Hi Gurus,
I need help in the following questions.
1)When do we need to create Service Master (AC03) and when we can select a suitable NLAG material for services in a PO?
2) If we put item category "D" in the PO, can we skip the material field and create a PO for services? Is creating Service Master necessary?
3) We need to configure the short text description in material type like the following way:
    Material Type:NLAG (Services). A buyer chooses an NLAG material and he can put any description(such as Consulting services, Cleaningservices, etc) in the Short Text column in Item Overview, while creating a PO.
    Material Type:ROH . This flexibility will not be available. The desription of the material will be pulled up from the material master and no change allowed.
Is this possible? If yes, then how we can configure it?
Thanks,
Kumar

Hi,
the recommended process for service procurement is the use of                 
MM-SRV with service specifications (service masters, service descriptions with just texts, limits) , PO item categories D or B.. Please select always the button "full screen services" to go to the services screen in the purchasing documents. I would also recoomend to open on the services screen the outline view - a hierarchical view for organizing your services according to your needs.                                                                               
Material type DIEN is just a small scale workaround for customers who         
deal with services only occasionally and judge that MM-SRV is too             
complex for them.                                                                               
For this purpose the SAP standard delivery contains material type DIEN        
which can be "purchased" externally. As DIEN materials are obviously          
no "real" physical materials they cannot be kept in stock.                    
Consequently PO's for DIEN materials must always have an account              
assignment category. With this regards DIEN materials are just                
an improvement of the purchasing without material number (freetext            
items). On the other hand the process is not at all comparable to             
the much more sophisticated service procurement with MM-SRV.                                                                               
I hope the above information answers your inquiry.
Regards,
Edit

Similar Messages

  • Sales of service materials from one SO or Contract with different durations

    Dear Gurus,
    I have to make a sales process for some service materials. Yet I could not decided whether I should go for sales order or contract. If contract then which one will be the suitable for my requirement?
    Requirement is like,
    for example I have a college courses as materials. so student purchased a course for 6 months from the middle of a month say from 16th of Jan and going to continue upto 15 July so I want the Jan invoice for amount of 16 days only. then the invoice of february for 28 days amount only later the 3 invoices for 30 and 31 days month with respective amount and the last invoice in july month will be for 15 month with the completion of the amount of 15 days only. hence the system should distribute the amount per days of the month from the start to end of the course duration.
    in the same order/contract i have a second course for same student where sale of a course for 1 year where he has to pay quarterly so the 4 invoices with with respective amount bifurcation are required.
    the third material with the 100% advance payment.and only one invoice on the same day of the purchase of course.
    can we do this scenario with single sales document?
    If yes what shall I go for? which Sales order or contract ?
    I think whether we go for sales order or contract we have to maintain different item categories for these three different requirements. which item categories will suit for these requirement?
    Can we have such different item categories in one document where some item categories have billing plan and some of them are without the billing plan?
    Gurus I am trying hard to get the solution for this problem and expecting your useful suggestion for the same.
    Please reply. Thanks in advance.
    regards,
    Sanjay

    Hi Sanjai
    Go for Rental contract (slaes document type is MV , item cat is MVN) and do the billing plan is periodic billing
    if u want to do  billing  in day wise, week wise, fortnight, monthy,quarterly,halferly ,yearly to customer , u have to do the following setting go to  SPRO go to sd-salesdocuments-contracts-contract data-define rules for determining dates
    there u have to determine rule table for determine dates
    I Think u r problem will solve
    Regards
    Chowdary

  • Changing Service Masters in to Service Materials (DIEN) any complications,

    Hello SAP Gurus,
    We are dealing with a Construction Based Client and along with Materials we also mainly require services,
    We right now have created Service Masters for catering our Service requirements, doing service entry sheets,
    But the major Issue with going by Service Masters is this Service masters could not be included them in BOM and we could not run MRP for there requirements,
    Basically for completing any Construction activity we require Material and also services to be performed but the service masters could not be included in MRP,  also the delivery cost cannot be handled going by Service masters,
    so we are planning to convert our Service Masters in to Service Materials to accomplish this requirements. any issues going by the same, and any precautions to be followed please suggest. have any one run there service requirements by using Service Materials instead of Service Masters / service activity please throw some light.
    Awaiting your suggestions
    Thanks and regards
    Kumar

    Hi,
    Thanks for your reply,
    The BADI and the info you have explained details about activating Services for Subcontracting Procedure, where in it requires to maintain Material Masters as required for managing and running Subcontracting process,
    But our company have already created 1000s of Service masters for managing there Service Activities ( only problem being cannot run MRP for Service masters  and Specify Delivery cost for Service POs)
    now as to get MRP we should  make a huge shift from Service Masters to Subcontracting Materials with BOM Values and should be well planned. i will definitely try to work on it and see how it goes.
    but also is there any way to use the existing Service Masters for running MRP, or including in BOM,  or any how to Plan services,
    Thanks and Regards,
    Kumar

  • Unit of Measurements of for Service Materials

    Hi,
    We want to create UOM for Service Materials like Per Well Per Month, Lumpsum.
    In SPRO-> General Settings-> Check Units of Measurement, do we need to create Dimension, ISO Codes before creating the UOM.
    While creating the UOM, what should we maintain in Commercial, Technical, Mesa. Unit Text. columns for the UOMs like Per Well Per Month, Lumpsum.
    Pls. guide.
    Regards,

    Dear Adi,
    These are information Fields.
    For LumpSum u can leave Blank ISO Code.
    Edited by: Pardeep  Malik on Mar 3, 2009 1:06 PM

  • Transfer of service materials.?

    Hi gurus
    Can anybody explain me , how to transfer the service materials to outside servicers.
    Eg,
    1.I m creating one service PO with Some materials (No material master for that material). only i m entering the material description.
    For above PO i want to sent the materials to vendor place (service-vendor).
    Hw we can send the material out side and get it back after service completed.
    Thnks
    sap-mm

    Hi thanks for ur reply
    As per ur advise i can't create a BOM or some thing .
    Becas , in my company somany materials are ther like this weekly i m sending  some 30 materials for externao service/repair.
    Those Materials not having any material master or BOM (Nothing is there).
    Please suggest me with some idea..
    Thnks
    sap-mm

  • Transfer prices for service materials??

    Hi All,
    We have activated Material ledger to have transfer pricing. We want to maintain the transfer prices for service materials (with material type DIEN). But since quantity and value updates are not possible for material type DIEN ML is not activated for these materials and hence its not possible to maintain transfer prices either.
    Is there any other way of maintaining transfer prices for service materials?
    Regards,
    V S

    Hi,
    Please refer this link:
    http://www.sapfans.com/forums/viewtopic.php?f=10&t=270331
    Regards,
    Pramitha.

  • Service Materials

    Hello SAP Gurus,
    My client requirement is that along with the products they also sell services involved to the customers like Installation, Commisioning etc.How to cater to this sceanrio in SD as the cost of services should be transfered to the delivered material as these services should not come as line items in the billing to the customer.Also these services are outsourced to third parties so how to handle this in SD.Please help me in this.

    Hi Sunil,
               1.You create service material with DIEN itemcategory group in MM01 transaction.
    You put procurement type as both procurements in MRP2 view.
    Maintain cost of the material at in the accounting 1 view.
    Main tain VPRS condition type in the pricing procedure.
    2.You are telling that, service amterial should not come in the billing document as item, for this you create new copying routine in VOFM, you assign to your billing documents and delivery documents at item level in the transaction VTFL.
    3.You are telling that some times you sourced third party for this you can control through itemcategory determination in the transaction VOV4.
    Here you assign third party item category (TAS)in Mltca column,when you create sales order normally Stadard Itemcategory(TAN) will come but when create sales order for third party services enter TAS item category based on that Purchage requesition will be created,then purchase order with reference to Purchage requesition.
    I hope it will help you
    Thanks,
    Murali.

  • Profit Center Derivation in Service (CS) order

    Hello All,
    I need some inputs / clarifications on below query.
    Service Order is being created with internal / external labors / services / materials. Debit memo request has been created.
    In Service Order & Debit Memo Request, Profit center has been derived from Responsible work center which has been maintained in Main Work Center in Header tab of Service order.
    Hope, this is standard functionality.
    But I want to get the Profit Center based on my reference technical object. I understand by going through many threads that profit center derivation from technical object's cost center can be done only though development as suggested in Profit center substitution in IW31/ IW32.
    Just by having curiosity as this thread had been posted in 2009, is there any new enhancement or functionality by which profit center can be derived from technical object's cost center??
    Looking forward your suggestions...

    Maheswaran KD,
    Yes, as standard the profit centre is determined from the cost centre in the main work centre.
    Have a look at user-exit IWO10005: Maintenance order: Customer specific determination of profit centre
    PeteA

  • How to deduct my Penalty amount in Sales order (Customer Service)

    Hi All,
    We have a Service contract to bill the customer monthly based on the usage of our Equipment. It has three components.
    1. Usage no. of units produced during the month of Billing @ Rs.100 / unit
    2. Bonus amount on stoppage hours due to Customers (lack of input or power)@ Rs.300 / Hr
    3. Penalty amount on stoppage due to Service provider (lack of spares or Service Engineers) @ Rs.200 / Hr
    We created a Service contract with three Service materials (line items) with agreed rate as Condition value.
    Daily we recording the reading above 3 parameters using Measuring point of the Equipment. We have a report to get monthly total of Productivity, Stoppage due to Customer, Stoppage due to Supplier.
    We are thinking to create a Sales order every month (will copy the rate from contract) and enter the readings (manually) in the Quantiy field.
    If I enter the Condition value -200 for third parameter (Penalty), system accepts and reflected in Sales order too.
    Request to verify my flow and correct me If I am wrong.
    Other solutions are also welcome.
    Thanks in Advance,
    Babu

    Any thoughts?...
    Babu

  • "Limit" tab on service PO

    Hi,
    May i know what is the function of"Limit" tab under Item for a service
    po?
    1)What is the overall limit purpose.
    2)There is a sub-tab call"Other limit" with "No limit" ticked.
    What is the impact if i unticked the No limit?
    Thank you.

    Hi,
    Hi, Please refer to the Online documentation: Material Management -> External Services Management -> Procurement of Services: Processes -> Accelerated and Simplified Processes -> Use of Value Limits (for Unplanned Services) Inside this documentation, it is stated that there is a variety of limits (combinations) to be used:- - Overall limit only - Overall limit and limit on services covered by contract item(s) - Overall limit, limit on services covered by contract item(s), - and other limit - Overall limit and other limit - Overall limit on services from model specifications or standard service catalog - Expected value.
    The expected value is used in the update of the PO item value and this is the value used in the release strategy. Here is the f1 help: Expected value - ESUH-COMMITMENT Value that the unplanned services (or the materials) covered by this item are not expected to exceed. Use If you are working with the release (approval) procedure for purchasing documents, this value serves as the basis for a release strategy applied to this document.
    If you tick 'No limit',you don't need to enter 'Overall limit',but must enter 'Expected value'. Because 'Expected value' will affect the release strategy. Please read the note 440601 connected to this:
    The expected value has to be mandatory in case only limits are     
    maintained in a purchasing document due to release strategie and commitment figures.   
    The expected value is added to the total value of planned services        
    of the purchasing document.                                               
    For example, a PO with ONLY unplanned services /materials                 
    (only limits maintained), the expected value builds the net value.        
    In such a case Controlling derives the purchase commitment figure         
    only from this value.
    Concerning the variability of actual cost of a purchase order,                 
    expected value means that the unplanned services (or materials)                
    covered by this item are not EXPECTED to exceed.                               
    It is not mandatory that it has the same value like total limit value.         
    Expected value can exceed, it is used for comparison with total limit          
    value in cost control.                                                         
    Expected value can also be combined with unlimited total limit in a            
    purchasing document.                                                           
    Regards, Edit

  • Category for service category S046 does not exist

    Dear Experts,
    This is regarding the Bdoc error "Category for service category S046 does not exist". ECC service materials are trying to replicate from ECC to CRM. In our scenario we doesn't required ECC service material in CRM. I have not downloaded service materials relevant data. Still i am facing the above error.
    Please help to fix the above error.
    Regards
    Ashwini

    Hi,
    Thanks for your reply. I have maintained the filter on service_master  object is not working.
    I have not downloaded the service material from ECC to CRM.Then what could be the reason for the above bdoc error.
    Please help me.
    Regards
    Ashwini

  • How to create a Catalog (Product/Service) & TAX issues

    SRM Guru's
    Product Ver: SRM 5.0 : ECC 6.0  ( No CCM or Service Master )
    TAX S/w: Vertex ( O )
    As of now:    We are planning to implement a vanilla SRM-ECC (in ext. classic). We are into Indirect procurement w/limit orders.
    Catalog:
    I want to create a Catalog ( UNSPSC or 1 level company catalog),
           1. Can this be created in ECC  (with out Products ) and replicated to SRM (EBP)
           2. How to go about creating it ?
           3. Can it be done with out CCM, if so how
           4. How to replicate it ? ( no CCM or middleware )
           5. Can i create it in EBP ? if so, plse say how..
    TAX:
    Vertex mentioned that, Tax codes will be mapped to services, in our case, since we don’t have Services except a free form text describing what service is provided ( eg: "Payroll Service" ), what can be done ?
    In a normal scenario, i can imagine having Service Master with all "Services", but in our situation, how can we use catalog to map to TAX codes. ?
    PS: If you could, please describe/break down the relationship between
       Catalog -- Category Id -- Product -- Services/Materials
    regards.,
    -Rupesh

    Hi
    <u>To create internal catalog there are three possibilities</u>
    1. CCM Catalog developed by SAP.
    2. SRM-MDM Catalog taken over by SAP.
    3. Requisite Catalog other catalog provider.
    <u>Check these links -></u>
    http://help.sap.com/saphelp_ccm20/helpdata/en/index.htm
    https://websmp101.sap-ag.de/ibc-srm here check SRM-MDM Catalog.
    http://www.requisite.com/solutions/index.cfm?pageID=productpac_bugseye
    Re: Catalog Mgmt
    <b>Other related links -></b>
    <u>Create Internal Catalog</u>
    Re: Create Internal Catalog
    CCM Create catalog link
    Re: creating a catalog
    Catalog ID does not exist
    Re: SRM Contract Catalog - Creation
    CCM SRM product catalog
    Re: Product Catalog to CCM
    <u>Managing Catalog content in SRM</u>
    http://help.sap.com/saphelp_srm50/helpdata/en/0a/f9353e39011a38e10000000a114084/frameset.htm
    http://help.sap.com/saphelp_srm50/helpdata/en/ba/7a50415e216e24e10000000a155106/frameset.htm
    <b>P.S: All tables for CCM (Catalog tables and CCM) start with "/CCM/" ,so you can search on that using SE11 transaction.</b>
    <u>MDM-SRM Catalog</u>
    Re: MDM SRM - Catalog - External Catalog - Punchout
    <u>Punchout catalog</u>
    Punchout catalog
    <u>Loading Product Data into Catalog using CSV files</u>
    Loading Product Data into Catalog using CSV2.0 file
    <u>Contract catalog</u>
    Re: Contract catalog
    Hope this will definitely help. Do let me know.
    Regards
    - Atul

  • Service PO's with tax and Non servie pos without tax

    Hi,
    In my present process.For service (ME21N)PO'S withholdingtax is calculated and for non service PO's there is no withholdingtax  calculated.
    In standard sap PO's.Tax will be calculated for both service POS and non service PO's.
    Can any guide me where the coding is done by which the system is calculating tax on service pos and no tax calculated on material pos.
    It will be great help.if you can through some light.
    Thanks
    Hagi

    Hi,
    With respect to WHT, vendors can be classified into three categories
    1) Service Vendors (subject to WHT)
    2) Material Vendors (not subject to WHT)
    3) Mixed vendors (WHT is applicable on services only)
    Identifying the type of vendor needs the data from business only.  There is no specific indication in SAP.  In case of 1 & 2 type vendors there is no problem.  Problem with type 3 vendors.  Since WHT keys are updated at vendor level, during IV system withhelds the tax amount on entire invoice which is wrong since materials may also be there in that invoice.  For this there is no standard solution by SAP.
    We need to further identify vendors based on supplies with both services and materials. If the % of services & materials combination is more, it is better to create two seperate vendors for the same vendor, one as service vendor and another as material vendor and ask the vendor to give seperate invoices for services and materials.  If it is very less %, while posting invoices just change the base amount against the WHT keys.  This is the practice we implemented for our client.
    regards,
    mallik

  • External Service Maintenance (PM Module)

    Dear All,
    Can u help with External Service maintanence in PM module.
    1. If in case i want to send material for service, a automatic service PR will be generated.
    2. But if i want to send material for some extra material to be fitted eg. if i want to send Rubber Rolls for Recoating which costs more. Then in this case do we need to create Service PR or PR with acct asst K.
    Now if i am creating orders in PM then only a Service PR is generated.
    Please guide how will the accountabily will be there for this kind.
    Is it possible to link both type of external service in Service PR ?
    1. Service
    2. Service + Materials to be added in material.
    Thanks.

    Hi
    If you want to buy a material, you have to use account assignment K. You cannot use as service item category D. In same PO you can have Material and service if your document type allows. (you see it in documen type config for allowed item category)
    Regards
    Antony

  • Service & Material Purchase:::URGENT

    Dear All,
    Can we purchase services & materials within the same purchase order ????
    If Yes can u guide me how ???

    hi,
    in standard SAP noway , becoz it depends on your PO document type ( it only decides what are the item categries to be allowed) in general we will be having separate document types for material procurmen & service
    Regards
    Illay