Chooge fields , system will take you to all the fields avail in EKKO or EKPO there you click on deselect icon then you select fields Purchase doc,date ,Material,Qty and supplying plant then click on copy, system will take you to the previous screen there you click on excute icon.
    I hope it will full fills your requirement
    Regards,
    Murali.

  • Excise asset tranfer from one plant to another within the company code

    Hi All,
    Please provide me the procedure how to transfer an asset from one plant to another.
    The asset is an excisable pls provide the process for accounting in SAP for movement of FA on which we have taken excise duty and further we have to pay duty on removal of FA
    Edited by: siva prasd on Oct 19, 2011 7:11 AM

    Dear,
    Please check: Re: asset transfer within company code from one plant to another using STO
    Re: how to transfer  an asset from one plant to another plant within comp code
    http://sap.ittoolbox.com/groups/technical-functional/sap-acct/asset-transfer-237416
    Regards,
    Syed Hussain.

  • Asset transfer from company code to company code

    Hi ,
    I want to transfer assets from one company code located in India to another company code located in the US. The existing configuration is as under.
    Both the the company codes share the same "chart of accoutns" but the "chart of depreicaiton" and the "controlling areas" of the above two company codes are different.
    The client wants to transfer the assets at net book value.
    In the above scenario (1) is it possible to transfer the assets.
    (2) shall we have identical depreciation areas in both COD's
    (3) what would be transaction variant should we use? and the its mapping the transaction types in "Define Transfer Variants" node?
    Moderator: Please, avoid asking basic questions

    Dear,
    Please check: Re: asset transfer within company code from one plant to another using STO
    Re: how to transfer  an asset from one plant to another plant within comp code
    http://sap.ittoolbox.com/groups/technical-functional/sap-acct/asset-transfer-237416
    Regards,
    Syed Hussain.

  • Transfer with in same Company code with a fixed mark up

    HI  gurus,
    here is the situation ,we purchase some unlabelled packing materials form vendor in the distribution center , then pack them up into many smaller packages with our own label , after that ,the DC transfer packed material to store for sales .
    the requirement is that ,we want to manage both the stock of raw material and goods for sales in different article number ,and when doing the tranfer posting from DC to store ,the cost of package material can be included in the transfer cost of sales goods,additionally with a fixed mark up. BTW , the DC and store belong to same company code .
    any suggestion?
    thanks in advance !
    Edited by: deyi chen on Jul 1, 2010 9:21 AM

    Dear Friend,
    your scenario look like STO within company code
    you can achieve your requirement by
    Mark up or by paking scenario if you use packing scenario you can use that item category is relevent for pricing and you can add packing charges into your main product pricing
    your SAP termilogy shows you are working on  SAP IS Retail

  • Stock transfer across company code

    Hello Expert,
    I have one business requirement that is to transfer the stock from plant belongs to compnay code "A" to plant belongs to compnay code B. Stock transfer within company code from one plant to other is possible but is there any way to transfer the stock from one compnay code to other company code plant?
    Please share your experience.
    Thanks in advance.
    Wih Best Regards,
    Shyam

    You can refer to lots of link for Intercompany Stock Transfer process wherein you can transfer material from one company Plant to another companies Plant. One of the link attached for ready reference.
    Re: Inter Company Stock Transfer Order
    S. Kumar

  • Cross company code subcontracting process

    Dear Experts,
      I want to map one scenario in sap mm.
    We have 3 company codes within the client. Company A and Company B we have already implemented.
    Now we are going to do Implementation for the third company C.  Company C mainly doing a job work (service) only.  Both the companies A and B are giving the job work to the Company C.  Currently we are considering company C as a vendor. Company A and B will create a PO, Subcontract Challan and MIGO. PP process also we need to include in company C. If we implement SAP in company C how to map the Process.

    Hi,
    You can use subcontracting STO between plants that belong to company codes (intercompany STO with subcontracting):
    Re: Subcontract
    But in my opinion it is not the best solution in SAP because raw material flow is very dummy (you can transfer the components to the subcontracting special stock segment of the plant vendor - no component transfer between plants).
    I would suggest you to check multi plant / multi site planning as alternative solution:
    http://help.sap.com/erp2005_ehp_04/helpdata/EN/f4/7d2d4d44af11d182b40000e829fbfe/frameset.htm
    Reagrds,
    Csaba
    Edited by: Csaba Szommer on Sep 29, 2009 9:03 PM

  • STO - Two plants within Different Company Codes

    Hello,
    Kindly help me out with this case, i want to create a STO for two plants within DIFFERENT company codes, so i've created all the required configuration and master data including creating the supplying plant as a vendor and the ordering plant as a customer, also all master data is maintained in both plants and i tried the scenario on the IDES system and it works okay so i know i'm on the right procedures. The problem is that i create the PO, but when i go to Transaction Code VL10B to create the delivery it gives me an error ( Delivery with no Line item not allowed ) even though there is more than enough stock in the storage location. Kindly help me out.

    17.01.2010     Stock                            10.500,000      0,000      10.300,000
    13.01.2010     Order     Totals record     100,000-     100,000      10.300,000
    13.01.2010     Deliv.     Totals record     100,000-     100,000      10.300,000
    17.01.2010     StLcSt     SLFR     10.500,000      0,000      10.300,000
    13.01.2010     Order     Totals record     100,000-     100,000      10.300,000
    13.01.2010     Deliv.     Totals record     100,000-     100,000      10.300,000
    17.01.2010     BtchSt     123     10.500,000      0,000      10.400,000
    13.01.2010     Deliv.     Totals record     100,000-     100,000      10.400,000
    17.01.2010     BStLoc     123       /SLFR     10.500,000      0,000      10.400,000
    13.01.2010     Deliv.     Totals record     100,000-     100,000      10.400,000
    This is the whole table.
    This is what i got. i believe that it is an availability check problem, i just can't see what is the solution.
    SLFR is the Storage location of the issuing plant.

  • STO processing within Same Company Code with Billing/Invoice

    Hello Guru's,  I have been asked by our finance department to look at having billing/prices associated with our STO (UB) movements of stock within the same company code.  We currently use a UB order type but obviously no billing is associated with the delivery type NL.  We do have inter company STO's (order type NB) and have prices and billing associated with the delivery type NLCC.
    I wanted to take a copy of the NB order type (copy to ZB) and attached to relevant elements in the IMG (assign doc type & define delivery types).  I have done this in an open DEV client and have got a new PO created (ZB) and created a delivery, picked and confirmed the picking.  I have got to a point of PGI and i get the following message ' Purchase order 45########## does not contain items for a stock transfer'
    Firstly, do any of you trade via STO within the same company code and associate a billing document?  The reason we want to is that our manufacturing plants want to charge a premium to the packing and distribution warehouse for the goods to get profit visibility.  At the moment the standard cost of goods manufactured at our manufacturing plants transfers to our distribution plant at the same value. 
    If any of you have any ideas then please let me know.

    Hi,
    Pricing configuration for STO: -
    In SPRO > MM > Purchasing > Conditions > Define Price Determination Process > Define Schema Determination > Determine Schema for Stock Transport Orders > Here assign Calculation Schema "RM2000" i.e. Stock Transfer Document to Schema Grp Pur. Org, STO Type (For e.g. UB) and Supplying Plant.
    Calculation Schema "RM2000" has condition type P101 which will pick up the MAP of supplying plant automatically during creation of STO in ME21N ("Conditions" Tab).
    You can create new freight / delivery cost conditions in M/06 for Margin and assign in pricing procedure "RM2000" in M/08 and also assign the Accrual Key to this and do the Account Determination for this Accrual Key in OBYC
    At the time of PGI, following accounting entry will get generated;
    Stock A/c - Dr - 110 INR (Receiving Plant)
    Stock A/c - Cr - 100 INR (Supplying Plant)
    Margin Account - Cr - 10 INR (Supplying Plant)

  • Plant to plant subcontracting(Under one company code)

    Hi,
    I need a help on one issue.
    We are having multiple plants under one company code.
    Material goes with 57F4 challan for subcontracting plant to plant.
    How to do the subcontracting process for plant to plant.
    Please explain step by step.
    I know the normal process (with vendor)
    Also, if I have create a subcontracting PO, how the receiving plant will come to know about this?
    How will he receive the material which I have send?
    How the production activities at their end?
    Do I need to do the MIRO?
    Please thrwo some light.
    Thanks in advance,
    Piyush

    1)  Create Subcontracting Purchase Order with `0` Cost
    2) Transfer of Components to Subcontractor
    3) Create Subcontracting Challan
       a)Receive the Components as non valuated Materials
       b)Process the Materials to get the SF Product
       c)Create the Outbound Delivery without Ref. To Sales Order
       d)Endorse the Subcontract Challan Manually
    4) Post Goods Receipt
    5) Reconcile Subcontracting Challan
    6) Complete / Reversal / Re-credit SubcontractingChallan
    During Reconcile the Subcontract Challan - J1IFQ,Enter Manually into the Assigned Quantity Field the Components that are actually assigned for this Subcontracting Process.
    Regards,
    eswarmanu...

Maybe you are looking for

  • Problem writing to serial port

    Hi All, I am very new to LabVIEW (just a couple of months). I need to communicate with a serial port of an Advanced Energy RF generator (Ovation) serial port (AE Bus) The manual talks about little endian conversion, CSR and checksum that I just can't

  • MBP running hot, full fans and sluggish with both Safari and Firefox

    Hi guya, Im having problems with my kate 2007 MBP. Im sure lately it seems to be running slower and slower and more and more sluggish - I was hoping my Mac wouldn't be subject to "slowdown" like every PC ive ever owned has. The biggest problem is tha

  • Table Control Modification for Note implementation.

    I am applying a note, wherein I have to add a field TAX1 to a table control. I am able to add the field, but it is shaded grey. Moreover when I run the note after doing the necessary modifications, it is giving an error 'Element TAX1 touches or overl

  • Using older iPod accessories

    I've been charging and snycing with the cable and power adapter from the 4g iPod with my iPod touch. It seems fine but is there a chance that there will be a problem in the long run. I don't like using the cable that came with the touch because its t

  • Copies of pictures

    Once a picture is imported, and the original is deleted, I assume that the image is stored in the iPhotolibrary in both Data and Original. Is that correct? Once the picture is modified in iPhoto, the new image is then stored in Modified folder? Does