Actual cost of the employee from HR  to be  posted in projects

Hi experts,
Help needed.
Scenario:
Employee fills in time sheet (CATS) against WBS  element  (different for different projects) which is transferred to HR (IT 2002). Overtime hours is also recorded.
Time evaluation and Payroll is run for the respective months.
The requirement is to calculate the actual Personnel Cost per Project. When i post results to FI, it is not taking the WBS element. 
I tried giving IT 27 , but when i try to post to FI, it gives out an error "Required field GL_ACCOUNT was not transferred in parameter ACCOUNTGL"
How can i transfer the cost from payroll to WBS element? Is it possible??? if so, how?
Pls help
Helpful answers will be acknowledged
regards

hi,
Pls check up with your WT list for posting
If all the desired WTs are posted to expense & Balance sheet accounts with proper Symbolic account
Check up with the FI team.
-Also check are you changing any symbolic account or any new GL is attchaed to an existing Wt
-Delimiting  the wage type chekc View: V_T52EZ.
Regards
Hemant V. Mahale

Similar Messages

  • PS - Report on Planned v/s actual cost of the project

    Hi,
    I have a client requirement on the above subject. In Report S_ALR_87013542, Under actual cost the system is taking both the Revenue and Actual cost booked on the project. Is there any other report wherein the system shows only the actual cost booked on the project so that planned V/s Actual can be compared.
    Rgds,
    Prasad

    Hi,
    You can also refer the report S_ALR_87013543 - Actual/Plan/Variance Absolute/Variance %. This will give the reports based on cost elements. Morever plan cost Vs actual cost can be obtained from Project Infosystem report (CN41/ CNS41).
    In fact the report S_ALR_87013533 is a hiecherachical report for plan & actual cost of project.
    If the system is calculating wrongly both revenue & actual cost under actual then you need to check Cost elements asignments & value category details.
    Hope this will help you.
    Regards,
    Rakesh Pradhan

  • Extraction of actual cost in the project

    hello all,
    Kindly suggest if any function module is available to extract actual cost incurred in the project? The actual cost includes the cost of material consumption, activity confirmation, Fi posting. The intention is to get the total actual cost on the WBS at one place.
    Regards,
    Sudhir

    RESOLVED

  • Distributing Actual Costs to the Product Level

    We are using Material Ledger at my client and we have some things such as Freight, Depreciation etc. being added to the standard cost as an additive cost. For the actual values for these is it possible to include this in the ML actual cost without having to go through MR22?
    Thank you

    Hello,
    I think you need to rethink the scenario. Freight should have been added to the material cost at the time of procurement and depreciation should flow from cost centers. Another alternate can be that you post actual freight and depreciation both in cost centers , define activity for them , plan them as well and use formula based planning templates to allocate so that they are build up in the cost estimate as well and in actuals they are actualised through the cost center route.
    Kind Regards // Shaubhik

  • Actual cost at the time of Goods Receipt

    Hi All,
    When I create Goods Receipt, I am getting actual cost in WBS Element. As per customer request, When I do the Goods Issue then only actual cost has to come to WBS Element.
    1. Is it due to statistical cost element cretaed for inventory account (BalanceSheet account)?
    2. If statistical cost element not cretaed, will commitment raise?
    (Or) Am I missing any configuration settings?
    Regards
    Suresh

    Sureshkumarsap wrote:
    > 1. Is it due to statistical cost element cretaed for inventory account (BalanceSheet account)?
    Yes, if you are using valuated Project Stock.

  • How to transfer the employees from one org unit to another org unit in OM.

    Hi Experts,
    I have a task of changing the employees, Positions & Jobs, from one Organization Unit to another Org unit, in the OM. I have around 50 position & Jobs and employees to be moved. Please suggest me how do I go about.
    I tried doing through PPOME (Org. and Staffing) but it is a lengthy procedure please suggest if there is an alternate option to do so in OM.
    Thank you in advance.
    Regards,
    Subbu.

    Dear Sharad,
    First of all I recommend to open a new discussion and not to post in a old-date one.
    Anyway, You can do it either PA40 or OOPME.
    In PA40 you should select an appropriate action like :Org. Change", "Promotion" and so on. In fact it depends what do you have in you action list.
    In PPOME you can do it by drag and drop also. Just take care about effective date. First you should select the right date in top of the screen.
    Regards,
    Omid

  • Actual cost for the Process Orders

    Hi Experts,
    I want to know the actual cost for total one month process orders.
    I can check actual cost for each order in COR2- by entering in to cost analysis.
    But, my request is, where to check actual cost for One perticular product for the total month (ex: 100 Orders) or certain period.
    can eny body give solution by sparing your precious time.
    adv. thanks and regards,
    Anand.M (Hyderabad)

    Hi,
    Try MCRI / MCRY or check the table entries of S027
    Regards,
    Srini

  • Planned and Actual costs at the Activity level

    Hi all,
          Can you tell me if there is a R/3 report which lists out the planned and actual costs for a project and displays it for each network and activity? I want these values at the activity level.
          I found a report which lists out these values for each network, but I cannot drilldown to the activity level. Please help.
    Thanks,
    Satyajit.

    Hi,
    There is setting in network type. Please go through transaction OPUV  i.e.
    Change view- Network type paramaeters : overview " Overview.
    Uner Network type parameters there is one radio button in front of ActvtyAcctAssgn. Just activate it.
    Hope this helps.
    Regards
    Tushar

  • Actual cost in the workplan task screen (hierarchy) not show value.

    Hi all,
    Could you advice me about actual cost if I want to show in the workplan task screen (hierarchy).
    Thank you.

    Well, then just check the master data setting in Query designer--> choose 0Costcenter and check the properties > choose advanced tab> under filter value Selection during Query Execution . check for these options
    1.Only Posted Values for Navigation
    2.Only values in Infoprovider
    3.Values in Master data table
    4.Characterstic Relationship.
    You need to choose the 3rd opitions as you need to read the master tables for 0costcenter.
    Hope it helps,
    Cheers,
    Balaji

  • Query to find assignment details of the employees from database

    Hi,
    For all the employees, I want to find following details from HRMS tables (This detail is shown on assignments window on frontend)
    Department, Role, Designation,Position(current),Supervisor
    Not being an expert in HRMS tables, so to avoid delays in R&D and to give quick results to my functional team, can anyone tell me the exact db query to save any time.
    Abdul Wahid
    http://iwidi.org

    Pls see if the below helps
    I have not got the Position details, you can join the Position KFF table to get those.
    select papf.employee_number,papf.full_name, papf.national_identifier
    , papf.start_date Hire_Date , papf.ORIGINAL_DATE_OF_HIRE   
    , papf.date_of_birth
    ,papf.email_address
    ,papf.marital_status
    ,pj.name Job
    , hou.name HR_Organization
    , hl.location_code location
    , ppf.payroll_name
    , paaf.normal_hours Working_hours, paaf.frequency,
    decode(paaf.employment_category,'FR','Fulltime-Regular','FT','Fulltime-Temporary','PR','Partime-Regular','PT','Partime-Temporary',null) Assignment_Category,
    sup.full_name Supervisor, 
    decode(sup.business_group_id,0,'United States',82,'United Kingdom',4063,'Spain',null,null,'Other') Supervisor_Country
    ,pa.address_line1
    ,pa.address_line2
    ,pa.address_line3
    ,pa.town_or_city
    ,pa.region_1 county
    ,pa.postal_code
    ,pa.country
    ,pa.telephone_number_1
    ,pa.telephone_number_2
    ,ppp.proposed_salary_n salary
    from per_all_people_f papf,
    per_all_assignments_f paaf,
    per_jobs pj,
    hr_all_organization_units hou,
    pay_payrolls_f ppf,
    per_all_people_f sup,
    per_addresses pa,
    hr_locations_all hl,
    per_pay_proposals ppp
    where papf.person_id = paaf.person_id
    and sysdate between papf.effective_start_date and papf.effective_end_date
    and sysdate between paaf.effective_start_date and paaf.effective_end_date
    and papf.business_group_id = 82
    and pj.job_id = paaf.job_id
    and pa.person_id(+) = papf.person_id
    and hl.location_id(+) = paaf.location_id
    and ppp.assignment_id(+) = paaf.assignment_id
    and sysdate between ppp.change_date(+) and ppp.date_to(+)
    and hou.organization_id = paaf.organization_id
    and ppf.payroll_id = paaf.payroll_id
    and sysdate between ppf.effective_start_date and ppf.effective_end_date
    and sup.person_id(+) = paaf.supervisor_id
    and sysdate between sup.effective_start_date(+) and sup.effective_end_date(+)
    order by ppf.payroll_name,papf.full_name

  • Report showing sum of Budget/actual cost of WBS elements from diff proj

    Hi,
    i need to display consolidated budget/cost report for separate projects. (example PROJ 1 and PROJ 2)
    in both projects, they have similar structure of WBS (same descriptions etc..)
    in reports i can run both project but the values are summarized for the entire projects.. (results = Total of PROJ 1 + total of PROJ 2).
    but i need report showing subtotals of WBS 1.1 of PROJ 1 + WBS 1.1 of PROJ 2 and so on...
    i thought i could do it using CJI8 but i cannot filter it by description and do subtotals since it does not have a description column.
    is my requirement possible with standard or need to customize a report?
    thanks in advance

    hi
    please try to use Co Object Name field with sub total

  • How to find the Actual Cost & NR of a material

    Hi experts,
      Can anybody tell me the table from which I can come to know the actual cost of the material and also the actual NR.
    Thanks in advance.

    Hi Shakeel,
    Go to Se16n transaction
    and select EKBE table, there u  will find so many field ranges, restrict it as u like
    u can get it there
    regards,
    subbu

  • Planned Cost is taken from Actual Cost even through there is Baseline Cost

    Hi All,
    Responsibility: Project Super User
    Create Project with fully shared structure
    Enter planned cost for 25000 against Task (Define Project scope in detail) with Financial Element as Resource and baseline the work plan.
    Now enter the actual cost for 15000 against Task (Define Project scope in detail) and system is computing 15000 in Actual Column along with planned cost as 15000 in planned cost column instead of showing 25000 in planned cost column.
    Why system is showing planned cost as 15,000 in planned cost column instead of 25000?
    Please help.

    Hi
    I'm not sure I understand the steps you were taking.
    Actual costs should be summary of expenditure items. Those could be labor hours entered on time cards, supplier invoices etc. Those are entered on Project Costing, Distribute and summarize there
    I couldn't understand your statement about entering 15000 actual cost on the same page as entering the planned cost for the workplan.
    Dina

  • Price differenc value in Actual cost of Production

    Hi,
    We are creating a production order for Billets that is our Semifinished goods. The material master is maintained at Std price.
    Lets say that Std prce of the Billet is 100.
    Lets say that after the production order is completed , the actual cost of Billet is comes out to be 125.
    Now this billet is used for the production of the finished goods Wires. For the production order of wires, the price of the billet is taken as 100. 
    In this way the actual cost of the Wire will not come.
    May be this is the standrad process. Let me know in any way can we use price difference of 125-100= 25 in the production cost of wires so that I can get the actual cost of the wire.
    We are not using Material Ledger.
    Any suggestion
    regards

    Thanks Ajay,
    Even using ML we cannot get the actual price before the end of the period. And at the month end only we can valuate the inventory withe actual cost. I hope I am right till now.
    Pl correct if I am wrong.
    But in this case some wires rods are already out from the inventory for the sale that was valuated with the Std Price of the Billet.
    Hence these invenories will  not be available at the month end for the revaluation.
    Pl. correct If my thought is OK.
    ML can only be used where ther is lots of Raw Matl price variation..Hence I think I should go with the std price valuation itself.
    regards
    Kamlesh

  • Actual cost of material in COPA

    Hi Team,
    We have implemented PP, CO & COPA  our client has the requirement to see the actual cost of material in COPA as per their requirement we designed the KE30 report as product wise profitability report in that report we used the record types B( direct postings from FI), C(Order settlement), D(over head cost) from the copa assessment cycle & F ( SD billing).
    1) Is it possible to see the actual cost of material( Including activity cost) in copa.
    2) If it is possible please advise.

    Hello
    It is not possible to get the actual cost of the material in COPA. Actual cost can only be derived if you implement material ledger.
    However in COPA we may come close to actual cost to some extent. The following configuration needs to be done:
    1. Run standard cost estimate every month so that the price reflects the most recent material prices.
    2. Define assessment cycles for auxiliary cost centers (whose cost should form part of inventory cost) to production cost centers.
    3. Configure for splitting and revaluation at actual price.
    4. Take the production variances to COPA.
    5. Create a report to show the standard cost and variances.
    One of the difference is that the total standard cost is for the quantities sold during the period however the variances will be for the quantities produced during the period.
    Another difference is that the unabsorbed overheads could not be allocated to individual materials.
    Hope this helps.
    Sangram

Maybe you are looking for