WBS element settlement to an AUC

Hi Everyone,
WBS element is settled to an AUC asset on periodic basis and on completion of the project the AUC is settled to a regular asset; in this process once the project is complete its status is set to technically complete before settling the AUC to regular asset. Now, my question is if there is a requirement to continue the same project as a second phase meaning incurring the costs to the same WBS element which is set as TECO; is that something possible at all i.e,. to post the costs on a WBS that is technically complete? If so, then would it be possible to settle the second phase costs to a new AUC asset and so forth for third and fourth phases of the project.
Your input in this regard is highly appreciated and will be awarded with points.
Thanks in advance,
Kumar

Hi Abhilasha,
Thanks a lot for your input. I have one more question; according to your information once WBS status is set to TECO it still can take FI postings in that case would those postings be settled? If so, then could that be a AUC? I know you said a WBS can be settled to only one AUC but, the client here wants to settle it to a new AUC for the second phase of construction of the project. So, settling the WBS to a new AUC is not at all a possibility? Could you please confirm?
I did not quite understand the point that WBS can take FI Postings after it is set to status TECO, could you please clarify a little bit on that?
Thanks,
Kumar

Similar Messages

  • Settling the WBS element costs to an AuC

    Please Explain the procedure for settling the WBS element costs to an AuC & then to asset?

    Hi,
    Please follow the below sequence of steps for this:
    1) For WBS element where the asset has to be created, AUC willbe created automatically when the WBS element is in release status to get this investment profile should be assigned to WBS element in Control Tab
    2) You can see in the system status show as AUC to see the AUC number follow the path
        EDIT-> WBS element -> Investment program--> Asset under Construction where you can see the AUC which is created automatically
    3) Once the above two steps are through, for settlement to AuC goto transaction CJ88 give the WBS element number select the processing type as partial captalization and execute all the costs pertaining to that. WBS elements will be automatically settled to the AUC which is created for that WBS element
    Thanks,
    Prithwiraj.

  • Activate the field in WBS element settlement rule

    Hi Experts,
    In CJ02, when I am selecting any WBS element, Go to the details(TOP Menu), select  Settlement rule,
    (Top menu) In Settlement rule, some actions like,
         Create with Reference
         Save,
         Print
    this are not enabled,  Can anybody tell me how I /User can able to do it ?
    regards
    mdas

    hi
      In CJ02 > enter proj >  press Enter key or in left corner just below the screen text 2 icons are there, one for WBS & other for Proj. Click on WBS (Trangular )
      It will give you the detail WBS overview screen for the proj and you will get eveything.
    kkumar
    Edited by: kkbdsp on May 4, 2011 1:13 PM
    Edited by: kkbdsp on May 4, 2011 1:16 PM

  • WBS Element settlement error

    Dear All
    My query is the prj is EP & WBS El is EP-99, under EP-99 the avialable values are Rs192,523/- as per different cost element wise. Those values have to settled on an one AUC-asset & the value will be settled periodicaly. My posted values are in 10th/2008 & I want to settled the said  values in 10th prd. But after processing of CJ88 the error has been raised "There no accured amounts settlement is not possible" Also note that Other WBSE has been settled under said prj.
    Please help me.
    Regards
    Avijit Barman

    Dear All
    My query is the prj is EP & WBS El is EP-99, under EP-99 the avialable values are Rs192,523/- as per different cost element wise. Those values have to settled on an one AUC-asset & the value will be settled periodicaly. My posted values are in 10th/2008 & I want to settled the said  values in 10th prd. But after processing of CJ88 the error has been raised "There no accured amounts settlement is not possible" Also note that Other WBSE has been settled under said prj.
    Please help me.
    Regards
    Avijit Barman

  • WBS element is updated while settling cost from WBS to AUC

    Hi Experts
    At the time of settlement , when we settling the cost from WBS to AUC , WBS element is updated in AUC line item of accounting document , but it should not be updated actually.
    As result AUC cost is loaded on WBS and budget of WBS is get affected , furthermore system is not allowing for MIGO even budget is available but in CJ30 it is showing assigned value is more then original budget.
    Please suggest.
    Thanks & Regards
    shailesh

    Hi Saurabh ,
    I totally agree with you , but in our case system is not allowing(Error Message: Budget Exceeded) MIGO against capex PO - > WBS.
    Note : in our case , system is checking budget at the time of MIGO also.
    in our case , report  S_ALR_87013558 is showing wrong actual value and  also in CJ30 , total assigned value is larger then total distributable budget , As result our available budget gets negative figure in report S_ALR_87013558 , even i have already run CJEN->CJBN 2 or 3 times.
    Note: Our Commitment value is correct.
    Actually , according to report S_ALR_87013542 , system is showing correct actual value , that means we have sufficient available budget for further MIGO's
    Now may be , due to WBS element is updated in AUC line item of accouning document of settlement (WBS to AUC) , system loads AUC values to WBS unnecessarily , our available budget gets negative figure.
    For your reference , i am attaching screen shot of accounting document which is generated at the time of settlement from WBS to AUC.

  • Which table has auc to wbs element relationship stored

    Hello everyone,
    I have to write a report on costs for AUC.  I have following scenario:
    auc1-----wbs2--internal order4
    ............... |----
    internal order3
    ............... wbs1----internal order1
    ............... |------internal order2
    ............... |
    auc2-----wbs3 -
    internal order1
    I tried my best to depict the scenario in the picture.....so basically i want auc1 cost.....now client does not want to see wbs3 element...since it is settling to auc2.....if i put in the project def in the following bapi(BAPI_PROJECT_GETINFO)...i get all the wbs elements..since there is a settlement from wbs1 to wbs3..is there any table which can give me relationship...or which can tell me that which wbs is settling for which auc....
    Thanks...i hope i was able to explain my question....
    appreciate the help....
    AS.

    Hi all, thanks for all the help and support on this...I found a way to get all the CO settlement doc numbers for a project and their relationship as sender and receiver..... first i went to anla and anek to get the AUC and the wbs settling to this AUC relatiionship...once i got my main wbs element...i found all the wbses for this project. I need to use the table AUAK, AUFK, and AUAA to get all that information. I got all my wbses for a project first....than I went to table AUAK with all these wbses...and found the belnr(settlement doc numbers)....this table does not give out complete settlement doc numbers for wbses....we need to go back to AUAK with the internal orders to get the belnrs for them as well....so to get all the internal orders for a project i went to AUFK....than i took these orders and went back AUAK with these orders and got my missing belnrs.... now I had all my belnrs for a project....so i went to table AUAA and did the select with these belnr...and since now i have the primary key the access is lighting fast....by doing that select i got all my relationship, i mean which settlement is goind where... mind you that I used AUAS to get the sender/receiver relationship with the amount....this is as well a cluster table but we have the primary key belnr(co settlement doc. numbers)...so no worries to get the data here as well.... here are my selects for AUAK, AUFK and AUAA....
    TYPES: BEGIN OF prps_ty, psphi TYPE prps-psphi, END OF prps_ty. DATA all_proj TYPE STANDARD TABLE OF prps_ty. DATA wa_all_proj TYPE prps_ty. TYPES: BEGIN OF objnr_ty, objnr TYPE auak-objnr, END OF objnr_ty. DATA lo_p_psp TYPE STANDARD TABLE OF objnr_ty. IF all_proj IS NOT INITIAL. SELECT objnr FROM prps INTO TABLE lo_p_psp FOR ALL ENTRIES IN all_proj WHERE psphi = all_proj-psphi. ENDIF. IF lo_p_psp IS NOT INITIAL. SELECT belnr objnr FROM auak INTO TABLE tab_auak FOR ALL ENTRIES IN lo_p_psp WHERE kokrs IN p_kokrs AND gjahr IN p_gjahr AND objnr = lo_p_psp-objnr * AND objnr LIKE 'PR%'. SORT tab_auak BY belnr. DELETE ADJACENT DUPLICATES FROM tab_auak COMPARING belnr. SELECT aufnr objnr pspel FROM aufk INTO TABLE tab_aufk FOR ALL ENTRIES IN lo_p_psp WHERE bukrs IN p_bukrs AND kokrs IN p_kokrs AND pspel = lo_p_psp-objnr. ENDIF. *get the belnrs for orders---this part is very important or we miss out all the belnrs for I/O... IF tab_aufk IS NOT INITIAL. SELECT belnr objnr FROM auak INTO TABLE tab_auak2 FOR ALL ENTRIES IN tab_aufk WHERE kokrs IN p_kokrs AND gjahr IN p_gjahr AND objnr = tab_aufk-objnr. ENDIF. *append these new belnrs to tab_auak LOOP AT tab_auak2 INTO wa_tab_auak2. * CONCATENATE 'PR' wa_tab_aufk-pspel INTO wa_tab_auak2-objnr. APPEND wa_tab_auak2 TO tab_auak. ENDLOOP. SORT tab_auak. "by belnr. DELETE ADJACENT DUPLICATES FROM tab_auak. *now get all the belnrs for this project...complete list.... IF tab_auak IS NOT INITIAL. SELECT belnr aufnr pspnr anln1 coobjnr FROM auaa INTO TABLE tab_auaa FOR ALL ENTRIES IN tab_auak * WHERE pspnr = wa_wbs-posnr WHERE belnr = tab_auak-belnr AND emtyp = 'PR' AND bukrs IN p_bukrs AND kokrs IN p_kokrs. ENDIF. SORT tab_auaa BY pspnr belnr.
    I used our own indexes for all the transparent table accesses.... to speed up the process...you might want to create your own indexes depending on the where clauses for transparent tables..... well thanks again..and hope all this will help someone else too.... AS...

  • How to identify WBS elements with AuC status

    Hello Experts,
    We had earlier developed a report which determines whether the entered project id can be set to CLSD status or not. The problem arises with few WBS elements which have AuC statuses. The report is displaying them as closeable but we fail to close them through CJ20N. The problem is that the program captures the status of some projects as TECO but these projects have WBS elements which have statuses like "TECO BUDG AUC  SETCu201D because of which the system doesnu2019t allow CJ20N to close it. So can any one help me suggest any means by which we can detect whether any of a projects WBS elements are in the AUC status?
    Regards,
    Uday

    Hi Virendra,
    Thanks a lot for your inputs. I was trying to go through the tables in detail before I again get back to you about anything. From TJ02 I got to know that I0163 is the status code for Asset in construction costs. So I obtained the OBJNR values of all my WBS elements and I went through all the 3 tables TJ02, JCDS & JSTO that you had suggested. The data in JEST for 1 of the OBJNR values contained this I0163 value in 1 row. I wasn't however sure as to which particular status we could consider for the WBS from among the list. Is it something like the last row of the table would be the current status of the element & that all the other statuses just point to the various history of changes that it went through? (Am mailing you a copy of the same thread so that you would get the data displayed in a proper tabular format.)
    Regards,
    Uday
    MANDT   OBJNR              STAT    INACT    CHGNR
      400         PR00304257       I0001      X           002  
      400         PR00304257       I0002      X           004  
      400         PR00304257       I0005      X           001  
      400         PR00304257       I0028                   001  
      400         PR00304257       I0045                   003  
      400         PR00304257       I0064      X           002  
      400         PR00304257       I0067                   001  
      400         PR00304257       I0163                   001

  • Validation for the settlement rule of a wbs element

    Hi Experts,
    I have a requirement that in which i have to validate the settlement rule of the wbs done through t-code cj01/cj02/cj07,cj20n.
    If the settlement receiver object is an G/L account (settlement category g/l )  then i have to check that if it is an o&m project type
    wbs element  settling on some already mentioned G/L e.g 0001081340,0001081341, then  it should through some error  like settlement rule not valid etc.
    I have tried cjb1/cjb2 through badi WBS_SETTLEMENT_RULE by creating some strategy but it did not have any option for G/L
    settlement reciever. Also client will not agree to this as they want to create settlement rule manually.
    I have also tried the exit 'EXIT_SAPLCOI1_027 ' but its not getting triggerred during settlement rules assign mentand also i think it will not solve my purpose.
    Please help me as i am struck in this for long time now.
    Warm Regards,
    Hariom

    Hi Prabhu ,
    thanks for the quick update.
    I have tried many badi's and exits but they are not triggering at the saving time of the wbs.
    badi :
    PROJECTDEF_UPDATE
    WBS_FIELDS_FOR_ASSET
    WBS_USER_FIELDS_F4
    WORKBREAKDOWN_UPDATE
    WBS_SETTLEMENT_RULE
    exits :
    EXIT_SAPLCJWB_004
    EXIT_SAPLCJWB_005
    EXIT_SAPLCJWB_001
    These above exits i have tried either they are not implemented or they are not triggered during saving of a wbs element.
    please suggest any exit or badi's which you may have used.
    Thanks and regards,
    Hariom

  • Re: WBS Element

    Hi,
    Can anyone pls help me with WBS. I would like to have the configuration details for WBS element from Financial point of view. My main goal is to know the wbs element settlement procedure in asset accounting.
    Can you pls help with steps involved.
    Regards,
    Anirban

    for settlement of WBS you can use Tcodes cjic and cj88. You can settle the AUC to either Fixed Asset or expense it off to a cost center.

  • Function module to get the status of WBS elements IN Project Systems

    Hi,
    I am suppose to delete the WBS elements in PS depending on certain conditions. WBS elements that are to be deleted should satisfy the following conditions:
    1.     Status of WBS elements should not be  ‘AUC’ construction
    2. WBS element, which have cost association, like PO association or internal order association      shouldn’t be deleted WBS element does not have confirmed activities.
    3.     WBS elements, which have confirmed activity in association with their networks, should not be deleted.
    Either I can check for status of WBS for the above mentioned conditions or if u can suggest me some diff way I shall be grateful
    Need help in this regards.
    Thanks

    Hi
    Use the FM:
    <b>JV_GET_WBS_ATTRIBUTES</b>
    Regards,
    Sreeram

  • Settle PREL WBS element to AUC

    Dear,
    In certain cases customer wants to settle partially released WBS elements to fixed assets under construction.
    Is this possible?
    Cuurently I am having an error when settling ("System status Created is active"). However when I check the business process 'Actual Settlement" for the PREL WBS element it is stated to be active (green alert).
    rgds,
    bert

    This is standard behaviour of system as I understand.  In WBS system status hierarchy is like as below.
    CRTD->PREL>REL>TECO-->CLSD.  System set PREL when below level WBS 1.1 is REL, So, indirectly on 1 lEvel WBS will have both status active at same time i.e PREL and CRTD. So, Eventhough actual settlement is green in PREL but it is blocked by CRTD status.
    However, for confirmation you can alwalys check in SE38 CNSTATUS Report which disply you inconsistancy in System status.
    If someone have other openion / view please share. Interesting question !
    With Regards
    Nitin P.

  • Credit Memo to transfer AUC balance to WBS Element

    We have implemented Project Systems in a limited way and now need to transfer the current AUC balances into project WBS Elements.  
    The plan is to issue credit memo's from the AUC to a clearing account then mark the balance with a WBS Element.  When the month end project settlement is run the balance would move from the clearing account to a new AUC created by Project Systems.  The original AUC and the Project Systems AUC uses the same GL account for so there would be no effect on the GL.
    My question is does it matter which credit memo transaction I use, ABGL-in Invoice Year or ABGF-in Next Year?     These original AUC's have balances spanning several years including transaction in the current year.
    Thanks for any information or suggestion on a better way to move the balances.
    Jeff

    Hi,
    You are trying to post a credit memo again a purchase order since its via MM. Therefore how can you have a credit memo value exceeding the original invoice value?
    If you are trying to post an advance (as you have mentioned that you are receiving money to the project), it should be recored as an advance rather than a credit memo. Consider the double entry you want to post to.
    NW

  • Error - Settlement for WBS Element

    Dear All
    My query is the prj is EP & WBS El is EP-99, under EP-99 the avialable values are Rs192,523/- as per different cost element wise & the values has been posted/transferred the reposting transaction from another wbs element. Those values have to settled on an one AUC-asset & the value will be settled periodicaly. My posted values are in 10th/2008 & I want to settled the said values in 10th prd. But after processing of CJ88 the error has been raised "There no accured amounts settlement is not possible" Also note that Other WBSE has been settled under said prj.
    Please help me.
    Regards
    Avijit Barman
    Edited by: Avijit  Barman on Feb 25, 2008 12:06 PM

    Dear Sreenivas
    My issue is solve but not from note. I convert status from REL to TECO of  WBS element & set the full settlement & prd 11 instead of 10th. Then run & its ok.
    Regards
    Avijit

  • Can i change AUC attached to wBS element.

    1) can i change the AUC attached to WBS element ?
    2) user has already posted some entries to WBS but not settled so far. Can i change the AUC now ?
    3) In another WBS user has already settled to AUC the postings made in the firest month. I can change the AUC to that WBS element?

    VS,
    (the previous posting is also mine)
    As some of members also indicated, if you have created the AUC from IM then you cannot replace it with other AUC after deleting the first one. However, you can create another WBSE, create AUC (automatically if with IM). NOw you can JV or transer the amount posted to previous WBSE as credit posting. YOu can JV/tansfer the amount to new WBSE as debit posting.
    When settlement occurs, the previous AUC will get credit posting and will be zeroed, and the new AUC will get debit posting by regular settlement from new WBSE.
    Hope that helps you.
    Thanks

  • Settlement doc number & wbs element relationship table

    Hello,
    I am trying to find any tables which can help me get the settlement doc number and wbs element relationship.  Presently I am using table AUAA and here is my select for that:
    SELECT belnr aufnr pspnr anln1 coobjnr FROM auaa INTO TABLE tab_auaa
                        WHERE emtyp = 'PR'
                        AND bukrs IN p_bukrs
                        AND kokrs IN p_kokrs.
    since I do not have "belnr"(the primary key) it is taking too long to get this info.....any one has any idea of any other tables to get this information or a bapi?
    appreciate the help
    AS

    Hi all,
    thanks for all the help and support on this...I found a way to get all the CO settlement doc numbers for a project and their relationship as sender and receiver.....
    first  i went to anla and anek to get the AUC and the wbs settling to this AUC relatiionship...once i got my main wbs element...i found all the wbses for this project.
    I need to use the table AUAK, AUFK, and AUAA to get all that information.  I got all my wbses for a project first....than I went to table AUAK with all these wbses...and found the belnr(settlement doc numbers)....this table does not give out complete settlement doc numbers for wbses....we need to go back to AUAK with the internal orders to get the belnrs for them as well....so to get all the internal orders for a project i went to AUFK....than i took these orders and went back AUAK with these orders and got my missing belnrs....
    now I had all my belnrs for a project....so i went to table AUAA and did the select with these belnr...and since now i have the primary key the access is lighting fast....by doing that select i got all my relationship, i mean which settlement is goind where...
    mind you that I used AUAS to get the sender/receiver relationship with the amount....this is as well a cluster table but we have the primary key belnr(co settlement doc. numbers)...so no worries to get the data here as well....
    here are my selects for AUAK, AUFK and AUAA....
    TYPES: BEGIN OF prps_ty,
            psphi TYPE prps-psphi,
            END OF prps_ty.
            DATA all_proj TYPE STANDARD TABLE OF prps_ty.
            DATA wa_all_proj TYPE prps_ty.
    TYPES: BEGIN OF objnr_ty,
               objnr TYPE auak-objnr,
               END OF objnr_ty.
    DATA lo_p_psp TYPE STANDARD TABLE OF objnr_ty.
    IF all_proj IS NOT INITIAL.
              SELECT objnr FROM prps INTO TABLE lo_p_psp FOR ALL ENTRIES IN all_proj
              WHERE
              psphi = all_proj-psphi.
            ENDIF.
    IF lo_p_psp IS NOT INITIAL.
              SELECT belnr objnr FROM auak INTO TABLE tab_auak FOR ALL ENTRIES IN lo_p_psp
              WHERE
              kokrs IN p_kokrs
              AND gjahr IN p_gjahr
              AND objnr = lo_p_psp-objnr
    *        AND objnr LIKE 'PR%'.
            SORT tab_auak BY belnr.
            DELETE ADJACENT DUPLICATES FROM tab_auak COMPARING belnr.
    SELECT aufnr objnr pspel FROM aufk INTO TABLE tab_aufk FOR ALL ENTRIES IN lo_p_psp
              WHERE
              bukrs IN p_bukrs
              AND kokrs IN p_kokrs
              AND pspel = lo_p_psp-objnr.
            ENDIF.
    *get the belnrs for orders---this part is very important or we miss out all the belnrs for I/O...
            IF tab_aufk IS NOT INITIAL.
              SELECT belnr objnr FROM auak INTO TABLE tab_auak2
              FOR ALL ENTRIES IN tab_aufk
              WHERE
              kokrs IN p_kokrs
              AND gjahr IN p_gjahr
              AND objnr = tab_aufk-objnr.
            ENDIF.
    *append these new belnrs to tab_auak
            LOOP AT tab_auak2 INTO wa_tab_auak2.
    *              CONCATENATE 'PR' wa_tab_aufk-pspel INTO wa_tab_auak2-objnr.
              APPEND wa_tab_auak2 TO tab_auak.
            ENDLOOP.
            SORT tab_auak. "by belnr.
            DELETE ADJACENT DUPLICATES FROM tab_auak.
    *now get all the belnrs for this project...complete list....
            IF tab_auak IS NOT INITIAL.
              SELECT belnr aufnr pspnr anln1 coobjnr FROM auaa INTO TABLE tab_auaa
                       FOR ALL ENTRIES IN tab_auak
    *            WHERE pspnr = wa_wbs-posnr
                                     WHERE
                                     belnr = tab_auak-belnr
                                     AND emtyp = 'PR'
                                     AND bukrs IN p_bukrs
                                     AND kokrs IN p_kokrs.
            ENDIF.
            SORT tab_auaa BY pspnr belnr.
    I used our own indexes for all the transparent table accesses.... to speed up the process...you might want to create your own indexes depending on the where clauses for transparent tables.....
    well thanks again..and hope all this will help someone else too....
    AS...
    Edited by: J Are on Oct 31, 2009 1:19 PM

Maybe you are looking for

  • Ipod mini battery change

    Can someone walk me through changing a battery to an Ipod mini? Is the battery something that I can buy at a store near me? Is it something i can do on my own, or do i need to send it somewhere? Thanks for any help/information/guidance you can give m

  • Why doesn't my apple tv show up in my source list on itunes?

    I purchased a movie and then realized it didnt sync on my apple tv. So I go to my computer to see that the apple tv isn't listed in the sources. So far I have unplugged the apple tv, restarted it, restarted my computer, made sure all available update

  • Are Workbook settings stored in any table

    Hi Gurus, Are the workbook settings stored in any of the tables? There is a requirement for me to collect the information on whether the Refresh automatic has been checked or not for the workbooks. It would be great, If any of you can provide me with

  • Source Filename for Boilerplate image

    Hello - I am trying to use someone elses report in Oracle Reports 10g. They have many images in the report which, when I try to go into paper layout, cannot be found. Currently the property just lists the image name (ex - logo.jpg), and not the entir

  • OWB Runtime repository installing error

    Hello I'm a newbie here and in Oracle world. I'm student who tries to learn Oracle Warehouse Builder use on freetime, so any help would be appriciated. So the problem is, always when i try to install Runtime Repository (using OWB Runtime Assistant) i