Technical Design Review Question: mySAP Execution Architecture.

I got my hands on technical design documentation for a project on COPA budget. I came up with a few questions but I will post them separately for fast closing and awards:
1. In the Requirements discussion, I came across something
“Job naming conventions apply… and completion of Autosys Job Schedule request form is required….Forward this form to the mySAP Execution Architecture team for processing”
Is this a an internal team or it refers to some group at SAP company?
Is the Autosys Job Schedule request form a standard for or you think the environment had just come up a form for their internal processes? What may this include?
Thanks.

Hi,
If I understood correctly, The organization wants to maintain a document on jobs to be maintained regularly in production system. It will be used as a  reference in the support of BW production activities.
I hope, the mySAP Execution Architecture team for processing is the internal team from your client.
With rgds,
Anil Kumar Sharma .P
Message was edited by: Anil Kumar Sharma

Similar Messages

  • Technical Design Review Question: Key Figures

    I got my hands on technical design documentation for a project on COPA budget. I came up with a few questions but I will post them separately for fast closing and awards:
    In the discussions of Key Figures, a table was provided showing Name, description, source field, data type and Unit. With the exception of 5 of them, all the key figures had data type as Curr(17,2).
    My confusion is why all their equivalent Units were 0Currency while the 4 exceptions which had Data Type QUAN(17,2) had Units  of the form zvv90_ME, zvv094_ME, etc.
    I will appreciate your thoughts on these.
    Thanks

    All the Key figures which are curr(17,2) are meant to be used as Amounts which can be ties to different currencies..
    Like The key figure might have a number 1,000 and the corresponding entry in 0currency might be USD which means its $1000.
    You can find all the valid currency keys in the TCURC table..
    On similar lines For Key figures which specify quantity a few examples will be ;
    100 pc
    30 Hr
    Where the unit is stored in 0UNIT.
    Ashish

  • Technical Design Review Question: Requirements.

    I got my hands on technical design documentation for a project on COPA budget. I came up with a few questions but I will post them separately for fast closing and awards:
    1. In the Requirements, I saw a reference to some terms and I am wondering whether they are standard BW terms that I missed or, whether they are some abbreviations related to the particular project.
    “Product Contribution, Gross Margin, etc. reports from SAID, RAPID, and SMRS must be enabled from the BW COPA design”
    Any clarification on the above quote and are SAID, RAPID, and SMRS some terms in BW or some abbreviations in the project.
    Thanks.

    Hi Caud,
    I think it's better to directly ask your client !
    Probably it's something related to reportins system...
    ??? SMRS = (Study Management and Reporting System from PercipEnz Technologies, Inc) or (Standard Mortality Ratios)
    RAPID = http://www.microwavenews.com/rapidereport.html
    ...but are you working on an healht and science project ?!?

  • Technical Design Review Question: Operating Concern.

    I got my hands on technical design documentation for a project on COPA budget. I came up with a few questions but I will post them separately for fast closing and awards:
    1. In the Data  Flow Description, it was noted that
    “The operating concern will be 1010”
    Any clarification on the above 1010? Any clarification as to how the decisions on the operating concerns are made? What are the options and why is one chosen over the other.
    Thanks.

    Hi Caud,
    http://help.sap.com/saphelp_erp2004/helpdata/en/7a/4c38b54a0111d1894c0000e829fbbd/frameset.htm
    Try to take a look to this operating concern definition to better understand which char, value and account compose it to better understand how your company build this organizational unit (with a more or less uniform structure) related to its sales and the reason for what they choos this OC rather than another one !
    Hope it helps!
    Bye,
    ROberto

  • Technical Design Review Question: Data target Mapping and transformation

    I got my hands on technical design documentation for a project on COPA budget. I came up with a few questions but I will post them separately for fast closing and awards:
    In the discussions of Data target Mapping and transformation, there was a table of characteristics, showing dimensions, BW filed, Source field, data type, etc.
    1. What is the technique in deciding which characteristics get grouped together into a particular dimension?
    2. Why do some dimensions only have one characteristic and what is its significance?
    3. I saw one BW field, OVAL_TYPE (description= valuation type) included in three dimensions: Customer, Material and Valuation Type(only field=OVAL_TYPE). What is the significance of this repetition?
    Thanks

    Morning,
    To define Dimension means, to group all characters together, which do have a relationship "1 to n" and not "n to m" to reduce data volume (cardinality). If you reduce cardinality (which means to define 1:m relationship whenever it is possible and group them within one common dimension) you increase performance (make performance better) because of less data volume. It is essential to understand that this can not be changed easily after definition in PROD. So data modeling is also from this point of view very important.
    Example:
    An accounting object has a "m:n" relation ship to the accounting partner object. that's the reason way accounting object and accounting partner object do not belong to the same dimension.
    Ni hao
    Eckhard Lewin

  • Technical Design Review Question: InfoPackage Selection

    I got my hands on technical design documentation for a project on COPA budget. I came up with a few questions but I will post them separately for fast closing and awards:
    1. In the discussions of InfoPackage Selection, a statement
    “The budgets InfoSource will have full/Replace loads, based on plan version”
    Can you explain what this statement may mean? I am not sure I get it right.
    Thanks.

    Hi Caud !
    I think that thi statement refers to the possibility to delete the content of an infoprovider for the same selection criteria...so, in this case, you have to load budget data on the basis of the plan version and delete (replace) the already existing data for the same plan version loaded before !
    Hope it helps!
    Bye,
    Roberto
    http://help.sap.com/saphelp_nw04/helpdata/en/f8/e5603801be792de10000009b38f842/content.htm

  • Technical Design Review Question: Characteristics --UNITS

    I got my hands on technical design documentation for a project on COPA budget. I came up with a few questions but I will post them separately for fast closing and awards:
    1. In the discussions of characteristics I find that some were user defined i.e. begins with z and others 0.
    How is the decision made to create your own Units? And in particular, what are the steps to define it in BW for the system to know it? Need to do the same on R/3 side?
    Thanks.

    Hi,
    You do not need to create the units and currencies in BW system .Those will be populated from R/3 system .For the updation of unit and currency table(in BW) you have an option in the context menu of source sytem in the source sytem tree(RSA1).
    With rgds,
    Anil Kumar Sharma .P

  • Technical Design Review Question: Technical Build

    I got my hands on technical design documentation for a project on COPA budget. I came up with a few questions but I will post them separately for fast closing and awards:
    1. In the discussions of the technical build steps, the Profit Center was to be made the field for partitioning.
    How is such a decision made?
    And what is the implication?
    Thanks.

    Hi,
    If the reports are profit center specific , you can built
    the partitions on base of profit center. That means
    reports does not take the data from multiple profit
    center , then take that characterstic as base for
    partition.
    Here you will go for logical partitioning by
    multiproviders.
    http://help.sap.com/saphelp_bw32/helpdata/en/33/dc2038aa3bcd23e10000009b38f8cf/frameset.htm
    http://help.sap.com/bestpractices/crossindustry/businessintelligence/v131/documentation/Multi-dimensional_modeling_EN.doc
    With rgds,
    Anil Kumar Sharma .P
    Message was edited by: Anil Kumar Sharma

  • BI Technical Design Review Criteria/Best Practice Assessments

    Dear Experts,
    I am currently involved in conducting a pre-build BITechnical Design Review i.e. Data Model structure/Extractor/Transformation Logic/Data Flow Diagrams.
    Are there any tangible criteria/review template/methods out there to ensure all components are included in a BI design and that they conform to the SAP Best Practices?
    Thanks,
    Jony

    Hi jonathan,
    The BW Project guidelines can be as follows ,
    Stages in BW project
    1 Project Preparation / Requirement Gathering
    2 Business Blueprint
    3 Realization
    4 Final Preparation
    5 GO Live & Support
    Project Preparation / Requirement Gathering
    Collect requirement thru interviews with Business teams /Core users / Information Leaders .
    Study & analyze KPI 's (key figures) of Business process .
    Identify the measurement criteria's (Characteristics).
    Understand the Drill down requirements if any.
    Understand the Business process data flow if any .
    Identify the needs for data staging layers in BW – (i.e need for ODS if any)
    Understand the system landscape .
    Prepare Final Requirements Documents in the form of Functional Specifications containing :
    Report Owners,
    Data flow ,
    KPI’s ,
    measurement criteria’s,
    Report format along with drilldown requirements .
    2 Business Blueprint
    Check Business content against the requirements
    Check for appropriate
    Info Objects - Key figures & Characters
    Check for Info cubes / ODS
    Check for data sources & identify fields in source system
    Identify Master data
    document all the information in a file – follow standard templates
    Prepare final solution
    Identify differences (Gaps) between Business Content & Functional
    specification. propose new solutions/Developments & changes if required at different levels such as Info Objects ,Info cube , Data source etc . Document the gaps & respective solutions proposed– follow standard templates
    Design & Documentation
    Design the ERD & MDM diagrams for each cube & related objects
    Design the primary keys/data fields for intermediate Storage in ODS
    Design the Data flow charts right from data source up to Cube .
    Consider the performance parameters while designing data models
    Prepare High level / Low level design documents for each data model.--- follow standard templates
    Identify the Roles & Authorizations required and Document it – follow standard templates
    final review of design with core BW users .
    Sign off the BBP documents
    3 Realization
    Check & Apply Latest Patches/Packages ...in BW & R/3 systems.
    Activate/Build & enhance the cubes/ODS as per data model designs...maintain the version documents .
    Identify & activate Info objects / Master data info sources / attributes ,prepare update rules
    Assign data sources .prepare transfer rules , prepare multi providers . prepare Info packages .
    perform the unit testing for data loads….both for master data & transaction data .
    develop & test the end user queries .
    Design the process chains ,schedule & test
    create authorizations / Roles …assign to users ..and test
    Apply necessary patches & Notes if any .
    freeze & release the final objects to quality systems
    perform quality tests .
    Re design if required . (document changes, maintain versions)
    4 Final Preparation
    Prepare the final check list of objects to be released .identify the dependencies & sequence of release
    perform Go Live checks as recommended by SAP in production system
    keep up to date Patch Levels in Production system
    Test for production scenarios in a pre-production system which is a replica of production system .
    Do not Encourage the changes at this stage .
    freeze the objects .
    5 GO Live & Support
    keep up to date Patch Levels
    Release the objects to production system
    Run the set ups in R/3 source system & Initialize Loads in BW
    Schedule Batch jobs in R/3 system (Delta loads)
    schedule the process chains in BW .
    Performance tuning – on going activity
    Enhancements - if any
    You can get some detailed information in the following link.
    http://sap.ittoolbox.com/documents/document.asp?i=3581
    Try to go to ASAP implementation roadmap.
    https://websmp103.sap-ag.de/~form/sapnet?_SHORTKEY=01100035870000420636&_SCENARIO=01100035870000000202
    Check the links below that gives you brief overview of the above steps .
    https://websmp201.sap-ag.de/asap
    http://www.geocities.com/santosh_karkhanis/ASAP/
    ASAP
    https://websmp201.sap-ag.de/asap
    http://www.geocities.com/santosh_karkhanis/ASAP/
    https://service.sap.com/roadmaps
    https://websmp104.sap-ag.de/bi
    ***Please reward if useful.**
    Blue Print:
    http://www.sap.com/services/servsuptech/bestpractices/index.epx --- look for blueprint
    http://iris.tennessee.edu/Blueprint/BW/BW-Blue%20Print-Final.doc
    http://help.sap.com/bp_biv335/BI_EN/html/Business_Blueprint.htm
    You can get some detailed information in the following link.
    http://sap.ittoolbox.com/documents/document.asp?i=3581
    also please chck out
    https://www.sdn.sap.com/irj/servlet/prt/portal/prtroot/docs/library/uuid/2e8e5288-0b01-0010-2ea8-bcd4df5084a7
    a hwo to on BI7.0 upgrade .. also as suggested check out the BW upgrade roadmap on the support portal..
    Hope it helps..
    CSM Reddy
    Assign points if helpful
    Message was edited by:
            CSM REDDY

  • Review Question in Captivate 7

    I have review questions throughout my course.  I have them marked to not report in the quiz.  I also have a quiz at the end.  I have marked in my quiz preferences if the quiz is failed to go back to the beginning of the quiz questions.  The problem is when you fail it goes back to my first review question in the module.  Please help!!!

    Retake/Review takes you to the beginning of the Quiz Scope and if you have also content slides in that scope, it is by design that everything is visited.
    You can create a shared action, triggered on entering the first content slide (if all is linear) or entering each content slide (if not linear) that checks the value of cpQuizInfoAttempts (if you are at least at Attempt 2) and cpInReviewMode (to see if you are in Review mode) and based on that check jumps immediately to the next question slide.
    That is the explanation. I have already explained those steps in another thread a while ago, stopped blogging or it should already have been there.
    Lilybiri

  • VSphere 5.5 Design Review Checklist

    In my new assignment,  I am doing Design Review of a vSphere 5.5 Environment.
    Is there a brief Checklist that mentions All the Best Practices; To get me started.
    Thank You !

    Hi,
    Usually companies like IBM, VMware, HP, etc. have their own Reference Architectures.
    A lot of Reference Architectures are  posted publically by VMware. Try to search, if you can find the one which suits your needs.
    If you work in one of the BIG companies, try to check your internal documentations.
    Good Luck

  • Where can I buy a larger hard drive for my late 2008, 15" macbook pro?  From reviewing questions and answers on the support community it would appear that having Apple remove the old and install the new hard drive is recommended.  But how/where?

    Where can I buy a larger hard drive for my late 2008, 15" macbook pro?  From reviewing questions and answers on the support community it would appear that having Apple remove the old and install the new hard drive is recommended.  But how/where?

    Welcome to Apple Support Communities
    You can install the new hard disk yourself if you want to. You just need a 2'5" SATA II hard drive, which is compatible with your MacBook Pro. You can buy one at OWC > http://eshop.macsales.com/shop/hard-drives/2.5-Notebook/ You can filter hard drives by computer, so press a "Click to view all...", choose your computer in the sidebar and it will give you the compatible hard drives.
    There are different brands for the MacBook Pro. The most recommended are HGST and Seagate, which have good reputation. A 7200 rpm hard drive will give you extra performance

  • RE: Multiple-Choice Format of Review Questions in i Books

    Greetings Developers of the i Books Author App,
    When will a widget be developed for i Books that allows users of i books to type their answers to review questions in a 'text field' so that users are required to logically demonstrate deep conceptual understanding in science instead of merely guessing a simple multiple-choice answer, either A, B,C, D, or E to a simple, trivial factual recall 'intellectually shallow' question in secondary high school science?
    Thanks and Best Wishes,
    BabyBoomer44

    You should send feedback to Apple directly as your target audience doesn't review the public discussion forums.

  • I'm a new iPad mini owner.  I bought this hoping to be able to use for school.  My problem is that in order to see review questions I need QuickTime what can I do?

    Hello, I am a new owner of an I pad mini.  I bought this hoping to be able to use it for school.  I am having a problem opening review questions because I need QuickTime.  What can I do

    QuickTime is not an app you can download to the iPad
    However, many users have had success with an app called OPlayer HD to view their videos. And, there is a lite version so you can see if it'll work for you before plunking down the cash for the fancier version. VLC Media Player app is another possibility.
     Cheers, Tom

  • Functional and technical design for reports

    Hello BW gurus,
    I am responsible for creating/developing few reports in Prod Planning and Inventory Mgmt.
    Is there a template for the Functional Design and Technical Design for the reports?
    How do I go about making the functional and technical design?
    Thanks

    jackofalltrades,
    If you could give us the stage of the report -
    1. whether you are reporting from existing cubes and this report would be an additional one on a existing cube or
    2. The report has to be designed from the ground up ...
    Depending on the same - the entire lifecycle will be different and also whether the query is to be shown on the web or through excel will  be helpful.
    You could have a look at ASAP Templates in the meanwhile.
    Re: ASAP Methodology
    Arun

Maybe you are looking for

  • Macbook just crashed out of nowhere and I can't get it to turn back on!

    My macbook suddenly just crashed on me out of nowhere and I held down the power button to turn it off and it made that little noise when you hold it down and it shuts off. I pressed the power button again and the screen doesn't even come up, only the

  • Custom Fields in BSEG not updating on FI document post

    Hello Experts I'm facing a problem when posting FI documents. I'm using BAPI_ACC_DOCUMENT_POST and passing some Z fields using Table Extension2 (bapiparex). The problem is that the Z fields are not getting updated. BADI_ACC_DOCUMENT is implemented an

  • External HD Idea, Will It Work?

    Can an iMac DVD SE with a DVD drive that has bit the dust be used as a monitor for a Mac mini (temporarily)? In other words can I plug in a Mac mini to an old iMac and reap the benefits of the Mac mini? If not, what are good valued monitors that I co

  • "XI file to be uploaded in ECC"

    Hi, I need to know how to upload the file in XI and get the output in ECC. Regards Harish

  • Backing up files/folders