Wrong planned cost calculation while actual is calculating correct for internal activities

Dear all,
I am facing an issue in which when i am doing network costing with work center, activity type, cost center and giving per hour rate in KP26. System is calculating correct actual cost but every time its calculating wrong planned cost. For example: If i have given per hour rate 60 usd when planning for 100 hrs in cj20n its showing 2500 while confirmation is working correct and for 10 hrs its showing actual cost of 600.
I have checked work kp26 also report KBST to make sure about rate. Also i have checked configuration related costing variant planned and actual and its standard PS02 and PS03.
I will really appreciate suggestions or some one face similar issue and got it resoved.
Thanks.

Dear All, this issue is resloved. I didnt give quantity in KP26. However i am more curious that most of the time i dont give any quantity in kp26 and always system works fine and calculate correct cost than why this time its calculating wrong planned cost.
Thanks all.

Similar Messages

  • Actual & planned costs calculated while creating Plant Maintenance Order

    Hi All,
    I would like to know how the actual & planned costs calculated while creating Plant Maintenance Order (PM Order)
    Thanks,
    Ajay

    You need to create an activity rate for 2014 for cost centre 51260201 and activity type NAHG20.
    This can be done via transaction KP26, but is usually performed by your Finance team.
    PeteA

  • IW33 : Good Issue but Cost show in Plan Cost instead of Actual Cost

    Hi All,
    Would like have your helping hand on below issue.
    Warranty Order been done the Good Issue but the cost still planning in plan cost instead of actually cost.
    Information as shown below.
    Thank you advise in advance.
    Trevor Wong.

    Abi,
    Can you see that there is a difference in the the actual costs reported on the Cost tab (350 RM), and those reported using the Rep Plan/Act button (1100RM).
    This is because the Cost tab costs are not correct.
    As pointed out by Maheswaran KD above, please run the correction program RIPMCO00 via transaction SE38/SA38, then check the Cost tab data again.
    PeteA

  • Plan Cost calculation problem

    Hi friends,
    I am facing problem in Plan costing part. When I run KOC4, & see Material Overheads, activity cost, it shows 0 agst Paln, but calculated agst Actual Cost.
    Is there any option to run for all plan order recalculation of costs in one go. If yes, what & how????
    regards
    Vikas

    Hi Amit,
    Thanks for your reply. I confirmed with my basis team that this note is already implemented in system but still we are facing this error.
    If any one help in this regard that will be really appreciable.
    Regards,
    AVI

  • Plan costs calculation during results analysis of sales order

    Hi Experts,
    I am in process of implementing sales order costing. I am facing a problem during result analysis with plan costs data.
    We have a sales order for which production order is generated. Cost object is sales order.
    Say, sales order cost estimate which is the plan costs --> is $ 1000 (which includes prod order COGM of $ 600) (So remaining sales and admin costs are $ 400)
    Plan cost of production order is $ 550 (as per production order cost analysis report)
    While calculating the result analysis for sales order, system is calculating the plan costs data as $ 1000 + $ 550 = $ 1550
    As a result, I feel plan costs data during result analysis is over calculated.
    I feel either plan costs should be $ 1000 (as it already includes COGM part)
    or
    $ 950 which is (plan cost of production order $ 550 + sales and admin costs of $ 400)
    Could some one explain me why result analysis shows plan costs data as $ 1500 and if I need to rectify how can I do so.
    Thanks,
    GAN

    Any suggestions please.
    Edited by: DSK on Feb 9, 2012 6:16 AM
    Edited by: DSK on Feb 13, 2012 4:39 AM

  • Work center planned cost calculation- PM related

    i have created a work center with t-code ir01, used in Maintenance order under operations tab. In cost tab, it is not showing Planned costs of the pm order. Please advise what are check ups or config settings should be done? Thanks.

    hi
    first kindly check whtether you have defined value categories, grouped the calue value categories then specified the defualt values categories for order,
    then plan for activity type and cost center specified in workcenter in KP26,
    also check whether you have specified the formula in the work center costing tab page
    regards
    thyagarajan

  • Fieldes planned delivery date and actual good recipt date for SAP QUERY

    Hi Gurus
    I am changing sap query. I need to find two fieldes  : planned delivery date and actual goods recipt date
    I dont know MM tables, do you know wrhere are?
    in table EKPO i don't find the fieldes.
    Thanks in advance

    Thank a lot!
    Regards

  • Costing Error No price could be determined for internal activity

    Dear Friends ,
    while i m trying to run costing in month tojune 2008 near fical year i recive follwoing error meaage how can i fix this error  kindlly send me details step becuase i m very new in FICO
    No price could be determined for internal activity 1405 1100-1100
    No price could be determined for internal activity 1060 1000-1000
    No price could be determined for internal activity 1055 1000-1000
    No price could be determined for internal activity 1110 1000-1000
    No price could be determined for internal activity 1610 1400-1400
    No price could be determined for internal activity 1050 1000-1000
    No price could be determined for internal activity 1405 1300-1300
    Regards
    Maheru

    Be careful with KP26, when you pass the initial screen, on the second screen where you can see the price,  you have to check the monthly price. You can do this from button Period screen (F6). Because in my case everything was OK, but I didn't have price for one of the months.

  • Actual Cost Calculation in Process Order

    Hi All,
    I updated Standard cost of a raw material through a cost estimate and also ran cost estimate of the FIN that is using this raw material but when I am creating a Process order, it is taking the cost of this particular raw material from the previous estimate not the recent one to calculate the target cost. Can any body help me with this.
    Thanks
    MKR

    Hi Ashok,
    My Valuation variants for the Costing Variant of Cost Estimate and Production order (Actual/Plan) cost calculation are in Sync to get the prices according to the price indicator in material master. But when it calculates cost for a production order, it is picking up cost from the previous period for that particular raw material. I have updated the standard cost by running the cost estimate but still its not working.
    Any lead on this. This will be really appreciated.
    Thanks
    MKR

  • Target cost calculation

    Hi All,
    In the production order, when we displays the cost analysis, we get Target cost. Can anyone please explain how the target cost for indirect activity allocation (ex:Machine hrs,Wage hrs etc.,) is calculated? I mean is there any specific formula or calculation involved in the same?

    Hi,
    In production order (CO03 --> Cost analysis) I want to know what different between Target cost & Plan cost & Actual cost?
    Total Plan Cost = Std Cost the material required to Produce X Planned Qty of the required material
    Target Cost = Std Cost the material planned to Produce X Std Qty of material required to produce, for Produced Actual Qty
    Actual Cost = Std Cost the material planned to Produce X Actual Qty of material consumed, for Produced Actual Qty
    For Example : Final Material - A,- Qty Planned to Produce - 2 nos
    As per Standards, Below Qty of Materials required to Produce A , for 2 Nos
    Mat B - 2Nos X INR 50 = INR 100
    Mat C - 4Nos X INR 60 = INR 240
    Activity Cost = 2 hrs X INR 10 = INR 20
    Total Plan Cost = INR 360
    Actual Qty Produced = 1 No
    Actual Consumption is as follows .
    Mat B - 1.5 Nos ( X INR 50 = INR 75 )
    Mat C - 2 Nos ( X INR 60 = INR 120 )
    Activity Cost = 2 hrs ( X INR 10 = INR 20 )
    So, Actual Cost = INR 7512020 = INR 215
    Whereas, Target cost for the Actual Qty ( of Product A - 1 Ns) is , as follows,
    Mat B - 1 Nos ( X INR 50 = INR 50 )
    Mat C - 1.5 Nos ( X INR 60 = INR 90 )
    Activity Cost = 1 hrs ( X INR 10 = INR 10 )
    Therefore, Target cost = INR 509010 = INR 150

  • SAP PM-Cost Calculation

    Dear All,
    Can you tell me how the cost is getting calculated through the order?
    Thanks & Regards
    Vishal Gadge

    Hi,
         Cost gets calculated based on the Costing variants .. for planned and actual each of them have a separate costing variants ..
    The costing variants are assigned to combination of order type & plant in spro
    The costing variants further have Costing type  and valuation variant. The valulation variants has details from where cost needs to be picked for cost calculation.Ex :-For material cost - cost to be picked from Moving average price ..check OKP6 /OKP8/OIOF
    Type of cost Estimate, Planned, Actual
    Estimate :- Can be entered manually
    Planned :- Calulated automatically based on the operation hrs /components entered
    Actual is also calculated automatically based on operations hrs confirmation in IW41, GI , GR for Non stock, S.E.S acceptance in ML81N ..
    How does the flow of costs works in SAP PM?

  • Valuation stragety "Net purchase price " for cost calculation

    Hi,i indicate "Net purchase price" used for plan cost calculation,but if there a many PO with different venfor for this material,how the system to determine which PO price used for cost calculation?
    thanks in advance

    Hi ajai,
    I agree with your point,we have 3 info record for a material and 2 are valid as such. The price maintained in  two info records are as 7.5 & 1.0 respectively(valid info records).
    The last price in the purchase order (of the info those records) are 0.41(dated on 09.04.2010)  & 0.2(dated on 19.04.2010) respectively, but when we execute the cost estimation the system picks the price of 7.5  not the least price of 0.2(as its the latest purchased price).
    Do let us know why and of what logic the system picks the highest price.
    Do revert.
    Regard,

  • Unable to copy Actual cost to Planned cost via CJ9CS

    I am trying to copy actual cost to planned cost for secondary cost elements via CJ9CS; currently there is a variance.
    How can I match my planned cost with the actual cost.
    We have already applied OSS note 304119 and we are on ver. 4.7.
    Has any one used enhancement COOMKPT4 and function exit EXIT_SAPMKPT4_010 Or is there any other way to copy the actual cost to the planned cost?
    Thanks
    Amit

    Hi Sudhir,
    Thanks for the quick reply.
    CJEN won't work for us, we are trying to find a way to fix CJ9CS.
    When we do CJ9CS the price is getting copied over from the price defined in KP26 instead of the Actual price.
    We have to find a way for the system to disregard the plan price while copying and just take the actual price.
    Any clues how we can do that?
    Regards
    Amit

  • Report for extracting the actual and planned cost from service orders

    HI all
    we are creating a report in BI for Module - Customer service . LIke , the report is all about how many complaints created in the system and how many completed technically and what is the cost involved for each complaint .
    Like we want the comparision between the planned cost and the actual cost .
    Now to give the logic to the BI Team for planned cost and actual cost , please suggest the flow of logic or table flow to arrive the planned and actual cost
    thanks in advance

    Hi Marthand,
    I am not sure which datasource your are using. In this case, you can use the 0VALUETYPE to differencitae between th eplan and actuals. Normally Plan which is budget will have value 050 and for actuals will have 010. For costs, you will have one key figure and at the reporting level, you will have the costs restricted by the value type for plan and actual to make comparisons.
    Hope this helps.
    Regards,
    Srinivas

  • Delivery cost calculation solution in SRM 7

    Dear all,
    We have a requirement to capture delivery costs associated purchases made via SRM. We would like to know if itu2019s possible to achieve the two scenarios indicated below. And if so, where and how do we enable delivery cost calculation process for SRM generated POs?
    Here are the 2 scenarios/requirements:
    Scenario 1.
    Shipping costs pre negotiated before a shopping cart is raised. When the PO vendor sends an invoice, shipping costs appear on a separate. We need a functionality to automatically calculate and add/capture these delivery costs to the SRM based PO and have the ability to match/pay for this when the vendor invoices.
    Scenario 2.
    Delivery costs such as fright costs are not know at the point the SRM PO is created. The PO vendor invoices only for goods that he delivers. Freight costs/charges have to be paid to another vendor - e.g. DHL. We need a functionality to automatically add/capture these Freight costs to the SRM based PO and have the ability to match/pay both the PO and Freight Vendors when they submit their invoices.
    Thanks in advance.

    Dear Poster,
    As no response has been provided to the thread in some time I must assume the issue is resolved, if the question is still valid please create a new thread rephrasing the query and providing as much data as possible to promote response from the community.
    Best Regards,
    SDN SRM Moderation Team

Maybe you are looking for

  • IMac Stuck on White Screen with Apple Logo

    Currently own: iMac 21.5" 2009 version with Snow Leopard, 4GB Ram, 500 GB Hard drive This computer was sitting in storage of my basement for 2 years because I was out of town on business. When I came home the computer worked fine. But earlier this ev

  • Trial version of Lightroom 4

    After downloading a trial version of Lightroom4 I get the following error message when launching the product "An error occurred when attempting to change modules" Could anyone advise how to solve this issue please?

  • Arabic pdf report

    hi we have uploaded a custom .rdf on the application, when we run this report with output text the arabic is shown fine but when we try to change the output to pdf the arabic is not readable (rubbish), is there a way to show arabic in pdf. we have re

  • Difference bwt PNP & PNPCE

    Hello SAP Minds, Can any one please focus on the difference between PNP and PNPCE with example. Thanks a lot for your support.

  • Partner Determination/Organization Structure

    Hi, I wanted to understand how through partner determination procedure relevant Service Team can be assigned. You can use example of Standard Service Order Transaction SRVO, Standard Partner Determination Procedure 00006, Standard Access Sequence 011