Supressing non work day messages for material requirments on Work orders
Message CN687, pretaining to delivery date of materials takes into account the factory calender/nonwork days of the calender associated to the plant. This message pops up for every material line item on a work order, One could understand how involved it can be if ther are a number of materials on a work order, as you would have to enter passed each warning before continuing.
Is there a way without preforming a mod that will allow us to supress this message on the work order side. Supply chain still wants to see it, however maintenance does not?
Hi,
As per my understanding your planned order is scheuling for 2 days.Check teh capacity view in the std plang book and check the date on which the capacity is being shown.IF the same is not showing on 15th then the problem is with scheduling not with capacity load.
Also check the factory calendar assigned to resource master data.Check the date 15th on the bucket capacity on resource master SNP bucket capacity view.If the same is showing as working day then the master data needs to be changes.
Hope this can help.
regards,
kaushik
Similar Messages
-
Dear Experts,
I have a requirement for making material description as non mandetory in change request view of mdg material screen.
I have done that using field usage in get data method of feeder classes, but still message is displaying.
This message 'Material description is mandatory is displaying with check action only, but not with save or submit after i anhance field property as not mandetory.
How to prevent error message for material description in MDG material detail screen, when user click on check action.
Thanks
SukumarHello Sukumar
In IMG activity "Configure Properties of Change Request Step", you can completely deactivate the reuse area checks (but will then loose all other checks of the backend business logic as well).
You can also set the error severity of the checks from Error to Warning (per CR type, not per check).
Or you provide a default value for the material description, e.g. by implementing the BAdI USMD_RULE_SERVICE.
Regards, Ingo Bruß -
Table names for Material Characteristic againgst production order
Hi Guys,
Actually I have a problem in finding the table name for material characteristic against production order such as Individual length, factor, color, etc. I really spend more than a day to find this. But I cudn't make it. Finally I found the flow some how, but is working only for few cases. Here is the flow.
AFKO(RSNUM) --> RESB(OBJNR) --> INOB(CUOBJ) --> AUSP(OBJEK).
T-code: CO02 / Fast Entry tab / Change Configuration(Item Level) / Change Characteristic values.
Anybody knows about this. Please help me out on this. And please note that, it is not the material characteristic from MM01, it is against production order from CO02.
Thanks
Yasin.Hi Yasin,
The best way to know Table Names in SAP is to use a Transaction Code Called : SQL Trace. Tcode : ST05. This will tell you about all the database tables that have been accessed while the Transaction was executed. And then you do a complete analysis of it, what are all the Tables that have been accessed, the fields and the data transfered. So, it's a complete trace of the SQL Query but you can use the information as needed.
Have a look at the following Links:
http://help.sap.com/saphelp_nw04/Helpdata/EN/17/358df9c9fee2469105731e10756921/content.htm
http://help.sap.com/saphelp_47x200/helpdata/en/d1/801f89454211d189710000e8322d00/content.htm
The best things is that you can use it across any SAP Transaction as it is available in SAP NetWeaver .
Hope this helps.
Thanks,
Samantak. -
Message for Material Document Generated
Hello Friends,
On creation of Production Order, we do picking of components thru CO27. After completion of this Pick, though goods movements ( mvt type 261 ) are successful we are not able to see the message stating material document number in status bar ( left bottom part of the screen ) as we get it in other cases/transactions. Are we missing any parameter settings pertaining to these kind of messages and T-code CO27. Kindly advice.
Regards
maheshDear Ram
you are right. Since it is a mass transaction, it does create multiple documents ( probably my user never exploited the potential of this transaction and used it for single order only ). I tried it for multiple orders (3 Nos ) and results were as expected ( 2 documents got created ). But I didn't understand the system's logic of material document creation here, as it is observed that for one component it has created only one document for 3 different orders ( same batch nos) where as for other component it has created 2 documents for 2 different orders even though batch nos are same. All the components are consumed from same Storage location. I checked and compared both the documents but didn't find anything noticable. Any idea, what it could be?
regards
mahesh
P.S. : Mangal, Thanks for your inputs too. -
Warning message for material substitution in ERP E-commerce
Hi Gurus,
We are implementing SAP ERP E-commerce with TREX, ECC 6.0 backend.
Automatic material substitution is working in ECC. The material is also dispalying a warining message before substitution.
In B2B shop the substituion works - material X is replaced with matereial y but there is no warning message during substituion.
I believe matereial substituion in E-commerce is standard funtionality and it should work as configured in ECC for VA01.
Any susgestion why there is no dispaly of any message during matereial sub in E-commerce.
Thank youHi Ram,
What type of messags can be displayed on ECO ERP can be configured via XCM "UI" component. By default only error messages are displayed, You can create a customer component with message severity set to 'Warning" / "info" as required. After this all the messages raised by the Standard BAPIs are displayed on the basket.
However you need to be careful what severity level you want to use as apart from the message that you require, lot of other messages might also be displayed on the basket.
Regards
Roopali -
XML message for material master records
Hello experts
We want to implement an interface with material master records to be sent to our customers. This interface is proposed to be in XML. Can you please provide me with links or documents that explain how to integrate XML within SAP regarding master data maintenance.
I need to know how we can trigger the XML message and where to include the logic of the attributes to be sent.
Thank you in advance,
AlejandraHi
You can do this scenario in BSP , better sit with ABAP and Portal(BSP) Consultant .
they can give much more idea about this. Using BSP you can evaluate this requirement.
Best regards
Ram -
Report for Material Issued against Service Orders But not Billed.
Hi Experts,
For CRM Service Orders Based on the Reservation number generated in CRM we will make the Goods issue document in ECC.
My Question In CRM Do we have any standard report to see Material issued against CRM Service orders but not billed. i.e. Work in progress.
Thanks in Advance,
AbhineshHi Vivek,
What I wanted to say that you won't get information from VAV about billing since as far as I know it doesn't contain any relevant table.
You should try create a query using LIKP-LIPS-(joint type: left outer)-VBRK. This will connect deliveries to billing document, you can also get SO number. Please try this.
(Sorrowully I don't know which logical database would be good for you)
BR
Csaba -
BAPI for material documents by production order
I'm looking for a BAPI that will provide the list of material documents for a given production order. This is similiar to the functionality provided by the COOIS transaction using: "Documented Goods Movements" as the list type. I've looked at BAPI_GOODSMVT_GETITEMS. However this BAPI does not contain a method to select by production order.
Message was edited by:
Glenn DohertyHI
Check this link it wuld be helpful to you
'BAPI_ALM_ORDER_MAINTAIN' for change in service order. -
Message for Missing Parts While Creating Order
Dear Friends,
While Creating & Saving The Production Order System Is Not Supporting In Giving A Warning Massage On Missing Parts In spite Of Deficit In Storage Location For Materials.
The Clint Requires A Warning Massage In Case Of Materials Shortage In SL
I Tried To Get This From the Following Method
Checked For Define checking control In OPJK.
Selected plant, Order type & selected the business function 1 for create or 2 for release. And Maintained These Settings
a) Removed tick mark in No Availability check.
b) Type of component check Given as - ATP check.
c) Material release - 1. User decides on release if parts are missing.
d) PP Checking rule (Which Is same As with plant parameter OPPQ)
e) In Define scope of check (OPJJ) made a tick mark in check w/o RLT.
Then Assigned the availability checking group at Mrp View of Header material.
In spite Of All These Settings Still At The Time Of Order Release/Save A Warning Massage Or A Informative Massage Is Not Appearing
Please Suggestu2026u2026u2026u2026
HariDear Friends,
I Did The Following Settings
A) Define Checking control 02 Individual Req
Total Sales Single Record
Total Div Rec Single Record
B)Define Checking Rule PP Check Rule
C)Define Scope Of Check Availability Check 02 Ind Req
Checking Rule PP Check Rule
Stock
Include Safety stock
Stock In Transfer
Incl Quanty Insp Stock
And When No tick Mark Is Applied In NO Stor Loc Inspectn
Not Used Checking Group "KP" In components material master.
After Making All This Settings Also Before Order ReleaseWhen Pressed u201CMaterial Availability Checku201D
The System Is Showing All Materials Available In Spite Of Deficit In Storage Location
Suggestu2026u2026 -
Actual cost not correctly displayed for material consumed in an order
Hi All,
I have an issue which is as follows:
In a service order, I have consumed 13 materials for which I am able to view the list of goods movement with its amount and plant and storage location.
For each goods movement system has generated material document, accounting document, controlling document, etc.
However system is not displaying the actual costs of all the 13 materials consumed within the order. Only one material cost is dispalyed in actual cost of overview tab of COSTS tab.
Incidentally, when I clicked the "Rep. Plan/Act." button, system is displaying the actual costs of line item wise material consumption.
Kindly let me know what could be the reason for this error.
Many thanks in advance............ JK.Kannan,
If the "Rep. Plan/Act." costs are correct, then you have problems with your value categories
Have a look at the following correction programs:
Run TCode OLI5 to correct value category errors (program RIPMCO00)
Run TCode OLPM to re-build structures (program RIPMS001)
PeteA -
Update required quantity for material component in Process Order.
Hello.
I need update component qty from Z dialog program.
The famous BAPI_PROCORD_CHANGE doesn't deal with COMPONENT structure but only HEADER. Then I tried to combine it with an enhancement.
I see that in WORKORDER_UPDATE~BEFORE_UPDATE I can't change values in IT_COMPONENT.
Anybody have used enhancement for this purpose and how can I transfer my calculated values to order?
In addition I check ENHANCEMENT-SECTION CO_BT_ORDER_POST_02 SPOTS ES_SAPLCOBT to do it.
What syntax our developers should write if it's possible?
Thanks
Alex DavidovKumar.
What should be copied? The header batch or some/all of the characteristics of the header batch to a new batch for the component?
Anoop -
Value tolerance in PO for Material purchase
Hi,
In PO, value tolerance to be given for Material Purchase in Service orders where both Service Line item(item Category D) and material line items will be there(account assignment K)
How it's possible?
RegardsHi
Even if you Provide the value Tolernace what will be its usage. You will not stop replacing the Part right.
& For Materials Delivery tolerance works at the time of GR & Value tolerances work only at the time of invoicing. so the invoice will be blocked for payment.
Thanks & Regards
Kishore -
Handling of End of Day message
Hi,
We are using MQ and MDB with JMS for listerning the message from the queue. All messages are in xml format
i have 2 types of message
eg: 1. Normal message which has some identifier 13203(Nmber Normal messages can arrive for a day)
2.End of day message has some identifier 13202 ( there will be a one end of day message for a day)
Step1: First i have to recieve the message
step2:If the message is of type 13203 i can take for processing.(Similar kind of message will pumped from queue and the same process has to continue for all message)
Step3:Message listener will consume the message immedately when any message comes to the queue. If the message is of type 13202 this message has to be waited untill all the normal message gets processed and must be reached at the end .
1.How to handle this suitation.
2.How to handle it clustering environment
Technologies used: Jboss4.0.2,jdk1.4,servlets,MQ 5.0,Message Driven Bean, JMS
Thanks for helping.I would guess your scope for the "error" variable is limited to the the field in which it was caught. Try passing the "error" variable to the "handleCatchedError(error)" and updating that function to handle the variable:
handleCatchedError(oError)
xfa.host.messageBox(oError); //No error reported??
return;
You also might want to look at the Error object introduced with version 6 and updated in version 7.
try {
app.alert(); // one argument is required for alert
} catch(e) {
for (var i in e)
console.println( i + ": " + e[i]) -
No creation if material is missing, Still IW31 ( Work order ) is getting created
Hi Experts,
I reviewed few discussions and unable to get the correct answer.
I did the configuration for Material availability check on Order Creation with Path ..
Plant Maintenance and Customer Service - Maintenance and Service Processing - Functions and Settings for Order Types - Availability Check for Material, PRTs, and Capacities - Define Inspection Control
In this I assigned my order type with Business Function 1.
Material Availability :
Plant XX01
Order Type XX09
Availability Check 1 Check availability during order creation
Checking Rule 01 No Blocked Stocked - All rec/issue elmts
Component Check Type Blank
Collect. conversion 3 No creation if material is missing
PRT Availability :
No Check ( Not checked )
Checking Rule 01 Status check
Collect. conversion Blank
Capacity check
No Check ( Not checked )
Overall profile Blank
Collect. conversion Blank
My question is:
MMBE for that Material ZERO.
Before Config,
when I create Order manually IW31 with a components , Status is showing Mat.availability not checked ( MANC ).
After Config.
when I create Order manually IW31 with a components , Status is showing Material committed MACM.
When Configured for [Collect. conversion 3 No creation if material is missing], still order is getting created.
I changed to 2 or 1 , still order is getting created with no difference
But its going to a confirmation proposals asking me to do
either continue / ATP quantity / Scope of check.
If I select 1 or 2, it should show Missing Parts status or if select 3, it should stop creation of Order. But its not happening as expected.
Please let me know where I am missing Config.Hello
Q1 )
If I change option 1 or 2 :
1 User decides on creation if material is missing
Answer:If Material is not Created the system wont allow to add you that material until unless you create the material master created.I am considering here that you don't have material master
2 Creation even though no material is available
Answer:It will allow you to create the work order.i am considering here that you don't have sufficient stock.
Q2) what should be the expected Status for Option 1 or 2.
Before Config it was showing
Status is showing Mat.availability not checked ( MANC ).
After Option 1 or 2, Expected Status ?
Answer: You need to enter value 02 on the Availability Check field on the MRP3 tab of Material Master via TC MM02.
you will be get Material committed MACM after Saving the Order.
Br
Rakesh -
Costing items for material 21000001 in plant 204A without cost element.
Dear Friends,
Kindly suggest solution to below problem,
Costing items for material 21000001 in plant 204A without cost element.
Message no. CK597
Diagnosis
The itemization for material 21000001 in plant 204A contains valuation-relevant items without a cost element.
System Response
The costs of these item(s) cannot be included in the cost component split. This means that there will be inconsistencies between the cost component split and the itemization.
Procedure
Check the log for further system messages for material 21000001 in plant 204A. Correct the error and carry out costing again.
Thanks
Gaurav ChopraThanks
The error has been resolved..
In master data itself.
For co-products , the version category was not maintained.
Moreover in BOM,
The items which were coproducts were not Ticked as co product.
Thanks..
Gaurav Chopra
Maybe you are looking for
-
How to restrict vendor open items to be picked to 45 during F110 process
Hi experts, My client want to restrict vendor open items to be picked to 45 max during F110 payment run for each vendor. For example: If vendor " xyz" is having 60 open items at the time of payment run, it should allow max to pick only 45 open items
-
my iPod touch is stuck in restore, if i rebute iTunes will it delete all my stuff on iTunes?
-
HP LaserJet P2015 not printing via network
Hi, looking for help. I cannot print via the network on HP LaserJet P2015. It works via USB. When I try to add the printer it is identificable by Bonjour (Nearest Printers). It tries to configure the printer and appears as being active (green dot) b
-
Iphone4s currently stuck in the recovery mode,
hello guys, i tried to install the latest version that software update informed me which was 7.1 something today, normally for me it would just go directly to the loading bar, but this time it shut down and went to the recovery mode or whatever(just
-
Problem when repairing disk permissions
When I repair my disk permissions I always get this message after its completed: Warning: SUID file "System/Library/CoreServices/RemoteManagement/ARDAgent.app/Contents/MacOS/ARDAg ent" has been modified and will not be repaired. Is that a problem or