Hi,
I had created a PO and a GR in 2009 but when I do MIRO in 2010 for the same items, I am getting Budget Exceeded message.
It is beyound my understanding that the system should check 2010 budget during MIRO when the PO was raised in 2009.
Any thoughts ?
Thanks.

Hi,
You are working on Annual Budgeting.
You are trying to do MIRO and i think there is some price difference which system will post in 2010 and budget is not sufficient to post that document.
Check how much budget is exceeding and how much you cost you are going to post against the WBSE.
Muzamil

Similar Messages

  • Do not want Budget check & Commitment value for purchase Requisition

    Hi Experts,
    I hope you all are doing well.
    My client's requirement is that at the time of Creation of Purchase Requisition there should be no budget check against WBS element and also Commitment value should not be for Purchase Requisition.
    Please suggest.
    Thanks & Regards

    Hi Gokul,
    Thanks for ur quick reply.
    I have done changes in tolerence limit (activated it for PO only).
    Now i created 1 Project PR of more than value of budget (system didnt check the Budget against WBS) but when i am trying to create PO with reference to same PR, system is giving error of budget. That is OK for me.
    Now my requirement is to not take PR value as commitment in my reports, i want only PO value in Commitment column of repport.
    I have read all 3 notes suggested by you. Can u tell me whcih one should i implement to stop PR value as commitment in reports.
    Thanks & Regards

  • Budget check not active for commitment & actual budget

    Budget check runs  fine while checking budget limits for Production order and vendor invoices i.e does not allow to further create production order and vendor invoices if budget limits exceeds the released budget.
    But  this budget check does not work on procurement processes ( PR, PO &GR).
    No warning or error message pop out and the system allows to further create PR/PO/GR  beyond  released budget
    What  config changes are required to make budget check active for procurement processes.

    Hi vishal,
    Check the Transcation groups in Budget tolerance limits.
    PScostsbudget---define tolerance limits.
    If you assign ++ All Activity groups it will activate the Budget avaliability control for all Transcation.
    Check the avaliability control in OPS9 whether the activation type is 1 or 2 . If  2 run the avliability control CJBN.
    Hope this will helpful,
    Regards,

  • Budget Checks in Classic for PO

    Hi everyone,
    We have a doubt with the budget checks in classic scenario and we need your help. We know when we create a SC, SRM verifies the budget in the ERP as a simulation. If there is not budget the system sends a error, but what happend with the PO?
    For example:
    Case 1: We create a SC. The SC is sent to SoCo. In SoCo, the strategic purchaser creates a bid invitation. A bidder wins the process and we whant to create a PO. When the budget is verified? The budget is checked before the PO is created in ECC or when? If there is not budget, the PO would not be created in ECC??
    Case 2: We create a SC. The SC is sent to SoCo. In SoCo, the strategic purchaser assigns a contract then, he wants to create a PO. When the budget is verified? The budget is checked before the PO is created in ECC or when? If there is not budget, the PO would not be created in ECC??
    We are working in SRM 7 with ECC 6 EhP 4.
    BR
    Ivá

    Hi,
    In classic deployment, commitment of budget only happens when the PR or PO follow-on documents are created in the ERP system. SRM SC has no capability to lock commitment in the ERP when the SC is released.
    If you are looking at the commitment locking in the ERP when SC is released, you may like to look at the SRM PPS which has this capability in the extended classic deployment.
    Regards.
    YS

  • Budget checking in item category U

    Dear sapient
    I am posting a PR  document in ME51N for stock transfer with item category U. But system is not checking the budget.
    I saw in FMRP_RW_BUDCON line item has been created in document journal as Zero value.
    Please let me know whether budget checking is possible for item category U or not. If it is possible then please suggest me.
    requirement is for stock transfer for internal consumption through me51n.
    ECC6 EHP4 fund management is active.
    Thanks & regards
    Soraj

    Dear sapient
    Thanks for the reply i had gone through the sap note, but in my case i am creating PR in me51n not getting any bug.System creates the pr and deriving the fund center and commitment item but when i saw in the report in document journal, line has been created against the PR but not reducing the budget value
    Regards
    Soraj

  • Can any body tell me the transaction for budget check in SRM ?

    HI,
    Experts,
    As i want to check the budget of a business partner / customer i am new to that can u please tell me basic information about budget check and pass the Standard transaction for budget check.
    Thanks in advance,
    Shabeer Ahmed

    Hi    Dinesh,
    Thanks for your reply and can u send me the Budget check standard transaction and related tables and how he going to check his budget.
    According to me:
    1    In which table Amount is maintained for BP
    2   How we have check the budget.
    Do u have any document related to this please forward it to me.

  • Components to be activated for Budget check in the table TRWCA

    hi,
    I want to know the components to be activated for budget check in the TRWCA table. I want to check the budget at the time of  PO creation , Goods reciept/Invoice receipt creation  using Network account assignment in PO  which is having WBS element and Project in its higher level.
    Thanks
    Rao

    ok well!
    Brother system will only check the budget, when your availability control is active.
    Further, as per your configuration, system will only prompt error  message when your budget exhausted 100%. ok
    please follow the same then  let me know
    check your WBS status is there avaiablity control active, when you entered the amount for budget/release.
    also check the transacion "CJBV - Activate Availability Control "
    Note: when ever you change the setting of your budget profie, must reconstruct the availability control transaction code is :CJBN/CJEN
    Thanks

  • Budget checking for Purchase Order

    Hello All Experts,
    Project Availability control: Tolerance limits
    on All activity groups - warning message for 101%
    on Purchase requisition - warning message for 101%
    on Purchase Order - error message for 101%
    1. Now we created a project with 5000 budget and Availability control activated.
    2. We assigned material to activity and created Purchase requisition for 6000. Here system issued message there is error in commitment and allowed us to save the project.
    3. We created Purchase order for 6000, system is allowing to create, that is any thing less then PR value, even though it is more than 101% and suppose to give the error.
    How do we over come this situation and make the system to look Budget value not the PR Value.
    Thanks,
    Karthik

    Hi,
    you have maintained activity groups ++ so system is considering All activity groups first for budget check instead of individual activity groups(PR,PO...). remove the ++ activity group and maintain individually(PR,PO,GI...) and check.
    regards

  • Budget check for purchase order

    Hi everyone!
    We have NO problems with budget check for the SC. But when we create a PO and exceeds the budget no message are displayed. The only thing that happens is that the PO gets status "error in process". But if we change the PO (still exceeding budget) we receive a correct message. Is this a program error?
    Sincerely
    Anders

    Hi
    Temporarily deactivate budget check: SRM: using Badi
    BBP_BUDGET_CHECK, AVC Backend customizing.
    Did you do budget check while creating sc? what did it says?
    Refere this old notes.
    Note 740933 - Incorrct purchasing budget for currencies w/o decimal
    places
    Note 747143 - User purchasing budget in pop-up incorrectly formatted
    regards
    Muthu
    Edited by: Muthuraman Govindasamy on Nov 5, 2008 3:08 PM

  • I need the BADI or the way for WBS budget check at SC line item

    Hi SRM folks,
    Do you have any BADI or the good way to do the WBS budget check at SC line item level.
    Donot suggest me the BBP_BUDGET_CHECK.ie for SC level only.
    Is there any way to do at line item level.
    Thanks in advance.
    srini.

    Hi
    Either use BBP_ITEM_CHECK_BADI or BBP_DOC_CHECK_BADI.
    Note -> Please read the relevant standard SAP documentation provided in this case for using SE18 Transaction.
    <b>Please go through the following pointers, which will definitely help -></b>
    Re: Reg the budget check in Shopping cart
    Re: Budget analysis
    How to implement the badi BBP_DOC_CHECK_BADI??
    Budget check for service PO
    Budget Check error for Fixed Assets ? :-(
    <u>Other related links -></u>
    Budget Check
    http://help.sap.com/saphelp_srm50/helpdata/en/4f/b3e739e62b714be10000000a114084/frameset.htm
    http://help.sap.com/saphelp_srm50/helpdata/en/de/237440116fd279e10000000a114b1d/frameset.htm
    http://help.sap.com/saphelp_srm50/helpdata/en/4e/1d74eff196d64e880fd28d41d4502b/frameset.htm
    http://help.sap.com/saphelp_srm50/helpdata/en/5a/af5eff85d011d2b42d006094b92d37/frameset.htm
    Do let me know as well.
    Regards
    - Atul

  • Budget check for PO based on delivery

    Hi,
    Can some guide how to configure budget check for purchase order based on supply schedule.
    This could be that you have raised a Purchase order for 12 Quantity and the delivery of the same is at 1 per month for 12 months.Budget should  be checked for one quantity for one month and not based on Purchase order which is for 12 quantity.
    We are using Former budgeting.
    Regards,
    Gokul

    Hi,
    I'm afraid you will have to create 12 items within the same PO and assign different delivery date to every one of them; then, the budget will be affected accordingly.
    Regards,
    Eli

  • Budget checking for services with "Unlilmited" indicator set

    hi friends,
    Under normal cases, the budget checking is happening properly for the services in a project.
    But I have certain service activities where I require to set the "Unlimited" indicator set (in the service specification screen)and some other services where I set a value limit to the unplanned services (in the Limit section of the service specification screen).
    In these cases, the budget checking is not happening as expected by the standard methods. Please note that the availability control is active.
    Please help me out.
    regards
    Pratap.V

    Hi Nitni,
    Thanks for the prompt replies.
    Now you have struck the point. Assume I have a budget of rs.50000. The planned services in PR is of Rs.20000 and I have set a limit of rs.50000 for the unplanned services in the same PR. Now my commitment is Rs.20000 only which is right.
    In our specific case, the budget check will not happen at PR.
    Now I am creating a PO of the above PR. So PO commt is rs.20000.
    After this, when I go to the service entry sheet and enter a planned services of rs.20000 and unplanned services of rs.40000 (remember i set a 50000 limit for unplanned services in the PR). Hence my total actual cost is rs.60000. Obviously I want the system to do a budget check here and stop the user at the time of service entry sheet. But this is not happening. The budget check is not happening at service entry sheet if I am having any unplanned services in the PR or if I tick the "unlimited" indicator against a particular service.
    Hope I have put my point clearly.
    regards
    Pratap

  • Budget check in PR/PO for Raw Materials

    Hello
    We have requirement that there should be a Budget check even for Raw Materials before PR /PO is created.
    We have observed that Budget check is done if Account Assignment Category "F" is used.But for procuring Raw Materials is there any way we can check the Budget.
    Can this be requirement  done through Funds Management ?
    Regards
    Vaibhav Mahajan

    Hi,
    'Budget check even for Raw Materials before PR /PO is created' before PR?when you want check budget?
    'We have observed that Budget check is done if Account Assignment Category "F" is used'-not only for F.
    'Can this be requirement done through Funds Management ?'-you can check at PR/PO level as well as GR/IR

  • Budget check for a Training Event

    Hi,
    My client has departmentwise budgets for Training. They want a budget check when the Training Event is being creating in SAP. If the training costs exceed the remaining training budget of the department, the system should not allow it. How to achieve this?
    Please help.
    Regards,
    Sasi.

    Hi
    Temporarily deactivate budget check: SRM: using Badi
    BBP_BUDGET_CHECK, AVC Backend customizing.
    Did you do budget check while creating sc? what did it says?
    Refere this old notes.
    Note 740933 - Incorrct purchasing budget for currencies w/o decimal
    places
    Note 747143 - User purchasing budget in pop-up incorrectly formatted
    regards
    Muthu
    Edited by: Muthuraman Govindasamy on Nov 5, 2008 3:08 PM

  • No budget checking for batch input

    Hi people
    We are using the budget checking functions under Funds Mgmt (Former Budgeting) ECC6.0. Is there a way that we can exclude budget checking for postings done through batch input?
    appreciate any help.
    TQ
    darth maut

    Hi,
    Please check the SAP note 573409
    Regards,
    Abhijit