Transport management during implementation

Hi,
The landscape for our implementation project is SM 7.0 SPS 15 with ECC 6.0 D, Q and P as satellites. We use SM for Blueprinting and Config management. Considering the short duration of the project CHaRM is not implemented in SM. We use SCC1 for intra-client transports and across D,Q and P by standard TMS.
My question is - in the abscence of CHaRM in SM, is there any way we can record/manage/document transports in SM during configuration phase?   
Thanks.
Mike
Edited by: Mike Sikorsky on Jul 23, 2008 6:05 PM

Hi Mike,
One Solution would be to have OS level Script which would record all the Transports across your ECC 6.0 D, Q, P ..but, for this the person
must have in-depth knowledge of internal architecture of  TMS and the OS as well. This is quite complicated .
Usually, the Unix Scripting can handle this, but if you have the Windows I am not sure if the Batch File can do this or not.
Hope this helps.
Thanks,
Regards,
- Rupen

Similar Messages

  • Issue management during implementation

    Hello!
    We are planning to use issue management in blueprinting and config phases in our rollout. We have SM 7.0 SPS16 with Workcenters configured. In Solar01/02 when I create an issue at a relevant project structure node I get the window " Issue Maintenance".
    How or where do I configure for the following settings in the " Issue Maintenance " window.
    1. Priority - I want to customize the drop-down menu with my own. (Instead of the default 1. very high...etc.)
    2. Subject - I want to customize the drop-down menu entries in this field too.
    3. I want to hide the tabs "Service sessions" and "Change requests" as we are not using this.
    Appreciate your help and inputs.
    Thanks.
    Mike
    Edited by: Mike Sikorsky on Jul 14, 2008 8:32 PM

    Hi
    1) Use OSC3 or OCS3 transaction, i could't remember which one
    2) You will have to use transaction SPRO and navigate to "Define Catalogs, Codes, Code Groups" and make changes there. After that you need to adjust/customize Code Groups, followed by Code Group Profile, followed by Subject Profile. Then you will have to make changes to Transaction Type SLFI. It's quite a lot of work
    3) I am not sure if you can hide those tabs.

  • Requirements from the business implementing transportation management

    Hi Gurus,
    Great day to all. Maybe you can help me with a list of requirements or a checklist that I need to get from a business who wants to implement transportation management?
    Any help will be greatly appreciated.
    Thanks

    hi
    check the same in help.sap.com

  • Usage of MRP Procedures in Consumption Based Planning during Implementation

    We have following procedures in CBP:
    1. Reorder Point Planning- Manual and Automatic
    2. Forecast based Planning
    3. Time phased Planning.
    In SAP implementations, which of these procedure is mostly used in companies in real time.
    Though the CBP planning node is in MM SPRO and  MM study material also contains CBP. During implementations, for CBP the responsibility rests with MM consultant or PP Consultant or both.
    Please share your views on this.

    Dear ,
    Let me share my views on this as we are runing CBP-Forcast base planning  in our trading business .
    Decision on CBP-Forecast base planning method are based on the following criteria
    1.Stockable and low value material
    2.Fast Moving with good sales pattern ( Trend Analysis , Historical Trend analysis on Product Group , Statistical Sales analysis )
    3.Inventory turn around based on the monthly physical inventory and sales
    4.Good service level percentage over an period .
    5.Consumption pattern .
    Decision on CBP-Re-order point planning method are based on the following criteria
    1. Material which are higher valu and Non Stockable
    2. Customer oriented traded goods
    3. Strategic vendor with good Sales pattern .
    4.Re-order Level based on Sales Forecast (Manual or Automatic )
    In SAP implementations, which of these procedure is mostly used in companies in real time : It is based on the business requirement (Trading /Manufacturing ) .Mostly Trading business goes for CBP-Forecast Base planning method (MRP Type -VV) IF THE MATERIALS HAS GOOD CONSUMPTION PATTERN OVER A PERIOD OF TIME .
    MRP is both the part of Supply Chain Planning and Manufactruing . Material master parameters are maintained by MM .CBP is one kind of MRP where Demand Management comes into PP whereas after MRP run , procurement proposal handeled by MM.So there is no hard and fast rule that it is only part of PP.It is the combination of MM and PP.
    Hope this will help you to analysise your requirement .
    Regards
    JH

  • Purchase Order determination Transportation management

    Dear Gurus,
    We are in process of analysing transportation management system.
    Kindly let me know the process of how the system automatically determines the purchase order during Transfer in shipment cost seetlement transaction.
    If we have multiple POs, then how system identify which PO to pick.
    During maintaining of purchase data for transportation planning point, we maintain only few things, then how does system identify a particular PO.
    Any help is appreciated.
    Thanks.

    Purchaser Activities
           1.      Choose Process Purchase Orders.
           2.      To create purchase orders manually (without a preceding document), choose Create.
                                a.      The system opens a new document in the change mode.
                                b.      You add any missing entries at header and item level.
           3.      To process an existing purchase order, you have the following options:
    ¡        In the worklist, choose the number of the purchase order you wish to look at.
    ¡        Use the search and choose the document from the search results.
           4.      In order to process header and item data, choose Change.
    For example, you can use  in the partner overview to transfer the preferred vendor to the purchase order.
           5.      Choose Check to determine whether entries still have to be made or changed in the purchase order.
    A list shows any missing or incorrect entries.
           6.      In order to transfer the document to the vendor, choose Order.
                                a.      The system generates an output action.
                                b.      The system processes the output action and sends the document using a scheduled output report
    You can read more at
    http://help.sap.com/saphelp_srm30/helpdata/en/38/4cc5376848616ae10000009b38f889/content.htm
    Hope this helps, Thanks

  • SAP APO Transportation Managment 5.0

    Hi,
              I would like to know the the process to Implement Transportation and Planning 5.0 in SAP APO environment ,presently the client is using SD for transportation and distribution.
              If you could mail me implementation guide in regards to Transportation Managment it would help me a lot.
                Could u send me some links which will help me.I have refer to master Data sep-up and understood the process in help.sap.com.
    Thanks
    Partha

    Dear Partha,
    Pl. find the below link
    http://help.sap.com/bp_scmv140/BBLibrary/documentation/S12_BB_ConfigGuideEN_DE.doc
    This guide will show you basic configuration settings to be made in both the systems. Though it does not list all the configuration, but it is quite useful guide to begin with.
    Regards
    Sandeep Patil

  • Change Request Management without Transport Management

    Hello Change Request Management Experts!
    I have understood that It is possible to take change request managment in use without transport management. So I could handle Change Request with different statuses without automatic funtions behind these statuies. We like to see how to handle changes between different roles of people and implement the functions after that.
    I suppose that I should take only Change Request (approvals) and not Change Documents (execution) from Change Request Management.
    Have any of you tried to do that? 
    Best Regards, Leena Nissilä

    Hi Andy,
    Thank you for your answer. I have tried to do that also but I where is still some configuration missing because I get error message in: No maintenance cycle is open for the current system. I have also tried to to that maintenance cycle but I thought that it needs CTS activation in some project.
    I also like to know what is minimun configuration for change management that I could use SDAD with Service Desk.
    I looking forward to you reply,
    Br Leena
    Edited by: Leena Nissilä on Sep 17, 2008 1:24 PM

  • Transport managment, source system changed in import

    Hi all,
    i faced with the need to change the source system in transport management. I mean, dev source system to assign a different test system source. now is the following:
    InfoPackage ZPAK_4MSK400H4M9FGMEKV9ZGDSN4M, source system LGDCLNT300 changed by source system LGTCLNT010 in import (tr STMS).
    I'm looking for opportunities to change the target source systems LGPCLNT010.
    Where can I find a setting to change the source system during the import?
    Thnx.
    PS LGPCLNT010 source system already exists in test. only need to assign LGDCLNT300 (DEV) -> LGPCLNT010 (TEST).

    Hi,
    The entries  are maintained in table RSLOGSYSMAP. Goto SM30 put the table name and click on maintain.
    Or simply goto transport connection from RSA1 and click on "Conversion button" on tool bar.
    Regards,
    Durgesh.

  • Transport management and Global trade system data to BI

    Hi All,
    We are trying to Extract Transport management (TM) and Global trade system (GTS) data into BI. Can you please let me know the standard Data sources and the process to extract the data.
    We are implementing EM, GTS and TM. Please let me know the process to extract the data into BI
    Regards
    Sathish.

    Hi All,
    I'm able to extract GTS data Now.
    Can any one please let me know how to extract Transport management data in to BI.
    Regards
    Sathish.

  • Cost of transport management system module ??

    Hello,
    I'm looking for an estimate on the implementation of an SAP Transport management module.
    Does anyone have a clue what this module cost ? And what time it takes to implement on an existing SAPR3 system ?
    Thanks

    Hi Tobias,
    Juan mean to say here that in the 1st run the transport failsed for some reason and in the 2nd run the same transport request imported successfully with warning (Yellow light).
    Any way import is over.
    Regards
    Ashok Dalai

  • A transport package during a BC installation

    Hi all,
    During and installation of some objects from business content appears a message about including my installation process as a subrequest into already existed request. And then it says that I cannot use that request. But there is no possibility to create a new request. It is automatically included into the old one. Where can I look at to figure out the reason of this? And how can I fix it?
    Thanks in advance.
    Best regards,
    Eugene

    Hi Eugene,
    A. As it's an old request, and if there's no problem in deleting this request, can you change the owner for this transport request in SE10 (using the icon a/b) to your name and try deleting it? Then you should be able to assign your components during business content activation to a new request that you can create on the fly, or create a blank request beforehand to assign the BC components.
    B. Or alternatively can you check this request to see if the "target" is filled in already, one possibility is that this may be a local request and you may need to change this from "local" to "transportable" by specifying the target system.
    C. Can you check to make sure your transport management system is functioning properly.
    Hope it helps,
    Sree

  • CHARM during implementation phase possible?

    Hi Gurus
    I would like to know the constraints of implementing CHARM during the implementation phase of the project.
    I am aware that, charm functionality is best suitable for post go live change tracking tool and it is not recommended during the implementation phase. But I would like to know the reasons behind not recommending CHARM during implementation phase.
    Please provide your valuable inputs.
    Thanks.

    Hi,
    The following may not be the detailed reasons behind not recommending CHARM during implementation phase.
    Implementation Project u2013 A project to implement SAP solution as a part of regular implementation or a roll out. This is considered for single-site implementations. Predefined scenarios can be selected from template projects.
    Change Request Management (ChaRM) is an SAP tool to manage all those activities performed between the design of a change and the final promotion to a productive system
    ChaRM can:
    o Improve efficiency and transparency of change management processes
    o Minimize business disruptions
    o Store documentation of implemented changes
    o Track and monitor changes
    o Improve audit process
    o Reduce risk of correction and project failures
    ChaRM benefits are:
    o Allow the Organization to control and manage changes in the SAP system effectively
    o Guarantee that any change to the SAP system follows the standard process flow and procedures with mandatory controls and documented steps
    o Effectively adheres to requirements for SOX compliance
    Please also go through [this|http://www.sap.com/community/webcast/2009_06_worldtour_fr/2009_06_Worldtour_SOL1_SAP_fr.pdf] document.
    Hope it helps.
    Cheers,
    Satish

  • Demo on SAP Transportation Management Overview + End to End Process Flow by Navin Nadpurohit-SAP TM Consultant - Krypt Inc-a Leading SAP Supply Chain Company

    Hello All,
    Attached is the link explaining SAP Transportation Management Overview and a system demonstration of End to End Process Flow.
    Link:
    TM Overview + End to End Process Flow - YouTube
    Thanks and best regards,
    Navin

    Very Good Demo Navin

  • Transport Management System with Solution Manager

    Dear all,
    Do you know the function transport management system(TMS) with solution manager, I already search in SAP document but not found this function.
    Do you know how to config solution manager for TMS and documents related with this function please guide for me!
    Thanks all very much !

    Hi,
    Check this link.
    https://websmp103.sap-ag.de/~sapdownload/011000358700000508502008E/ChangeRequestManagement.pdf
    Hope this answers your questions.
    Feel free to revert back.
    -=-Ragu

  • Transport Management in SOlution Manager

    Hello All,
    We are currently running a Conf. Room Pilot for our customer. As part of the CRP, the customer has created a new template project in Solman and have also a created a new sandbox as a copy of their production for the CRP where we have got full access.
    The customer wants us to use SAP transport management functionality in Solman where all transports & changes made in the sandbox can be tracked and they can be moved to their production if required using solution manager.
    Now customer doesnot want to configure ChaRM.
    Two possiblities I see are
    1. Create an IMG project in Sandbox system through Solution Manager and in the Sandbox systems' project activate CTS functionality. Give TR Create authorization to team members with restriction of assignment to CTS project only. (Dis-allow TR creation w/o CTS project assignment in Sandbox)
    2. Activate Change Request Management (ChaRM ) in the template project with only CTS functionality (No other functionality of ChaRM is useful here). At the moment I am not sure if this will be allowed.
    please let me know, how do I restrict creation of TR without assigning to CTS?
    Regards,
    Shyam

    Any answer to this?