11.0.3 MRP creates WIP for dep demand at other plant - need internal req

At one manufacturing plant for finished good item, have component sourced from other plant. When MRP runs it creates WIP Job for component sources at other plant, need is to have internal req. Please advise what needs to be changed.
Ex - Finished Good is Car at chicago plant, one of main subcomponent wheels is from mexico plant.
Wheels are setup as buy, with inventory source type and source plant from mexico in item attributes at chicago org.
This wheels item is setup at mexico plant.
MRP release of planned order is creating WIP job at mexico plant for wheels component.
we want mrp release of planned order should create internal requisition when demand for finished good car comes at chicago plant.
Please advise what needs to be changed in 11.0.3 environment.

Hey there,
I think you should check your SOURCING RULES for those items wheels.
Make sure the sourcing rules are of "TRANSFER FROM" type with the right org and not "MAKE AT".
Hope this helps, if you find it helpful or correct please kindly mark it as such,
Aaron

Similar Messages

  • You should also create directories for and mount any other partitions

    Hi,
    I've downloaded archlinux-2012.12.01-dual.iso and wrote it to USB. I've booted from that USB and set up partititons using command cfdisk.
    /dev/sda5 ==> /boot
    /dev/sda6 ==> /
    /dev/sda7 ==> swap
    /dev/sda8 ==> /home
    I don't remember if I've created /mnt or if it was already there. I've created two directories: /mnt/boot and /mnt/home as per instructions:
    "https://wiki.archlinux.org/index.php/Installation_Guide
    Mount the partitions
    We now must mount the root partition on /mnt. You should also create directories for and mount any other partitions (/mnt/boot, /mnt/home, ...) if you want them to be detected by genfstab."
    I've mounted /dev/sda6 on /mnt
    and now there are no /mnt/boot and /mnt/home under the /mnt
    I don't understand what to do now because instructions state that I should create directories /mnt/boot and /mnt/home and mount them but now that I've mounted / on /mnt the /mnt/boot and /mnt/home are not available to mount partitions /dev/sda6 and /dev/sda8
    Regards

    mount /dev/sda6 /mnt
    mkdir /mnt/boot
    mount /dev/sda5 /mnt/boot
    Then do pacstrap etc. Add /home to fstab before you reboot.
    Alternatively you can mkdir /mnt/home and mount /sda8 there too, then genfstab will add the entry in fstab for it for you.
    Last edited by Mr.Elendig (2012-12-18 14:27:48)

  • If we activate MRP Areas what are the implications on other plants.

    Q:- If we activate MRP Areas what are the implications on other plants.
    My Business is having many plants with different business
    eg :- One Plant (1000)MRP is currently being executed at Project Level MD51
    Second Plant (2000) MRP is currently being executed at Plant Level ,
    Third Plant (3000) is currently being executed at materail levels only (MD02/MD03)
    Issue  :-
    for our new scenario we need to execute MRP  at MRP Area only -- Storage location MRP run
    So we would have to activate MRP @ MRP area level , but doing so
    You convert the existing planning file entries at plant level to planning file entries at MRP area level.
    To convert the planning file entries, you use the report that you trigger in Customizing for MRP in the IMG activity Convert planning file entries for MRP areas.The system creates a new planning file and MRP areas for the existing plants. These MRP areas, however, do not affect how material requirements are planned. The number of the plant MRP area is identical to the plant number and therefore has four digits.
    Preparing for Material Requirements Planning with MRP Areas - Special Planning Processes - SAP Library
    Can any one provide , what are the drawbacks , if activated at MRP Areas are activated , since it is activated at client level ,
    Will it impact my current MRP execution process for other Plants ??( other plants MRP is being executed at Plant MRP /Project MRP / etc,,
    Please Reply /Share your comments urgently
    Regard's
    Tallha

    Hello Tallha
    The only visible impact is that you will have an extra field on MD04 and another MRP transactions.
    If you simply activate MRP areas but don't create MRP areas for the materials, your process will not change and you should be able to continue using MRP as you were using before.
    There is a positive impact on the conversion of the planning file may improve the MRP general performance.
    BR
    Caetano

  • Restrict PO creation as material blck for quality reason in other plant

    Hi QM Experts,
    one material (say MAT-1) in maintained in  two plants (Say- X & Y).
    qm in procurement active in material for both the plants.
    created two Q-info records with material MAT-1, vendor ( Say- V-1). one info record for plant X & other for plant Y.
    while creating PO for material -( MAT-1)  in plant X, system giving error- material blocked for quality reason.
    even though in Q-info record for plant X, material is not blocked . it is blocked in Q-info record of plant Y.
    why system looking for plant Y, even when we are trying to create PO in plant X for same material and vendor.
    please guide on same,
    Thanks & Regards,
    Roshan
    Edited by: roshan s on Dec 16, 2011 6:29 AM

    hi,
    Please check ur Q-info of Mat-1 V1 and X properly and please also check ur material master in X, whethere some control key is defined in QM in Procurement or Not. If any control key is there than chcek the settings of that control key and as per ur requirement remove it .
    regards

  • Is there a way to create aliases for formulas without using other cells?

    I have long formulas in certain cells, that consist of a bunch of smaller formulas that I re-use in multiple cells. Is there a way to create an alias for a formula (or create my own function) that I can then piece together into one big formula? I think I can use another cell to drop the formula in, but that just clutters up the spreadsheet.
    Message was edited by: David Powers

    David,
    it looks like you can't define own formulas or create aliases for formulas.

  • Good receipt for job work from other plant

    Dear Experts:
    1.Material Received from Other Plant for job work with challan and how to bring the Material into Stock at receiving plant.
    The same material stock number available in this plant also.
    Regards,
    Sridhar.N

    Hi,
    You could use serial number concept or bacth managment here to separate within the material code.
    Regards

  • MRP - Create STO for Stockk Transfer between Storage Locations

    Hi Everyone,
    I have a scenario where MRP run should create Planned Order as well as STO for a VSF Requirement. The reason is our Plant has got 2 Storage Locations. One is the Production Storage Location and the other is Warehouse Storage Location. The Planned Order should be for Production SLoc and STO should for Stock Transfer from Production to Warehouse Storage Location. Your suggestions are much appreciated to resolve this issue.
    Thanks,
    Jay.

    new releaes bring new features........
    not all new features can run in old environments.
    I know that companies did already Storage location to storage location STOs in 4.6c but they had z-tables to assign customer numbers at storage location level, and they had changed some  coding to make it happen.
    I am not sure if there is an OSS note that explains the steps and modifications needed......but try to search OSS.

  • Error creating instance for target process default/QuoteProcessLab!1.0*/Req

    I am trying to run the sample lap workflow and I get the error when I click on the link for the application in the BPM Workspace. Where are the logs that may help me debug this error?

    hi im mehdi
    you can access the file with name "AdminServer-diagnostic.log" in this path:
    [your domain path]\servers\adminserver\logs\AdminServer-diagnostic.log
    i hope this will be useful

  • Suppress "Barcode-Pop-Up" for MM-Movements of other plants

    In order to archive different kind of attachments for MM-Movements, a barcode will be entered in the “Standard Barcode Pop-Up functionality” (T-Code OAC5) provided by SAP every time a movement is beeing created.
    Additional SAP let you configure for which "Object type/Document type/User"
    (also over T-Code <i>OAC5</i>) and for which "Movement types and  transactions" (IMG: <i>Materials Management->Inventory Management and Physical Inventory->Goods Receipt->Activate storage of incoming documents</i>) the Pop-Up for entering a barcode will be shown.
    The problem we have now is that more sites are on the same system and we should configure the system so that only for specific sites (MM-Plants), the Pop-up should be shown. Does somebody know some additional customizing or an easy way to assess a solution to this request?
    Thanks in advance and best regards

    On 4.6C it is not possible (under standard situations).

  • Does OWB 9.2.0.2.8 creates CWM2 for OLAP/BI?

    The environment is:
    Personal Oracle9i Release 9.2.0.3.0 - Production
    With the Partitioning, OLAP and Oracle Data Mining options
    JServer Release 9.2.0.3.0 - Production
    JDev 9.0.3.1035
    I managed to run the OLAP/BI Beans tutorials. So, I am now ready to create my own OLAP Metadata.
    I created some Dimensions, Cube and Measures with Oracle Enterprise Manager (OEM) which generates CWM (Common Warehouse Metadata) for 9R1.
    But to use full capabilities I need CWM2 from 9R2 so to generate OLAP Objects in CWM2 it seems that I need to go to OLAP Worksheet (via OEM's OLAP Management) or use the PL/SQL packages for CWM2.
    While at:
    http://otn.oracle.com/products/warehouse/htdocs/OTN_collateral.html
    I came across document named "Use Oracle Warehouse Builder To Build Your OLAP-Ready Data Warehouse" dated 2002, authors: Particia Fay, Jean-Pierre Dijcks and Oracle Corp. This documents shows how to create OLAP Objects with OWB in 9i.
    Does Oracle Warehouse Builder generates OLAP Objects of CWM2 type ?
    Thanks for the feedback.
    Pedro Garza

    For the benefit of others looking at this post, it has been cross-posted to OWB Forum and answered there
    Does OWB creates CWM2 for OLAP/BI
    Nikolai

  • Restriction of planned order generation (mrp)in other plant.

    Hi,
      I am running mrp for sales orders and i want to restrict the planned order generation in other plants other than the sales order plant. 
    through standard activity it can be blocked by not maintaining special procurement key of stock transfer.
    But some users are creating manual demand in other plant(STPO) against the same sales order for some sub assembly. so if they are running MD02 in their plant it is creating planned orders against the same sales order.
    I want to restrict the planned order generation against any sales order in other plants. How it can be done.any enhancement please suggest.
    Regards
    Madan

    Hi,
          we cannot restrict the authorizations so specifically here in my business client.
    Based on planned orders we have defined some programs.
    the programs are  effecting because of these unwanted planned orders which have been created  for a different plant sales orders.
    Is there any enhancement or BADI to control the creation of planned orders in other plant for a sales order of different plant.
    please suggest.
    Regrds
    Madan

  • Pur. req. not created for Dep.req. of Sub. Contracated Material after MRP

    Hi Guys,
    Pl. observe the below scenario,
    Our client scenario is Make-To-Order     
    u2022     Sales order is created for FG material in plant "0001"
    u2022     Material BOM is created for FG material in Plant "0001" with 10 raw materials
    u2022     Routing is created for FG material in plant "0001"
    u2022     Now MRP is carried out for the FG material, system created Planned order/Purchase requisitions as defined in field u201CProcurement typeu201D in MRP tabs.
    u2022     Purchase requisitions are converted into Purchase orders and against some of the GR is done.
    u2022     Due to some reason, we wanted to subcontract the FG (vendor is u201Cexternal vendoru201D or another plant with in Karle Group).
    u2022     Steps followed to subcontract the FG material
    1.     Converted planned order into Purchase requisition
    2.     Converted Purchase requisition into Purchase order.
    u2022     Now some more raw materials added into FG material BOM in plant "0001" and carried out MRP with planning mode indicator as u201C2 i.e. re-explode BOM and Routingu201D.
    u2022     In T.Code u201CMD04u201D checked to procurement proposals for newly added materials in plant "0001", found out that, system is not generated the purchase requisitions.
    Kindly help me this...
    Regards,
    Satya Prakash

    Dear Satya Prakash,
    If the entire operation is sub contracted ,please try the following steps.
    1.Let the system create a planned order.Create a production order.
    2.Change the control key under the operations tab to PP02.Fill in the required details such as
    a.Purchase group.
    b.Cost element etc and SAVE the order
    3.This will generate a PR.
    Create a Sub contracting PO and process further.
    After the receipt of PO.Close the order.
    Regards,
    Joseph Charles Vaikathussery

  • MRP  supplier consignment create delivery for  Scheduling Agreement

    Hello,
    We have a situation where MRP is used to calculate for a material which is subject to supplier consignment and also to scheduling agreement. When we run the MRP generates purchase requisitions for the consignment material , but it does not find the scheduling agreement for the material. We expected that it would create deliveries for the scheduling agreement.
    The question is, is it possible to obtain deliveries from the MRP for the scheduling agreement?
    Thanks a lot
    Ignasi

    Yes, it seems the problem was in Quota Arrangements which was not  well defined for consignment material.
    Thanks.

  • Creating Planned orders and Requisitions for a particular MRP controller and for all the others only Requisition is to be created.

    Hi Experts,
    Currently we run Program 'RMMRP000' as a batch job to create Planned orders and requisitions.
    The client wants that Planned orders and Requisitions should be created for a particular MRP controller and for all the others only Requisition is to be created.
    I implemented Exit 'EXIT_SAPMM61X_001' in the following manner by passing MRP controller to user_key.
      IF mt61d-dispo <> user_key.
        no_planning = 'X'.
      ENDIF.
    But as you can see that this will not meet my client requirement.
    If any of you has worked on similar requirement / if any one knows that this is achievable or not,
    please share your inputs.

    Moved from SAP ERP Sales and Distribution (SAP SD) to ABAP Development
    G. Lakshmipathi

  • Create wip jobs for same item with different routings.

    My scenario is , i am having 2 production lines for the same End item. If both lines are available to use, then WIP jobs have to be created for both lines. If either one is available then WIP job has to be created only for that line. Please suggest the setups for this. This way i can increase the production rate.

    HI Jey-2013,
    In your organization, you first need to define Bills and Routings for the item/items.  Now to use two routings for 1 item, you need to define Alternate Routing.
    For that go to BOM>Setup> Alternates and create an Alternate name for the second routing.
    Then Go again to BOM>routing and use the Alternate name for the item to create a different Routing. After that you will have two different routings for same item.
    Whenever you create a job in WIP, you will have an option to choose either the default or the original routing. This way you can accomplish your goal of using different routings as and when required. Hope this helps you. Kindly let me know
    Regards,
    Bhargav

Maybe you are looking for