Can anybody explain me , how to transfer the service materials to outside servicers.
Eg,
1.I m creating one service PO with Some materials (No material master for that material). only i m entering the material description.
For above PO i want to sent the materials to vendor place (service-vendor).
Hw we can send the material out side and get it back after service completed.
Thnks
sap-mm

Hi thanks for ur reply
As per ur advise i can't create a BOM or some thing .
Becas , in my company somany materials are ther like this weekly i m sending  some 30 materials for externao service/repair.
Those Materials not having any material master or BOM (Nothing is there).
Please suggest me with some idea..
Thnks
sap-mm

Similar Messages

  • Transfer prices for service materials??

    Hi All,
    We have activated Material ledger to have transfer pricing. We want to maintain the transfer prices for service materials (with material type DIEN). But since quantity and value updates are not possible for material type DIEN ML is not activated for these materials and hence its not possible to maintain transfer prices either.
    Is there any other way of maintaining transfer prices for service materials?
    Regards,
    V S

    Hi,
    Please refer this link:
    http://www.sapfans.com/forums/viewtopic.php?f=10&t=270331
    Regards,
    Pramitha.

  • Sales of service materials from one SO or Contract with different durations

    Dear Gurus,
    I have to make a sales process for some service materials. Yet I could not decided whether I should go for sales order or contract. If contract then which one will be the suitable for my requirement?
    Requirement is like,
    for example I have a college courses as materials. so student purchased a course for 6 months from the middle of a month say from 16th of Jan and going to continue upto 15 July so I want the Jan invoice for amount of 16 days only. then the invoice of february for 28 days amount only later the 3 invoices for 30 and 31 days month with respective amount and the last invoice in july month will be for 15 month with the completion of the amount of 15 days only. hence the system should distribute the amount per days of the month from the start to end of the course duration.
    in the same order/contract i have a second course for same student where sale of a course for 1 year where he has to pay quarterly so the 4 invoices with with respective amount bifurcation are required.
    the third material with the 100% advance payment.and only one invoice on the same day of the purchase of course.
    can we do this scenario with single sales document?
    If yes what shall I go for? which Sales order or contract ?
    I think whether we go for sales order or contract we have to maintain different item categories for these three different requirements. which item categories will suit for these requirement?
    Can we have such different item categories in one document where some item categories have billing plan and some of them are without the billing plan?
    Gurus I am trying hard to get the solution for this problem and expecting your useful suggestion for the same.
    Please reply. Thanks in advance.
    regards,
    Sanjay

    Hi Sanjai
    Go for Rental contract (slaes document type is MV , item cat is MVN) and do the billing plan is periodic billing
    if u want to do  billing  in day wise, week wise, fortnight, monthy,quarterly,halferly ,yearly to customer , u have to do the following setting go to  SPRO go to sd-salesdocuments-contracts-contract data-define rules for determining dates
    there u have to determine rule table for determine dates
    I Think u r problem will solve
    Regards
    Chowdary

  • Changing Service Masters in to Service Materials (DIEN) any complications,

    Hello SAP Gurus,
    We are dealing with a Construction Based Client and along with Materials we also mainly require services,
    We right now have created Service Masters for catering our Service requirements, doing service entry sheets,
    But the major Issue with going by Service Masters is this Service masters could not be included them in BOM and we could not run MRP for there requirements,
    Basically for completing any Construction activity we require Material and also services to be performed but the service masters could not be included in MRP,  also the delivery cost cannot be handled going by Service masters,
    so we are planning to convert our Service Masters in to Service Materials to accomplish this requirements. any issues going by the same, and any precautions to be followed please suggest. have any one run there service requirements by using Service Materials instead of Service Masters / service activity please throw some light.
    Awaiting your suggestions
    Thanks and regards
    Kumar

    Hi,
    Thanks for your reply,
    The BADI and the info you have explained details about activating Services for Subcontracting Procedure, where in it requires to maintain Material Masters as required for managing and running Subcontracting process,
    But our company have already created 1000s of Service masters for managing there Service Activities ( only problem being cannot run MRP for Service masters  and Specify Delivery cost for Service POs)
    now as to get MRP we should  make a huge shift from Service Masters to Subcontracting Materials with BOM Values and should be well planned. i will definitely try to work on it and see how it goes.
    but also is there any way to use the existing Service Masters for running MRP, or including in BOM,  or any how to Plan services,
    Thanks and Regards,
    Kumar

  • Unit of Measurements of for Service Materials

    Hi,
    We want to create UOM for Service Materials like Per Well Per Month, Lumpsum.
    In SPRO-> General Settings-> Check Units of Measurement, do we need to create Dimension, ISO Codes before creating the UOM.
    While creating the UOM, what should we maintain in Commercial, Technical, Mesa. Unit Text. columns for the UOMs like Per Well Per Month, Lumpsum.
    Pls. guide.
    Regards,

    Dear Adi,
    These are information Fields.
    For LumpSum u can leave Blank ISO Code.
    Edited by: Pardeep  Malik on Mar 3, 2009 1:06 PM

  • Transfer of service tickets

    Hi all,
    I am working on CRM 4.0. I have a requirement where I would like to transfer service tickets of a business partner to another. In short I want to change the main Bupa of a service ticket. Is it possible ? or I will have to copy the service ticket to new business partner ?
    Regards,
    Vin

    The transfer of service tickets means transfer of sold to party  or any other partner functions are involved. If it is Sold to ,then u cannot but if  is for the other Bupas then u can
    Hope this answers
    Thanks
    Surya

  • Transfer of service between lines & major loss of ...

    Prior to Monday 1st March we had two phone lines installed, the first for phone and the second for broadband and fax (a legacy of when I required a separate fax line for work and when we using dail-up internet). The broadband speed was good, not the 8Mbs advertised, but I reckon perhaps at least 2Mbs (don't have the numbers from any old speed tests).
    In an attempt to save some money and due to no longer requiring the use of the fax machine, on Monday I arranged for BT to transfer the broadband service to the phone line. The result however has been a shock to the system and a step back 10 years... the download speed now is 0.3Mbs! Nothing else has been adjusted - filters are in the right places, no difference in the cabling etc... Productivity has been majorly affected, and there's no point in making any attempt at streaming anymore...
    Should I have expected to experience this major loss of speed after the transfer? Is there anything I can do, or is this going to be an issue for the BT complaints department?

    For your selected line, on the Leadselection event, you can get the contents of the line, pass the values to the node that is mapped to the component controller.
    Then in the other view, you can use the same node again to get back the values.
    Mapping should be done properly.
    So if the line in the table has 3 fields, all these 3 fields can be put to a node of Comp Controller.
    Then this node needs to be bound both to view A and view B.
    Hope it helps...

  • Stock transfer for blocked materials

    Hi,
    I have blocked the material  for procurement in MMR, in purchasing view in "Plant-sp.matl status" field...
    Now when ever i am creating PR,PO i am getting error message as "Status "Blocked for procment/whse" of material XXXXX does not allow external procurement"...Till Here it is correct.
    Now my requirement is, i do not want to procure this material, but i want to issue and do stock transfers for the remaining materials which are lying in my premises.
    When i tried doing stock transfer i got error message that "Material XXXXX has status Blocked for procment/whse in plant XXXX
    Message no. M7092..
    I tried to change the message as warning in OMCQ,There i didnot found this message, so i created it and made it warning.
    Now when i tried Stock transfer again i am getting same error.
    Pl help.
    Utsav

    hi
    goto OMCQ and click n new entry and then add this message as folows
    version   00
    Application Area   m7
    Message number   092
    and make this as WARning
    or goto OMS4 and here for ur block indicator make the Purchasing msg. as A  i.e. warning
    regards
    kunal
    Edited by: SAP Learner on Jul 16, 2009 1:29 PM

  • Account Assigment Transfer to Service entry sheet

    Hello;
    I wanted to transfer time sheet from cat2 to service entry sheet (SES) using catm without having to enter the GL and the cost center in the SES I tried to put the accnt assgmnt info thru the PO still I'm getting error in CATM saying GL not entered.
    Any help would be appricaited
    Ibou

    Hi,
    I think maintaining suitable Data Entry Profile will solve your problem. Take help from HR consultant.
    SPRO->Cross Application Component->Timesheet->Specific Settings for CATS Classic->Setup Data Entry Profiles.
    Regards

  • Stock Transfer for Excisable Materials Using Movement Type 301

    Hi,
    We are having a Plant 1002 as excisable Materials.
    During GR we following the process like GR (Part -I), Capture Invoice, Post Invoice.
    Can we transfer the Material from Plant 1002 to other Plant, say 1001, using Movement Type 301?
    Or we need to follow some other router for Stock Transfer for the Excisable Materials?
    I was told by the ex-consultant that we would be using Mov Type 301 for all Stock Transfers, but I have a doubt, please guide.*
    Regards,

    Hi PK,
    Here in Brazil we work with excisable material and when we have to transfer it plant to plant, we have to use IVA that performs tax posts on accounting document. Also, we have to create Nota Fiscal (BrazillianLegal Document).
    I think you have to talk to your legal/accounting area in order to make sure which procedure you will have to use.
    If you need tax posting on accounting document, then you will not be able to use 301 movement type.
    We use MM/SD Plant to Plant transfer (movement type 861 / 862)
    Depending on your Legal/accounting area feed back, you could use this scenario or just MM plant to plant transfer (movement type 303/305).
    If they are ok with no tax postings on accounting document, then 301 movement type should be used.
    Try to make a test, show then how it works, then you could get ok from then
    I hope it helps you.
    Best Regards,
    Natan

  • Transfer of Service master short text  from PR to PO

    Hi All,
    We have a scenario where we use Generic service number to order one time services. Based on the requirement we keep on changing the short text (description) of the service master in PO or Purchasing requisition. The issue is - Short text on generic service master is changed in PR but it is keep on reverting to original short text as in service master while converting PR to PO. . 
    For Example :
    Service master - Code - 100001 - Description - "Generic Corp Miscellaneous Services"
    I created a PR, included service no 100001 and changed the description of short text to - "Fixing tiles at foyer". Now when I converted PR to Purchase order service description should transfer to PO. But it is showing as 'Generic Corp Miscellaneous Services'. After investigation I found it is coming from the Contract that is linked with the PR as source of supply. And if I removed the Contract from the source of supply short text transfers from PR to PO. So Contract get precedence over PR.
    The requirement is - short text of service master should transfer from PR even when source of supply is Contract. It means always transfer short text from PR to PO not from contract. Is there any user exit/ config or change to ABAP code is required.
    Any help is greatly appreciated.

    Hi
    If you have document management system active in your system and if it the document type of documnet (which you created in CV01N) has link object PO and PR. Surely it will be transafred from PO to PR. But if you have added document in service object in Me52N then it will never go to PO automatically.
    Thanks and Regards
    Antony

  • Service Materials PO

    Hi Gurus,
    I need help in the following questions.
    1)When do we need to create Service Master (AC03) and when we can select a suitable NLAG material for services in a PO?
    2) If we put item category "D" in the PO, can we skip the material field and create a PO for services? Is creating Service Master necessary?
    3) We need to configure the short text description in material type like the following way:
        Material Type:NLAG (Services). A buyer chooses an NLAG material and he can put any description(such as Consulting services, Cleaningservices, etc) in the Short Text column in Item Overview, while creating a PO.
        Material Type:ROH . This flexibility will not be available. The desription of the material will be pulled up from the material master and no change allowed.
    Is this possible? If yes, then how we can configure it?
    Thanks,
    Kumar

    Hi,
    the recommended process for service procurement is the use of                 
    MM-SRV with service specifications (service masters, service descriptions with just texts, limits) , PO item categories D or B.. Please select always the button "full screen services" to go to the services screen in the purchasing documents. I would also recoomend to open on the services screen the outline view - a hierarchical view for organizing your services according to your needs.                                                                               
    Material type DIEN is just a small scale workaround for customers who         
    deal with services only occasionally and judge that MM-SRV is too             
    complex for them.                                                                               
    For this purpose the SAP standard delivery contains material type DIEN        
    which can be "purchased" externally. As DIEN materials are obviously          
    no "real" physical materials they cannot be kept in stock.                    
    Consequently PO's for DIEN materials must always have an account              
    assignment category. With this regards DIEN materials are just                
    an improvement of the purchasing without material number (freetext            
    items). On the other hand the process is not at all comparable to             
    the much more sophisticated service procurement with MM-SRV.                                                                               
    I hope the above information answers your inquiry.
    Regards,
    Edit

  • Possible to transfer ECC service notification?

    Hello,
    we are using service notifications on ECC side and I would like to transfer them on CRM 2007...  I have found BDoc SM_NOTIF but it seems to be a direct transfer from ECC to CDB?  Is there any way to transfer these notification (standard type S1) in an activity in CRM?
    Thanks for your help!
    Monica

    Or maybe I could call and have them refund the $140 I just put in? Have a feeling it's going to be a hassel though!

  • Transfer of Service tax / Utilization of Service tax

    Dear friends
    How to utilize the service tax paid?
    I transferred the Service tax from Interim to Final Account.
    Now I have to utilize
    From which T Code I can utilize the service tax against the Excise duty payable?
    Regards
    Kiran A

    Hello,
    Use the transaction code J2IUN. At the bottom of the screen, you have the option to use service tax for Cenvat. Select the radio button and give the final service tax accounts in the fields provided. This will enable you to use the service tax balance against the cenvat payable.
    Regards
    AKV

  • Error when transfer 2 oil materials with different UoMs into 1

    Hi experts,
    I have an urgent & tough issue like this:
    Our customer have a process of transferring 2 materials with 2 different base-unit-of-measure into one single material. See the following example for better understanding.
    Material 1: Mazut measured in Kg
    Material 1: Diesel measured in L15
    Some time Mazut seem to have very bad quality and need to be qualified before selling out, so our customer merge Mazut and Diesel together to improve the quality of Mazut. But it seems to be impossible in SAP.
    I've asked SAP support but no luck, it's been designed that way.
    I want to know whether other Oil projects encountered this before and what was the solution? Otherwise can you tell me how do they manage these 2 kinds of materials?
    Thank you very much,
    Best regards,

    Hi,
    I just one to know: What is the based unit of Diesel (Mazut) in other oil&gas company in the would?
    If you have any information of based unit of Diesel that is difference with DiepDH case. Please let us know.
    Thank so much,
    Huyen

Maybe you are looking for

  • Making a video with single frames

    Hi, I'd like to make a video with single frames. One of my computergames is able to take 25 frames per second (or 30, 40 etc.). The game saves the frames in a folder. For one minute there are over 1000 frames. Now I need to know, how I can tell After

  • Updated feed problem, PLEASE help, tried everything....

    Ive seen this same issue here in forums with no solution: Service Provider hosting my old feed was going down in a month... I placed the correct update tag in my feed to point to the new feed.... 1 month went by, the server went down... my new feed i

  • Add Year

    Hi, I have a query where I am converting a date to a year field and adding 1 onto the year: to_char(s.active_month, 'YYYY')+1 active_month is in date format DD-MON-YYYY I get an error message: ORA-00932: inconsistent datatypes: expected NUMBER got CH

  • Paralysis - voice control options?

    Hi, Hi, Im hoping to receiving some advice and direction to support a friend. A close friend was involved in a motorbike accident about 3 weeks ago. The positive news is that his recovery is progressing and while he will never have 100% mobility he w

  • OSX Zip files not readable by PC

    The brilliant Compress feature isn't working on the other end - won't work on PCs - or possibly these PC users are just idiots. LOL At firs they said they could not open it - now, they are telling me - "After downloading the file and then extracting