Hi Experts,
I reviewed few discussions and unable to get the correct answer.
I did the configuration for Material availability check on Order Creation with Path ..
Plant Maintenance and Customer Service - Maintenance and Service Processing - Functions and Settings for Order Types - Availability Check for Material, PRTs, and Capacities - Define Inspection Control
In this I assigned my order type with Business Function 1.
Material Availability :
        Plant                      XX01
       Order Type            XX09
       Availability Check    1    Check availability during order creation
       Checking Rule        01 No Blocked Stocked - All rec/issue elmts
       Component Check Type    Blank
       Collect. conversion  3  No creation if material is missing
PRT Availability :
          No Check ( Not checked )
           Checking Rule        01 Status check
           Collect. conversion  Blank
Capacity check
          No Check ( Not checked )
          Overall profile Blank
          Collect. conversion  Blank
My question is:
MMBE for that Material ZERO.
Before Config,
   when I create Order manually IW31 with a components , Status is showing Mat.availability not checked ( MANC ).
After Config.
   when I create Order manually IW31 with a components , Status is showing     Material committed MACM.
When Configured for [Collect. conversion  3  No creation if material is missing], still order is getting created.
I changed to 2 or 1 , still order is getting created with no difference
But its going to a confirmation proposals asking me to do
either continue / ATP quantity / Scope of check.
If I select 1 or 2, it should show Missing Parts status or if select 3, it should stop creation of Order. But its not happening as expected.
Please let me know where I am missing Config.

Hello
Q1 )
If I change option 1 or 2 :
1 User decides on creation if material is missing
Answer:If Material is not Created the system wont allow to add you that material until unless you create the material master created.I am considering here that you don't have material master
2 Creation even though no material is available
Answer:It will allow you to create the work order.i am considering here that you don't have sufficient stock.
Q2) what should be the expected Status for Option 1 or 2.
Before Config it was showing
Status is showing Mat.availability not checked ( MANC ).
After Option 1 or 2, Expected Status ?
Answer: You need to enter value 02 on the Availability Check field on the MRP3 tab of Material Master via TC MM02.
you will be  get Material committed MACM after Saving the Order.
Br
Rakesh

Similar Messages

  • Approval for material return issued against the Work Order

    Hello,
    We are using PM module and issuing materials against the work order.  Many times users are returning the un-used material back to stores.  This un-used material may come back <b>with or without</b> work order reference.  i.e. Sometimes they just return bunch of material but don't know the work order # against it was issued initially.
    We need to control this flow of un-used return material through proper system approval.
    How can do this.
    Thanks,

    Hi,
    In standard SAP There is no approval process to return the material.
    I have one work around , you can create one PM order to return the material & instruct your store people to receive the material only with reference to PM order.
    With out releasing a PM order, system will not allow to post the goods return.
    I hope it may help you.
    Regards,
    Manish

  • How to find the material received in warehouse for work order through table

    Dear All ,
    I am creating alerting system We have  requrirement that if the notification or work order is pending for 10 days then alert to be sent to planner and 20 days to his senior and 30n days to his senior
    We have created FM for this  every day program will run and check open work orders and notification pending for some days
    Now my question in the FM I want to add fields for material receipt
    Idea is say for refuebsihment order pending material is received in warehouse now when this is received alert to be send in the work order planner that material is arrived
    From which tables I can track this and how to know for the alerting system that material is arrived in warehouse so alert to be send
    please reply
    Regards
    pratap
    Edited by: Pratap bhikai  Ingole on Jun 5, 2010 9:20 AM

    Hi ,
    With reference to your second point , if your looking for some alret then whenever you have goods receipt or goods issue of stock material you can have a mail triggerred through workflow .. in our project what we did was , we had a user status ALMR - All Material received and this is SET by a  Z programme which checks whether all stock materials or non stock materials against the order have been received and sets the user status and this programme is run as a batch job with 30min frequency ....
    regrds
    pushpa

  • View labor and material costs in plant maintenance work order

    Hi
    I am aware we can bring in the costs in the work order through Activity types and assigning the costs to the acitvity type.
    Is there anyway we can bring in the actual cost for the work performed by the associate? should we link the work center to HRMS?
    Please advise. I need your valuable input for all the points below.
    Main points that need to be addressed:
    1. Each associate that is capable of confirming hours to a work order needs to be assigned an hourly rate that is reflective of the actual cost for the work performed by this associate. These hours are then tracked through the work order to give a cost for labor assigned to that particular job.
    2.Any materials used in the performance of the required task(s) dictated by the work order will be assigned to that order. These materials can be assigned through SAP purchase requisitions, tool crib spot buys, or procurement with a purchase card.
    3.Standard reports need to be created so we can track the total maintenance costs for any level of the equipment hierarchy as currently set up in SAP. When this report is created it should show the total maintenace costs for all the levels of the equipment hierarchy broken down into labor cost and material cost.  I am using Tcode IW37N and IW40 . Is there any suggestion?

    Greetings Chandra,
    1) You will need to create Work Centres for your associates and create the Activity Types. You can default the Activity Type for each Work Centre and maintain the rate for the activity via t-code KP26 planning.
    2) Planned and unplanned Purchase Requisitions for Components with category N will debit the order with material costs. But what do you mean by "tool crib spot buys" and "procurement with a purchase card"? You may need to develop a solution to do such postings to the Order (or for purposes of Cost controlling, manual activity allocation similar to confirming work may be desired such as Manual Activity Allocations via CO transactions (KB21N), unless you can cover that with Purchase Requisitions and POs with "F Order" account assignment.
    3) MCI8 Cost Report should be suitable for you, once you set up the Value Categories & Cost Key Figures.
    See
    PMIS Cost Analysis Reporting Overview
    Maintenance Cost Key Figures in MCI3 and MCI8 Reports
    PM Order Value categories and costs display

  • How to find sapscript or sapform for tcode IW31 - work order

    Hi Experts
    I want to do some modification of sapscript or smartform for tcode IW31 with program name SAPLCOIH.
    but the problem is I am not able to find what is the sapscript/smartfom name and how can I find out.
    Could anyone comment on this please
    Regards
    Piroz

    Hello Piroz,
    When printing from IW31/ IW32, you have to go through the following path from the menu bar.
    Order --> Print --> Order.
    It will give you a pop-up where you have to select the "Shop Paper". This is something similar to "Output Types". In "Shop Paper" you have the Print Program name, the form routine & the SF/script name.
    Hope this is helpful.
    BR,
    Suhas

  • My ipod is stuck on connect to itunes i do that restore and it still doent work i cant get inside my ipod!!!HELP

    My iPod Touch 5th gen is stuck on connect to Itunes and i cant see any of my apps or anything internal.HELP!!! PLZ!!!    

    What exactly happens when you try to restore via iTunes? Error message?

  • Work Order Material Availability Check Customizing

    Hi,
    I am currently trying to set up material availability check in the work order before saving. I am testing it by entering a material in the work order for which there is zero stock. Then clicking on ORDER > FUNCTIONS > AVAILABILITY > CHECK STOCK MATERIAL. However SAP would return 'All checked materials in order 100000317 are available' in status bar.
    My customizing is as follows:
    Define Checking Rules (SPRO):
    PM     Checking rule for plant maintenance
    Define Scope of Check (OPJJ):
       Availability Check: 01 (Daily Requirements)
       Checking Rule: PM (Checking rule for plant maintenance)
       Availability check: 2 (Check availability during order release)
        Stocks
        Include safety stock: X
        StockIn Transfer: X
        Incl. quality insp. stock: X
        Replenishment lead time
        Check without RLT: X
        In/outward movement
        Incl. purchase orders: X
        Incl. purchase requisitions: X
        Incl. dependant reqs: X
        Include reservations: X
        Include sales reqmts: X
        Include deliveries: X
        Incl. planned orders: X (check all planned o)
        Incl. production orders: X (take all production)
    Define Scope of Check (OIOI):
       Plant: (Corresponds to Work Order)
       Order Type: (Corresponds to Work Order)
       Check material availability when saving order: X
       Check rule: 02 (Corresponds to material being used)
       Release Material: 3 (No release if parts are missing)
       PRT Availability: No check
       Capacity Availability: No check
    I would appreciate if you could indicate if I am missing something in the customizing or if there is some sort of error. I would like SAP to display a system message on the status bar stating that this material is not available once the user enters this material.
    Regards,
    Nikolai

    I'am facing the almost the same problem. Could anyone tell me:
    1. How to make material availability check work  during Work Order creation?
    My requirement is Work Order can not be created when it has missing parts. I have set the config to '3' can not created when is has missing parts, but it still does not work.
    I have implemented SAP Notes 1148139 on my system (SAP ECC 6 Ehp 5) also, but still does not have any effect.
    I must not set the config Res./Purch Doc creation to 'immediately', because it does not fit to my user requirement. Is there anyone knows how to solve this requirement?
    2. How to make  information message/ Availability check screen appear when sparepart is missing, without clicking Availability Check button? for example: appear when clicking Save button.
    Thank you
    -amoonra-

  • Supressing non work day messages for material requirments on Work orders

    Message CN687, pretaining to delivery date of materials takes into account the factory calender/nonwork days of the calender associated to the plant. This message pops up for every material line item on a work order, One could understand how involved it can be if ther are a number of materials on a work order, as you would have to enter passed each warning before continuing.
    Is there a way without preforming a mod that will allow us to supress this message on the work order side. Supply chain still wants to see it, however maintenance does not?

    Hi,
    As per my understanding your planned order is scheuling for 2 days.Check teh capacity view in the std plang book and check the date on which the capacity is being shown.IF the same is not showing on 15th then the problem is with scheduling not with capacity load.
    Also check the factory calendar assigned to resource master data.Check the date 15th on the bucket capacity on resource master SNP bucket capacity view.If the same is showing as working day then the master data needs to be changes.
    Hope this can help.
    regards,
    kaushik

  • Payment Card Information with Material Groups and Work Orders

    When processing purchase transactions that were purchased using a payment card, standard functionality in SAP says the system automatically generates a parked document with authorized users allowed to post these documents. When these documents are being posted, does anyone know if the user can enter a material group and/or a work order number for reporting purposes?

    >
    Monique Stephens wrote:
    > Training is not the issue.  Material groups are a matter of personal preference.
    >
    > My main concern is if it would be a violation of SOX if the material group is changed from the original shopping cart on the PO itself.
    >
    >
    > Monique
    If your business is privately held then SOX does not apply to you. If your business has stock w/shareholders then it does.
    Correcting or making the material group more accurite is something that would be MORE SOX complient and not a violation.

  • How to make material availability check work during Work Order creation

    Hi Experts,
    Kindly advice about these matters:
    1. How to make material availability check work during Work Order creation?
    My requirement is Work Order can not be created when it has missing parts. I have set the config to '3' can not created when is has missing parts, but it still does not work.
    I have implemented SAP Notes 1148139 on my system (SAP ECC 6 Ehp 5) also, but still does not have any effect.
    I must not set the config Res./Purch Doc creation to 'immediately', because it does not fit to my user requirement. Is there anyone knows how to solve this requirement?
    2. How to make information message/ Availability check screen appear when sparepart is missing, without clicking Availability Check button? for example: appear when clicking Save button.
    Thank you
    -amoonra-

    Hi Maheswaran,
    I have implement the prerequisite notes. (Notes 790219 and 1034962). Do you know why it is still does not work?
    Thanks
    -amoonra-

  • Creation of Materialized view and Materialized view log.

    I wanted to create materialized view with 'REFRESH FAST ON COMMIT' option.
    1) Table1 --it is partitioned range + list -- Added primary key
    2) view1   -- having primary keys on view's base table
    Steps:
    1) create materialized view log on Table1 ; -- default primary key
    2) create materialized view log on view1.  --- It is giving below error.
    ORA-00942: table or view does not exist
    i wanted to create Materialized view like below
    create materialized view
    REFRESH fast ON commit
    as
    select ...
    ... from table1
    where c1 in (select c1 from view1 where ... );
    Question:
    1) As i am getting above error while creating MV log on view. Can we create MV log on view or we have to create MV log on view base table?
    2) To create MV with ''REFRESH FAST ON COMMIT' option , do we need to have primary key on master tables? 
    Any pointers on this will really helpful.
    Thanks
    Prasad

    Also created MV LOG on 3 tables and tried with joins ..
    create materialized view
    REFRESH fast ON commit
    as
    select ...
    ... from table1 , tab2 t2,tab3 t3
    where ....
    and ...
    Get same error ORA-12052: cannot fast refresh materialized view AVSYS.EVENT_LOG_MV
    2052. 00000 -  "cannot fast refresh materialized view %s.%s"
    *Cause:    Either ROWIDs of certain tables were missing in the definition or
               the inner table of an outer join did not have UNIQUE constraints on
               join columns.
    *Action:   Specify the FORCE or COMPLETE option. If this error is got
               during creation, the materialized view definition may have be
               changed. Refer to the documentation on materialized views.

  • What are the mandatory fields while creation of material master in differen

    what are the mandatory fields while creation of material master in different views?

    Hi Gopi,
      This is purely depends on the function configuration, which would be done MM consultants.  Kindly check with them.
    thanks & regards
    Kishore Kumar Maram

  • Automatic creation of Material Master at the time raising the PO !!!

    Hello All,
    I am stuck in a scenario of our client which should be implemented (or mapped) in SAP.
    Scenario: At the time of creating the PO (in there legacy system -in house developed) they can choose the items from the existing master data or/and they can also add a new item (which is not present in the master data records at the time of creating the PO).
    Now as soon as the system realise that a new item is inserted into the PO, it will create that item record automatically in the backend (database) and the master data will be present from there on.
    The items they are dealing with are all fashion accessories and they generate order on the following basis:
    1. Demand of particular item in market.
    2. List of items provided by the vendor.
    3. Based on the requirement in there outlets.
    So for them its very difficult to fix there master data records, as it can be changed daily or monthly as per the market conditions. At the same time every time they order, its almost around 100 different items (some time 80 of them are new) in a single PO so they cannot create 80 records manually each time.
    These items are not consumable material so obviously they are maintaining the stock for them. They are also not going to use IS Retail.
    I am not at all sure how can we map this particular practice in SAP, it would be really appreciated if any one could help me on this problem.
    Please let me know if you need any other details from my side.

    Hi,
      As you have two different systems one in house developed and another SAP, and the PO creation part starts from Legasy system which creats the PO in SAP, you can do some development as per below
    1:  While Passing the details from legasy to SAP, use two columns in legasy one will contain the Material Code of ECC (for laready exist material ) and another for deescription of material.
    2: In case material is new for which there is no material master in ECC pass only description from legasy systems.
    3:While getting triggred from Legasy to ECC to create the PO, first check whehter all the material code exists or not in ECC.
    4:If some material are not created (only description present) for those material first create the Material Code using BAPI 'BAPI_MATERIAL_SAVEDATA'.
    5: Aftre creation of Material code create the PO using BAPI ' BAPI_PO_CREATE1'.
    6:For the new created material , trnasfre the master record from ECC to Legasy systemso that next time user can see that material in your legasy system.
    Regards,
    Zafar

  • Creation of material master

    Dear all,
    While entering of MM01, MM02, MM03 T codes, The system showing the error message - "Record Y1 01 does not exist in Table T133A" - for this what do I do, Plz suggest.
    reg
    Vishnu.Ch

    Hi Madhu,
        Thanks for your reply. But, I have one more doubt. For non stock materials, we
    will specify the cost centre and G/L account at the time of creation of Purchase order. Then, do we have to specify the valuation class at the time of creation of
    Material Master since there is no automatic account determination?
    Regards
    Yoga

  • MARA-GEWEI is not overtaken during creation of material from cdesk

    Hi, we work in ENV SAP R3 4.71 and create material in background out from
    cdesk.
    Therefore we defined in the customizing of CAD Desktop that in case of
    creation of material MARA-GEWEI determination type = constant and
    determination parameter is "ST" for "piece"
    Every other parameter works fine during creation of material ==> as soon as
    we fill a weight into the corresponding fields SAP tells us a message
    "ENTER the unit of weight for the net weight" ==> if you press "continue action then" SAP ends creation of material an nothing happens....
    ANY ideas?
    (will enter this message for sure as well into the oss....)

    Hi  Gerhard,
    have u put
    EXP_MARA-BRGEW           Gross weight
    EXP_MARA-NTGEW            Net weight
    from Inv side in config...
    Also check in cdesk_cus under create material
    <b>Base Unit of Measure               Constant     ST
    Net Weight               File Attribute     Physical_Properties_MassValue</b>
    hope this helps

Maybe you are looking for

  • Here we go again - PLS DON'T LOSE WAVY 10/FOX 43/NBC IN HAMPTON ROADS

    Gosh, we got through the fiscal cliff, and we got through not losing CBS on FIOS, now we have the threat of losing NBC!  I sure hope "three is a charm" as this would be a major setback if that happens.  VERIZON CAN YOU HEAR ME NOW? - PLEASE DO NOT LE

  • OfficeJet Pro 8600 Plus - N911g - refuses to print with an exhausted cartridge (yellow)

    Hi, I owned this printer some months ago, and I have already substituted the black cartridge some times ago. In fact, I usually use the b&w option to print my documents, and I use very little to no colors, instead. Before deciding to buy this printer

  • How do I make two page spreads export correctly to pdf with a book file?

    I have a book I am working on in the book pallet. I have several documents in the book and have it set to auto update page numbers and keep it all organized, which is all good. However, when I export to pdf, though the page numbers and order is corre

  • Variance analysis KKS2

    Dear All,    When i run the variance analyis through KKS1/KKS2 the following error message appears. "Only remaining var. in version 0 - No target cost for the order....".  Kindly help me in this regards Regards Vasantha

  • Anyone tried to deploy IBM's Java resource adapter for IMS on WLS6.1sp2?

              Has anyone had success or attempted to deploy the IMS Connector           for Java (IBM's resource adapter) on WLS6.1sp2? I would like to           use this to connect WebLogic to IMS via IMS Connect 1.2?           Thanks           Sam