Order plan cost not appearing in PS report.

Dear PS friends,
I have an issue in order plan cost updation ( budget report ).
Used the prescribed WBS in maintenance order ( additional data ), but its not appearing in planned cost of CJ31 screen.
Checked the following
a)  WBS is account assignment element.
b) Network type order appended indicator in OPSV.
c) Setting in network type parameters for " determine plan  
    cost".
d) WBS and order - both are showing plan cost when booked separately, but not integrated.
Can anybody help me to resolve this ! 
Thanks in advance
--  Sri  --
Edited by: Srinivasan Madaswamy on May 18, 2008 2:15 PM

Hi,
In case of the maintenance order (Order Category:30)
Please check the follwoing in Tcode OPSV:
1. type is maintained default i.e ++++ (this will consider all the order types mantioned for maintenance order.
2. Please selelct the appropriate controlling area.
3. Appended plan indicator has to be checked mark,
4. Assigned funds in the plan indicator has to be checked mark,
5. In Tcode IW32: In the additional data Tab assign the WBS Element. Save the maintenance order.
Hope its useful.
Reward point if useful. Revert abck if any other issue.
Thanks..

Similar Messages

  • COPA - Planned Material Cost not appearing in KE30 report

    Hi all
      In COPA planning, I manually planned the Material cost (Material External Price) along with the Sales Quantity and Revenue for two company codes (one plant in each co code). But in KE30 report, I could see the material cost (MEP) values only for one company codeplant. What could be the issue?
      I even tried valuation in KEPM. Valuation step is calculating and populating the material cost in KEPM, but the values are not flowing to KE30 reports. And this happens to only one of the two company codes.
    Thanks
    Vamsi

    Hi Vamsi
    Please check table CE2XXXX, where XXXX = Op Concern.... Here, can you see the plan line items??
    If yes, then the issue is with your report definition in KE30... May be you are restricting values display in KE30 report by virtue of your selection parameters
    br, Ajay M

  • CN41N and S_ALR_87013533 report not showing Production order planned cost

    Hi Experts,
    I am having issue to get total planned production order values in my CN41N or S_ALR_87013533 cost report. I am facing 2 issues :
    1. CN41N repoet does not show individual material cost planned in BOM.
    2. CN41N report and S_ALR87013533 report does not show total value but only picking fixed value.
    Example :
    1. CN41N report :
    Above screenshot shows no values in Project plan cost & Order cost column but it shows total cost as a lumpsum on top for project. I need to know how can i get material cost populated here for Project Valuated stock material?
    2. S_ALR_87013533
    This report shows Total Cost of BOM as 1 line under Material Procurement activity similar to CN41N report. Also Order value is picking from Fixed cost from planned order and total cost is added on top. How can i get Total cost picked from production order?
    Is there any Setting in PS config which allow me to pick the detail production order plan cost in both report under planned cost.
    Thanks in advance.
    Ashish

    Hi Ashish,
    I doubt whether Item level reporting  in S_ALR... (hierarchy report) is possible or not because I haven't seen item level cost in them only the lump-sum cost because they are summarized at cost object level itself. Navigation path are there which we use to go into details of cost.
    Please check the following links:
    https://scn.sap.com/thread/1743833
    (In the above thread,focus on  Mr. Mohamed Rafi comment.)
    http://scn.sap.com/thread/3530080
    http://scn.sap.com/thread/1311820
    Order cost plan in report CN41N
    Display of plan cost., CN41N | ABAP, SAP, benX AG, benXBrain,&…
    Just an additional pointer ,have a look on your costing variant and variation variant settings for material section.
    Regards
    Saurabh

  • Target cost not appearing in process order

    Hi All,
    Please let me know the reasons for target cost not appearing in process order.
    Thanks,
    SAP PQ

    Two more scenarios:
    1. You have co-product.
    2. You reverse the variance calculation.
    It will show the target cost only after you run variance calculation.

  • Service Order Planned Costs and Cost Center Planned Line Items

    Experts,
    I am curious of Service Order Planned costs, and whether or not these planned costs are being posted to the Cost Center linked to the Service Order Operation's work center.
    I am a but puzzled as I don't see any planned costs from any Service Order Operation in a cost center linked to the Operations work center, when reviewing "Cost Centers: Plan Line Items" report.
    BR,
    Cenk

    The planned costs were input in one of the Service Order operations as planned hours. There is a column for it in the operations list. The amount of hours have incurred a planned cost on the Service Order header.
    I simply assumed that this cost would be credited to the Cost Center linked to the operation's Work Center. But that is obviously not the case. I am not familiar with the PLICC field and the functionality it provides.
    Thanks!

  • Material cost in production order plan cost

    Dear all,
    -we are in sales order cost object with non-valuated stock...
    -we have created two production orders from MRP run. First one is for semi finished material and second one is for finished material.
    Issue-1
    Both production orders not showing material cost in production order plan cost...
    Issue-2
    When i consumed raw material against semi-finished material production order (261-E), system not gnerated any document and material cost not updated either in production order or sales order...
    where should i do changes in configuration to get updated material cost in the production order...
    Best regards
    Kishore

    Hi
    Issue 1 : Check Whether Standard cost is present for header material of prod order, and under control tab of order costing variant for plan is present.
    Issue 2 : Use 261 instead 261E.
    Rajneesh

  • Lead time values are not appearing in the report for current year.

    Hi friends,
    Iam checking a report in production.  where lead time values are displayed as 0 for 1 key figure lead time3 (w/0 dim) . i found there is a formula for this it shows like NODIM ( 'Lead Time 3' ).and there is a value for cal.lead time
    how can i get values in the report.
    Thanks ,
    VRV.

    Hi,
    Although your question is not clear, I understood that the formula built on that KF is NODIM. Basically it means, units of measurement is not considered when calculating.
    Eg: 5 Minutes + 5 Kilograms = 10
    You please try to analyze your KF by the above logic. Then you would be able to figure out why the data is not appearing in the report..
    Assign if helps...
    Regards,
    Suman

  • Order Number is not appearing in Asset PR

    Hi,
    At the time of creation of Asset PR, the order number is not appearing. I had already assigned the order number in "origin" tab in Asset Master. Please find below details:
    1) Creation of Asset with AS01
    2) Creation of Order with KO01
    3) Assign the order in Asset Master "Origin" tab. The field is "Investment Measure".
    4) Creating a PR with Account Assignment "A". But the time I provide asset number, the Order field is coming as "blank".
    I am making Direct Capitalisation through Internal Order with asset under Construction.
    Please suggest.
    $atya

    Hi
    please check the settings from the note 684659.
    Best Regards,
    blaz

  • ATP Error-production order details is not appearing in ATP check

    Hi ,
    As per the details which I updated, production order details are not appearing in Sales order ATP check.
    Pls help me to solve it ,the settings needed to do in the system.
    Thanks,
      Vijesh

    Hi,
    i checked the configuration, it is same as you said, but still the production order window is not showing in the ATP check.
    thanks to  help.
    Regards,
    Vijesh

  • While executing TCode F13 and F13E, purchase order number is not appearing.how it should be displayed into tcode f.13, please any one help me

    While executing TCode F13 and F13E, purchase order number is not appearing.how it should be displayed into tcode f.13, what are the requirements need to display into tcode f.13, please any one help me, i am facing this problem in  production server

    Hi Nattu,
    Please check it will show the PO no under Purchasing doc field
    Check which layout you are applied.
    its should be
    SAP&F124
    Without Specification of Crcy
    Regd,
    Khan.

  • WHT amount not appearing in FBL1N report for Document type RE

    Dear Friends,
    While running FBL1N report for any vendor where TDS is applicable, the WHT amount is appearing for KR document type. But when it is RE document type the WHT amount is not appearing in the report. How can we resolve this? Any enhancement/any note to be applied?
    Regards,
    Ramkumar

    Hi,
    FBL1N is having the classic withholding tax field hence please don't refer the those fields.
    please don't refer those fields.
    Please review attached note 363309 for detailed explanation.
    BSEG-QBSHB is designed to fill for the classic withholding tax. And
    extended withholding tax information is stored exclusive in table
    WITH_ITEM.
    You can check in table BSEG for the fields and will find that system
    do NOT update field BSEG-QBSHB.
    In your line layout,you define a field BSEG-QBSHB. But actully the field
    of vendor/customer line item is filled with zero from FI. Thus,it shows
    zero in line item display.
    And as note 363309 says,
    "Remove the field which contains the withholding tax information
    from your display variant.
    If you want to display the withholding tax information, double-click on
    the document number and subsequently choose 'Withholding tax'."
    Regards
    Madhu M
    Edited by: M Madhu on Jan 18, 2012 9:13 AM

  • S_ALR_87013532 report -plan cost not rolling upto the WBS/Project level

    Dear All,
    Plan cost from production orders is not rolling up to the WBS/Project level in S_ALR_87013532 ( Plan/Actual Variance report).
    Where as plan cost from network is properly rolling up to the WBS/Project level in the above report. 
    Please suggest what could be the reason for this issue. Is any configuration needs to be done for this.
    Thanks & Regards,
    Vishal

    Dear sir,
    Thanks for the reply & sorry for late response from my side.
    OPSV settings are already maintained in our system.
    Some how i realized  later that cost are actaully getting rolled to the WBS level, but we have observed one more discrepancy.
    Example -
    Production order "X" value - 100 (  as seen through co03)
    Production order "X"value- 40 ( as seen through report s_alr_87013532).
    We found that  in report  s_alr_87013532 , although my total  producton order value of 100 is represented at the WBS /Project level, but at the production order level , it is showing value of 40. 
    On further analysis we found that for production order X
    Materail cost- 60
    Labour cost-40
    The material cost of 60  is not getting fetched against production order "X" in report " S_ALR_87013532".
    There are very few cases , where such discrepancy is seen.
    Kindly suggest.
    Regards,
    Vishal

  • Work orders planned cost report

    Hello
    In our organization, works order can have two types of settlement receivers (cost centers or internal orders). To report planned cost by receivers, we create automatically groups of works orders (by receiver) and uses standard transaction S_ALR_*.
    But it works only if settlement is not modified.
    Does one of you know a better way to report those costs?
    Thanks

    Hi,
    I don't want to report planned costs by maintenance objects but by receivers.
    For exmaple: i have 2 work orders on the same receiver (cost center 1)
    WO1    CC1   11/2011      500u20AC
    WO2    CC1   11/2011      600u20AC
    I try to report planned cost  for CC1
    Regards
    Simon
    Edited by: Simon Maes on Nov 25, 2011 11:31 AM

  • Planned Cost not coming for CO Activity in PM Order

    Dear All,
    I am putting up the entire configuration process i am carrying out for CO activity and using it in the PM Order.
    Please see the link and guide me through as to why the Planned Cost for the Activity is mssing.
    http://www.scribd.com/doc/21375098/PM-Activity-Configuration
    Regards
    Praveen Dhankar

    Hi,
    Kindly check the logs in the maintenance order,it will show that the valuaton variant defined wasnot successful.
    The problem is The activity price is not calculated properly,ask the CO consutant to maintain the activity price proprerly with updation. against that cost center.
    The second one is no need to maintain the activity in workcenter as per your attachment sheet.
    Maintain in Basic data of workcenter as standard value key as SAP0 No standard value key & in Costing view maintain the cost center,Activity in below field & maintain the formula as SAP0008.
    Regards,
    Raj

  • COPA Plan values not appearing in report

    Hi
    I posted COPA Plan values using KEPM and line items are appearing in KE25 but no values are not being appeared in COPA line item report we created using report painter. We used KE94 and KE91.
    Actual values appearing correctly in report.
    Any help??

    Check if you have Plan/Act indicator maintained correctly with the plan value. If it shows up in other reports, I don't see any reason why it will not show up here. I would also check other parameters entered in the report and see if any other characteristic is preventing plan values from populating.
    Shail

Maybe you are looking for