WBS element exceed error

hi:
   We are using SRM5.0 with ECS.I transfer PR into srm with plan driven procurement.
   When I creat a PO for this PR and check it, the error message occurs,says item 001 wbs element *** exceed budget, I could not save the PO but hold it,so I think this error message was not the one from  R/3.I am just wondering ,what budget does the system check?
          Hope some could help me.Tks.

Usually, 99% of this issues can be solved when you read and understand the SRM budget check note 520717 and read as well the related notes esp. regarding the CO-report RKACSHOW -- here you see and understand, how and where the budget data are stored on CO-tables and how the AVAC - availibility control works.
You can debug as well -- out of the BBP_PD-Form PROCDOC_CROSS_CHECKS the FM BBP_PD_COMMITMENT_FILL_ITAB is called. Here the data are mapped into backend structures in way ERP-backend requires it. Before the RFC-call is made please look up how exactly the structures are filled. This is something you need to understand whether  there are some special tolerance-limits maintained on the CO side. You'll find these AVAC-tolerance limits in the CO-IO resp. WBS customizing (ask a CO-friend if you don't find it right away;). There you see exactly the tolerance linked to certain document type etc.
You can debug as well from the RFC call on -- once you're on the ERP side set a breakpoint at FM RWIN_CHECK -- here all check for Accounting are loaded. One of these checks refers to CO-AVAC. It is something like K_...BUDGET... or K_...OPEN_ITEM or K_...AVC....You have to look up yourself as this is just too long ago.
Cheers,
Richard

Similar Messages

  • Item 001 WBS budget exceeded error while posting cat7

    Dear Experts
    We have implemented the following modules
    PS , CO , HR
    The project system has number of projects ,
    the time booking is done using cats , the actual labour cost is entered in the cats sheet it self in the price column.
    for cost posting after the data is posted to HR system , we are using cat7 to post the data to controlling and PS module.
    Mostly all the data is transported , but for some WBS i am getting the following error
    Item 001 WBS element <wbs element name> budget exceeded  and the system is not allowing to post data to controlling for this wbs .
    What is the relavance of this error in context of HR ?
    This error is related to which module , PS , HR or CO?
    How do i reslove this issue.
    Regards
    sameer

    Hi,
    Check the budget Limit and allocation of WBS elemet.
    Tcode - CJ30 ,CJ31.
    Check the budget avaialability control as well.I think the message is coming from availability control.
    check transactoin CN41,CJBN.
    check this link
    http://www.sap-img.com/ps001.htm
    Manoj.

  • WBS element creation error

    Hi All,
    I am trying to create WBS element using BAPI BAPI_BUS2054_CREATE_MULTI. The sequence is as follows:
    BAPI_PS_INITIALIZATION
    BAPI_BUS2054_CREATE_MULTI
    BAPI_PS_PRECOMMIT
    The error while creating element is :
    Final check of the project definition and the WBS elements: Error
    Any pointers on this why I am getting this error and what needs to be done?
    Thanks,
    Seema

    Hi Seema,
    After the BAPI BAPI_PS_PRECOMMIT you have to call explicitily
    COMMIT WORK AND WAIT.
    You can have those details in the documentation of the BAPI "BAPI_BUS2054_CREATE_MULTI".
    Regards,
    Smart Varghese

  • WBS Element settlement error

    Dear All
    My query is the prj is EP & WBS El is EP-99, under EP-99 the avialable values are Rs192,523/- as per different cost element wise. Those values have to settled on an one AUC-asset & the value will be settled periodicaly. My posted values are in 10th/2008 & I want to settled the said  values in 10th prd. But after processing of CJ88 the error has been raised "There no accured amounts settlement is not possible" Also note that Other WBSE has been settled under said prj.
    Please help me.
    Regards
    Avijit Barman

    Dear All
    My query is the prj is EP & WBS El is EP-99, under EP-99 the avialable values are Rs192,523/- as per different cost element wise. Those values have to settled on an one AUC-asset & the value will be settled periodicaly. My posted values are in 10th/2008 & I want to settled the said  values in 10th prd. But after processing of CJ88 the error has been raised "There no accured amounts settlement is not possible" Also note that Other WBSE has been settled under said prj.
    Please help me.
    Regards
    Avijit Barman

  • Message error Item wbs element budget exceeded

    Hi
    when I do a purchase requisition imputed to WBS element, WBS element consuming, but when I'm going to make the budget document of the reserve (R) in a transaction FMX1 jumps me an error message:wbs element budget exceeded ,it is trying to consumed WBS element , when it has consumed in the purchase requisition.
    I have solved it error with limits tolerance but in the funds commitments consumed other time , we see these results  in the report S_ALR_8713558.
    Where is the problem????
    Than you

    You have to differentiate the beaviour of the availability control in customizing for PS > Costs > Budget > Define tolerance limit
    With the "transaction group" you can differentiate for:
    ++     All activity groups
    00     Purchase requisition
    01     Purchase order
    07     Funds reservation
    Ciao
    Giorgio

  • Error in WBS element while doing the purchase requisition

    Dear All,
    While doing the purchase requisition in ps
    the error is : Item 010 WBS element IN05-PR09-16 . 04 budget exceeded.
    Kindly parovide any solution.
    Best Regards,
    Venkat.

    Hi Venkar,
    Check the available budget against WBSE - IN05-PR09-16 . 04 (S_ALR_87013558 - Budget/Actual/Commitment/Rem Plan/Assigned ), and the PR amount. Available Budget should be more than PR amount. Based on the tolerance limits set for the  budget profile, maintain the Current Budget with budget updates and try to create a PR accordingly.
    Hope this solves your problem !!
    Br
    Hari.
    Edited by: Hari Krishna Kudaravalli on Aug 20, 2009 3:25 PM

  • Budget exceeded WBS element

    I am creating purchase order for WBS element of amount 76214 USD but getting error Budget exceeded. Details of WBS element is (checked through CJ31) Distributable 807,800.00  USD and  Assigned 847,753.97  USD.
    Please can you help how to check balance amount in WBS element.

    Hi
    Please note that distributable amount is the figure on that particular WBS element which can be utilised on it or can be on its lower level WBS elements. Assigned value is total of commitment and spent value.
    In you case assigned value is more than distributable - it means full value is utilised on this WBS element.
    You need to check under CJ33 for the released value and assigned value.
    or if you want to know available amount then use the report s_alr_87013558 or S_alr_87013561.
    And also check the tolerance % for excess amount that can be spent on WBS elements in configuration through PS -> costs -> budget -> tolerance limits.

  • WBS Element Budget Exceeded.

    Hi All,
    During creation of Excise Invoice in T.Code J1IIN we get an error (MSG NO. BP603) WBS Element Budget Exceeded.
    Ideally the same should not as we are posting the income & not the cost.
    Please Guide.
    Regards,

    Hello,
    I don't think that's a workflow question, maybe another forum would be able to help you out.
    regards
    Rick Bakker
    Hanabi Technology

  • Runtime error on Project/WBS element release

    Hi All,
    I am trying to release a WBS element, however the system hangs and eventually causes a runtime error. How do I rectify this?
    Thanks in advance.
    Regards,
    PS_PS01

    Hi,
    I have done that already. This problem is 4 days old. Everyday I log off, then log in.
    The error meassage reads: "time limit exceeded. The program "SAPLCJDW" has exceeded the maximum permitted runtime without interruption and has therefore been terminated."
    Is there perhaps a note I can apply to correct this?

  • Error while Creating WBS element using BAPI 'BAPI_BUS2054_CREATE_MULTI'

    Hi Expert,
    I've a requirement to create WBS elements using BAPI. And I am using BAPIs in the following manner.
    CALL FUNCTION 'BAPI_PS_INITIALIZATION'
      CALL FUNCTION 'BAPI_BUS2054_CREATE_MULTI'
        EXPORTING
          i_project_definition = g_pdwbs
      TABLES
        it_wbs_element             = it_wbs_element
       et_return                  = it_return
      EXTENSIONIN                =
      EXTENSIONOUT               =
        CALL FUNCTION 'BAPI_PS_PRECOMMIT'
          CALL FUNCTION 'BAPI_TRANSACTION_COMMIT'.
    When I do so I am getting the below errors. Please suggest.
    "Individual check for creating the object WBS Element C-497082 required ".
    "Individual check for creating the object WBS Element C-497082-0001 required".
    Please suggest how to correct this error. 
    <REMOVED BY MODERATOR - REQUEST OR OFFER POINTS ARE FORBIDDEN>
    Edited by: Alvaro Tejada Galindo on Aug 18, 2008 5:25 PM

    I am getting the same error, but I cannot figure it out how to detect it and fix it.  Will you please share your solution?
    Thanks,

  • Error while creating WBS element.. regarding source structure

    I am creating a project and then a WBS element. Its a investment project. While creating WBS element XXX, it gives me error that "WBS element XXX: SOurce assignments for source structure A1 missing in Investment Profile ZZZZZ."
    What shall I check? what could be the reason?
    Thanks,
    A

    hi,
    In this IMG activity, you define the source structures used when settling and costing joint products.
    A source structure contains several source assignments, each of which contains the individual cost elements or cost element intervals to be settled using the same distribution rules
    Just consult with your CO Consultant...
    Venkatesh

  • Error while uploading Journal with wbs element

    Hi SAP Folks,
    I am trying to upload journal through a customized transaction.
    The journal line item has wbs elements in it.
    While uploading journal it is showing the below error only when I am using a particular cost element from XXXX Cost element group.
    For other cost element from ZZZZ cost element group, it is not showing any error.
    ERROR: This G/L Code is only valid for Capital Projects (C-WBS elem.
    Is there  any transaction code which will link the cost elements to the project codes.
    Please help.
    Thanks in advance.

    Hi Paulo,
    This G/L code is only valid for Capital Projects (C-WBS elem
    Message no. ZCO002
    Prerequisite
    CO Area = 'XXXX'
    AND G/L >= '10000' AND G/L <= '19999'
    Check
    ( WBS Element >= 'x.1' AND
    WBS Element <= 'x.9.99.999.9.9.9' )
    OR
    ( Network >= 'x1' AND
    Network <= 'xZZZZZZZZZZZ' )
    OR
    ( Order >= '700000000000' AND
    Order <= '799999999999' )
    "| PM Orders can use Capital GL codes for Capital Works |"
    Message
    message type - E
    message no. - 002
    Message class - ZCO
    message text - This G/L code is only valid for Capital Projects (C-WBS elem
    Do i need to change anything.
    Error message no. ZCO002 is matching with the message of Validation.
    How do I proceed further??
    Thanks in advance
    Regards,
    Sophia

  • Error - Settlement for WBS Element

    Dear All
    My query is the prj is EP & WBS El is EP-99, under EP-99 the avialable values are Rs192,523/- as per different cost element wise & the values has been posted/transferred the reposting transaction from another wbs element. Those values have to settled on an one AUC-asset & the value will be settled periodicaly. My posted values are in 10th/2008 & I want to settled the said values in 10th prd. But after processing of CJ88 the error has been raised "There no accured amounts settlement is not possible" Also note that Other WBSE has been settled under said prj.
    Please help me.
    Regards
    Avijit Barman
    Edited by: Avijit  Barman on Feb 25, 2008 12:06 PM

    Dear Sreenivas
    My issue is solve but not from note. I convert status from REL to TECO of  WBS element & set the full settlement & prd 11 instead of 10th. Then run & its ok.
    Regards
    Avijit

  • Error Individual check for creating the object WBS Element required

    Hi Expert,
    I've a requirement to create WBS elements using BAPI. And I am using BAPIs in the following manner.
    CALL FUNCTION 'BAPI_PS_INITIALIZATION'
    CALL FUNCTION 'BAPI_BUS2054_CREATE_MULTI'
    EXPORTING
    i_project_definition = g_pdwbs
    TABLES
    it_wbs_element = it_wbs_element
    et_return = it_return
    EXTENSIONIN =
    EXTENSIONOUT =
    CALL FUNCTION 'BAPI_PS_PRECOMMIT'
    CALL FUNCTION 'BAPI_TRANSACTION_COMMIT'.
    When I do so I am getting the below errors. Please suggest.
    "Individual check for creating the object WBS Element C-497082 required ".
    "Individual check for creating the object WBS Element C-497082-0001 required".
    Please suggest how to correct this error.

    Hi Karthikeya,
    I think the project profile which you are using has a different mask and the WBS element you are passing is different to the BAPI.
    Are you able to create manually from CJ01 using the same WBS element?
    Create a project manually and it will give the list of the mandatory fields set in the config. Using that list populate the BAPI struture accordingly.
    Hope this helps.
    Thanks
    Lakshman.

  • Item 10 WBS element Budget exceeded

    Hello All,
    I am facing an issue while creating a PO with the newly created WBS element. I have followed the below steps in creation and release of the WBS Elements:
    1. The user has created a WBS element for the Financial year 2015, but the user allocated the budget in FY 2014.
    2. We have made the release value to '0' for the year 2014 and maintained the budget for 2015
    3. Released the budget via Tcode:IMCBR3
    But, I am still facing an issue while creating a PO that WBS element budget exceeded.  Please let me know if there is any other process to follow for this scenario. Kindly help.
    Thanks,
    Mercy

    hi,
    Increase budget for the WBS in CJ30 and then release in CJ32
    Regards,
    Rakesh

Maybe you are looking for

  • Can't open more than one document at a time

    I have to open a few text documents. No matter of they are three or six, sometimes it will open but most of times, they won't. Also, Pages won't start after jumping for a while in the Dock. If you open the documents from the Open menu it will work bu

  • Parse Problem?

    I'm rendering out an image sequence of a time lapse that was shot over two days. For some reason I can't render it out. Can someone tell me what this error message is? I tried to render it to the codec (APple Prores (HQ) an also the default Animation

  • Bank chains /  Intermediary banks

    All, I have setup intermediary bank and tested to see if it's working.  I'm expecting see DME file generated for Intermediary bank and update the REGUH table when I do the payments.  But, neither of them seems to be working.  The DME is genereted for

  • Desktop Troubles

    I'm having some issues with my drag and drop selection on the desktop for iMac. Whenever I click and drag one place on the desktop, the mouse seems to always show a selection about 3 inches above where I actually click. Also, files disappear on the d

  • 21.5" Flickering... No firmware for 21.5"?

    Been looking for help on this because I know there's a 27" firmware update for flickering, but what about 21.5"? It only does it when I reduce the screen brightness to the bottom three settings, but those happen to be my favorite! Just got this compu