Transportation cost before the reception of the material in MIGO (Stock in transit)

Does it exist a way to make a reception of materials in transit and post the transportation cost before the reception of the material in MIGO ?
The  material is own of company before to be receipt in plant.  We need to pay the transportation before that material is arrived at plant. 
As the value is an important cost, we need that this cost be linked with the cost of the material.  We can put a condition, but it does not work if the material in not receipt in MIGO.  We can enter a subsequent debit memo, but the invoice of the reception should be enter in the system and by the way the reception too.  So how should we process to link the transportation cost with the material if this material is not received at plant and by the way in MIGO.
Thanks in advance

Hi,
   As of my knowledge, system will allow to process the shipment document - create shipment cost document and vendor invoice also, even before doing GR for the PO. Please check the scenario and revert back if you are getting any error.
   If you want the shipment cost as delivery cost, refer the note: 427944 - Info: Shipment costs as delivery costs during goods receipt
Regards,
AKPT

Similar Messages

  • Transportation Cost to be Settled with the Invoice

    Dear Friends,
    Is there any way in which we can transfer the Shipment cost components to the Billing and get it settled along with other conditions for pricing while releasing to accounts.
    Please advise.
    Regards,
    Harsh

    > Dear Friends,
    > Is there any way in which we can transfer the
    > Shipment cost components to the Billing and get it
    > settled along with other conditions for pricing while
    > releasing to accounts.
    >
    > Please advise.
    >
    > Regards,
    > Harsh
    Hi
    Transportation cost can be added at the time of delivery creation.you can create separate pricing procedure for delivery document type.
    Meghalinagm

  • Forbid the reception of the same SN already in stock message IO231 in error

    Hello Experts,
    I am discovering that is possible to recieve the same part number with same serial number in the plant.
    Expl: receive agaisnt PO1 the part number A with SN1, then i can receive again the same part 1 with the same SN1 in the plant.
    How can we manage to raise error message at reception in MIGO for this case?
    How can i change message IO231 which is in warning know to an error message at reception.
    Thanks
    regards
    Edited by: Moomoz on Jan 6, 2012 5:11 PM

    Hi,
    Thanks for reply.
    The transaction PMS1 doesn't exist. Could you please check?
    For TC: S_ALR_87000304 it is going to customizing Serial number parameter, nothing related to the check box you are indicating
    And the field is already checked
    Thanks
    Edited by: Moomoz on Jan 9, 2012 6:16 PM
    Edited by: Moomoz on Jan 9, 2012 6:27 PM

  • Is the reception of iPhone 5c better than 5s.

    Was advised at a Telstra store that the reception of the iPhone 5s was worse than that of the 5c. Am thinking of upgrading from 4s.
    Has anyone experienced this?

    Not sure about the 5C but the 5S is hugely worse than the 4S for data. And tethering is a dead loss in poor signal areas where it would work reliably with the 4S.
    However it's not that simple - the 5S voice call performance seems BETTER than the 4S. I did a 45 minute call yesterday during a drive through several known blackspots where my 4S and indeed other non-Apple phones reliably drop the call, and not only did the 5S maintain the call but I didn't even have any dropped audio at all.
    But despite the audio being solid I couldn't get ANY data out of it at all - and yes it was on 3G so should have been able to do voice and data simultaneously.
    So my guess is a serious bug in the firmware or baseband around data handling rather than inherently poorer hardware in the 5S. Or at least that's what I hope as one wouldn't expect a newer phone to be worse than the previous model especially after the bizarre mess of the iPhone 4 and antennagate!

  • Improving WiFi reception on the receiving end?

    I did numerous searches and couldn't find any info that pretained to my problem. We travel extensively in our motorhome to a lot of places that provide wifi, but in many cases, I either get a very low signal or no signal at all because of distance from the antenna. Is there anyway to improve the reception on the MacBook Pro? I see an external antenna by C. Crane that is supposed to work with the Mac. Any input on that or a solution would be appreciated.
    Thanks in advance.

    Looks like a visit to Apple then ?
    Cheers
    Brian

  • Assignment of the asset during the equipment creation

    Hello everyone,
    I am currently working on the PM-AA interface which consists in linking the asset field (ITOB-ANLNR) of an equipment with the asset number given in the purchase order. The goods receipt (MIGO) creates automatically an equipment (thanks to the serial number profile of the materiel).
    As the purchase order contains the asset, I expected that the system would put this value in the corresponding field of the equipment.
    In the customizing, we have made the following changes :
    - equipment is modified synchronously with tha asset modification
    - the assignment of master data fields of assets and equipment includes the asset fields itself
    - the serial number profile is assigned to the material and allow the creation of the equipment during the goods receipt.
    Has someone already experienced this case? What do I have to do to have the asset number saved in the equipment during its creation?

    Hi Paul,
    Thanks for you answer.
    I've already checked these customizing aspects but tjey are not saisfying enough : my customer wants the equipment to be created at the goods receipts in order to save the serial number registered during the reception.
    Furthermore, I'm not sure of the process if I create the equipment formerly : will it take into account the material and serial number that are given during the reception of the goods? And how does the system react with more than one equipment?

  • What is the deal with the Zen Aurvana headphones?

    Can anyone explain this to me? (Please note that I am a review addict, and look at reviews before buying anything so I don't make a regretful choice. One of the things that sealed my decision on the Zen was the 8.3 from CNET.)
    I've been deciding to upgrade from the Zen's EP-480 set for a few weeks now, and it's a tossup between the Aurvana and the EP-630.
    Problem is, everywhere seems to report that the Aurvana is very average. Looking at customer reviews on retail sites and media critics, they all barely rate the Aurvana above average. Looking in the same sources at the EP-630, it has a close to perfect score from various ones.
    Now, here's what blows my mind. I stumble upon Creative's European site, and the reception for the Aurvana is better than the EP-630 set. Other countries seem to love the Aurvana more than the EP-630, while the US does not. See for yourself:
    http://hu.europe.creative.com/produc...397&nav=awards
    http://hu.europe.creative.com/produc...702&nav=awards
    What's the deal here? I need help with my decision from fellow Creative fans. Has anyone owned both?
    Message Edited by BetaWolf on 02-15-200802:57 PM

    I use it quite a bit for zooming in and out (by dragging up and down) but you have to be careful you don't move left or right when doing this as it then becomes a bit unpredictable as you say...
    If you just want to use the playhead for dragging left and right (and if you can't find a pref to turn it off) you'll just have to be careful to drag only in the horizontal axis and not up or down..
    Cheers
    Robo

  • Change the valuation class of material [Stock transport order scenario]

    Dears,
    Client would like to change the valuation class of material.
    There is no open Purchase order/Process order/Purchase requistion and stock in plant.
    Scenario- One Stock transport order is created.
    For same goods issue (351-issuing plant) and goods receipt (101-receiving plant) is done.
    When we are going to change the valuation class of said material, message is "purchase order is open
    and it shows the no of STO [for which receipt and issue is done]"
    To resolve this issue we had first delete the STO line item no(ME22N). Then change the valuation class.
    (this allows). and then undelete the STO line item. Through this we can change the valuation class of material.
    Please advise in such business process that this is right way or there may be other option.
    Thanks & Regards
    Rajan

    rajanshah219,
    Here's my take on how to fix:
    *Manually change Config TCode OMT4 - change message MM 326 & 327 to type "W"   (if open order exists...now you can enter through warning messages)
    *If inventory exists, then issue out of stock to a cost center
    *Change valuation class
    *Put stock back into inventory (reverse to that same cost center)  Note issue out and reverse back into inventory must happen in the same posting period.
    **Valuation class should be changed as expected
    **Manually change config  TCode OMT4 - change message MM 326 & 327 back to type "E"
    Thanks,
    Jason

  • How to post Unplanned Delivery Cost before the actual invoice

    Hello Experts
    Our client has a scenario when they received the unplanned Delivery cost before the actual invoice of that purchase.
    We are handling the Unplanned Delivery cost by entering on the header level on the regular scenario.
    Can somebody give there exert thought how we handle the Unplanned Delivery Cost Invoice before the actual Invoice.

    Hello,
    It is a process issue and I have seen similar situtations. Here is a possible solution.
    1. You should estimate the standard freight and put this as part of Material Cost.
        This can be a condition type or it can come from PIR, depending upon how you
        calculate the material cost.
    2. At the purchasing level, add a condition type for Freight. So, at the time of GR,
        system will automatically accrue the freight amount. This will be based on the
        esitmated amount and not the actual amount. You can capture the offset  
        account in a separate accrued freight payable account.
    3. At the time of processing the actual freight invoice, debit the accrued freight
       payable account.
    4. On regular basis watch your estimated and actual freight expenses and make  
        necessary adjustments.
    Hope this helps.

  • How frieght cost can be incorporated in the price of the material ?

    Hi Friends,
    Requirement is frieght cost should be incorporated in the price of the material .How this should be configured  'Sales Order value greater than equal to 15000,then frieght cost is free '.
    If it is less than 15000,frieght cost levied.How to calculate freight cost?
    One way we found is adding new requirement type or alternate calculation type in the pricing procedure.How far is it correct?My approach is correct or not.
    Some customers picks up the mateials from the warehouse itself.The sales commission caluculation will be different for this kind of orders. How to identify pick up orders without configuring new order type??How to calculate sales commission for these kind of orders?
    Our client is not interested to configure seperate order type.
    Can any body have ideas ,how best can be approached for  this?
    Thanks in advance...VM
    Edited by: vm on Mar 10, 2009 7:48 PM

    Hi VM,
    In the new conidition type created by you for frieght cost you need to make use of scales to maintain pricing based on the quantity.
    Firstly make sure that you have made Calculation Type as 'C' in control data for this condition type.
    Then in VK11 create a new condition record. Click on sclaes for this condition record and maintain the minimum frieght charge that you need to apply based on the order quantity.
    eg: Lets consider the example given by you. For all orders less than 15000 units you need to apply freight charge of 100 USD. So in sclaes you will enter values as follows
    Scale Quantity.........UOM........Rate.........Unit...........Per...........UoM
    .................................GA..........     10............USD.........1...............GA
    15,000.............................................................................................
    Now if an order is created for 15000 GA based on sclaes no rate will be applied. But if an order is created for qty less than 15000 GA a rate of 10 USD per GA will be applied.
    Hope this helps.
    Regards,
    Sajith.

  • Material cost updating in COPA at the time of Billing and Delivery 2 Time.

    Hi All
    I had created sales order( MTO).
    Sales Order No 61224069 u2013 50
    Sales Order line item 40 created > PR & PO created (MD02) > MIGO > Delivery of Order (VL01N) > Settlement (VA88) >Billing( VF01) > Settlement (VA88).
    I have two COPA Document and Material Price updating 2 Time in COPA report.
    Please let me know Its Process error Or Configuration error.
    If Process -- Please let me know the correct process
    If Config -- Please let me know where to check
    Thanks In Advance.
    Alok Dixit

    Hi Ajay
    Thanks for the reply.
    The COPA Documents Generated 2 Times through settlement.
    *When document generated.*
    1 After Delivery Sales order is settled
    2 After Billing  Sales order is settled
    *What sort of value*
    There i maintain the PA Stracture as same as CCS. But in the COPA report system is updating Material Cost 2 times.
    *Record Type*
    Record Type for documents is C in both cases
    Settlement after Billing  & Delivery.

  • How to include some costs  in standart price on the base of material costs?

    Hi,
    the current client want to include some costs in standart price for the material on the base of raw material costs (according to bill of material). "Some costs" are costs for whole plant or workshop: electricity, gas, salary of some wokers an so on. These costs can not be ascribe to concrete finished products, but must be included in cost of goods manufactured. I assume to use cost center to collect these costs. Direct costs for raw material collects on cost collectors.
    Now the problem by standard cost estimate:
    1.The balance this cost center must be zero (it follows flegal requirements). Therefore I can not use overhead rates. Or I don`t know something?  
    2. I can create activity type, calculate its price on the base of planned costs of this cost center and use it in operation in routing for finished product. But in routing I can not use the costs of raw material to determine how many units of activity type must be confirmed. I can make only rule like: 1 Unit finished product - 1 Unit of activity type.
    So, no chance?
    P.S.
    In fact there is no problem - I can use distribution of cost objects hierarchy
    Best regards,
    Yury
    Edited by: Yury Pogorelov on Jun 17, 2009 4:33 PM
    Edited by: Yury Pogorelov on Jun 17, 2009 4:33 PM
    Edited by: Yury Pogorelov on Jun 17, 2009 4:34 PM
    Edited by: Yury Pogorelov on Jun 17, 2009 4:35 PM

    Hi Anu,
    Putting the resource files in WEB-INF/classes is the correct and good way!
    Simon

  • Scrap cost generated is more than the raw material cost

    Dear Gurus. Please help me in this scenario
    The conversion cost of the material is lesser than the scrap cost when the material is sent to vendor for any grinding operation, in such cases we need to recover money from vendor.
    Eg:  Conversion cost is Rs 100 , Scrap generated value is Rs 800. Hence Rs 700 needs to be recovered from vendor.
    How to put this in Info record? and how to handle this situation in PO and further process?

    Hi,
        Please create new material code for the scrap mateirial.
    Now your sending material code is 1000 and receving material code is 2000. While creating subcontracting po manually add scrape material code negative qty.
    So when you take GR for the material 2000, material 1000 go to consumption and scrap material posted to stock. Then created returnn purcahse order for scrap material to the vendor.
    I hope it will work.
    Ashish

  • Freight cost to be included in the Raw material cost while creating VL31N

    Hi all,
    We are purchasing raw material from other country. we are paying freight for the imported material.
    My requirement is, when doing inbound delivery freight cost has to be included in the raw material cost.
    Now its not getting included in the raw material cost.
    What are all the necessary steps to be done to include the freight cost into the raw material?
    Thanks in advance,
    Babu

    Hi,
    You can create dummy material inmaterial master record.
    You can enter the material manually while creating inbound delivery, which will come as unplanned delivery cost.
    Br,
    Tushar Patankar

  • Please maintain  the master data for material during product cost collector

    hi
    i get a error
    please maintain  the master data for material during product cost collector
    please guide me
    regards
    leo

    Hi Leo,
    Can you elaborate your issue, like when did you get the error exactly?
    If it is the error you got while creating Product Cost Collector, then this is not the right Forum to post.
    Please post your question in the 'ERP Manufacturing (PP)' forum
    Regards,
    Manimaran M

Maybe you are looking for

  • Plot with a printer

    I have a file with about 100 coordinates. For instance A= (0,0)  B= (10,0) and C =(0,5). Now i want to make a print from this three coodinates, in a way that the place and distances of the three points are exact good: AB= 10 cm, AC= 5cm and so on. I

  • Frm 40598

    Dear all, i have an item which REQUIRED property is set to yes i have a form level on-error trigger my :system.message_leve='25' when i try commit the form without providing the required fields it do not commit nor issue any message. in on-error trig

  • How to pick classes in atg

    Hi Guys How atg will pick classes for each componet I have deployed my ear file jboss but i did not find atglib folder inside ear Please tell me how atg will pick java files for each component

  • Daylight saving time changes - Netweaver Java

    Hi, For DST, we are planning to shutdown ABAP systems. What about JAVA systems, shall Hi, For DST , we are planning to shutdown ABAP systems. What about JAVA systems, shall we need to shutdown JAVA systems?? It would be great, if any one can provide

  • Problem-Loading Byte code from DB

    Dear all, have any one tried to load the bytecode read from the database. If so, please suggest me a way to do it. Iam developing a frame-work where nothing except a servlet would reside on the disk as a file. after designing the frame work, i've enc