Hi all,
I need help in adding a column to the gantt table in the workplan tab on Oracle Projects module. I need to add a description column near task-number column.
I've followed the standard personalization procedure: Personalize page, select the table region, add item (MessageStyledText), rendered=true.
No matter the view instance/view attribute i assign to it, but I can't see the column on the table.
If I return in the page-personalization I see that the column has been added, but I continue not seeing it on the gantt table......
Do you know, what can I do?
Thanks,
Dario

Hi,
"The resource list member is not a member of this resource list XX Planning Resource List", r u trying to export from MSP to Projects? If so, the resource should be the member of the project (Team Member, PM, Accountent...........)
Please check your Planning Resource List > People.
Regards
Raghavender K

Similar Messages

  • Oracle Project - Gantt Chart probem java.lang.NoClassDefFoundError

    Hi all,
    I have and apps11i instance (11.5.10.2) in OEL 5 x86 and DB 10g R2
    Patch set level is as per Software Updates for +Oracle Projects Rollup Patch 4 for Oracle Projects Family Pack M (11i.PJ_PF.M)[Article ID 423428.1+
    When radio button Gantt chart view is selected in Workplan tab the following error is shown
    *JSP Error:*
    *Request URI:/OA_HTML/OA.jsp*
    *Exception:*
    *java.lang.NoClassDefFoundError*
    Any help is highly appriciated
    Thanks in advance and regards,
    Soni                                                                                                                                                                                                                                                                                                                                                                                                                                                                                                                                                                                                                                                                                                                                                                                                                                                                                                                                                                                                                       

    Soni wrote:
    Hi all,
    I have and apps11i instance (11.5.10.2) in OEL 5 x86 and DB 10g R2
    Patch set level is as per Software Updates for +Oracle Projects Rollup Patch 4 for Oracle Projects Family Pack M (11i.PJ_PF.M)[Article ID 423428.1+
    When radio button Gantt chart view is selected in Workplan tab the following error is shown
    *JSP Error:*
    *Request URI:/OA_HTML/OA.jsp*
    *Exception:*
    *java.lang.NoClassDefFoundError*
    Any help is highly appriciated
    Thanks in advance and regards,
    Soni
    Please see (Receive Error When Attempting To Open A Work Plan Gantt Chart View [ID 306413.1).Thanks,
    Hussein

  • API for adding external roles/parties to an organization in oracle projects

    Hi,
    I need a help on the API for creating external roles/parties to an organization in oracle projects. There are two APIs in oracle for roles - pa_project_pub.load_org_roles and pa_project_pub.load_key_members. load_key_members api is used to load team members which are employees to a project and load_org_roles is used to add an organization role to a project. But how to use these API to load a party/external role to the organization role (or) is there any other api to do this functionality. Please suggest me on this.
    Thanks,
    Ramky

    Hi all,
    The order of blogs is:
    /people/valery.silaev/blog/2005/09/14/a-bit-of-impractical-scripting-for-web-dynpro
    and then
    /people/bala.krishnan2/blog/2006/09/25/bid-adieu-to-bots--using-captchas
    Help me soon...

  • Oracle Projects Differences from 11i to R12

    Hello All,
    Currently we are upgrading from 11.5.10.2 to R 12.1.3
    We have oracle projects implemented in 11i.
    I am researching to get the differences occurred in oracle projects functional and technical from 11i to R12
    It will be a great help to us if we could get some documents or a link which shows the differences.
    Thanks and Regards,
    Ankit Vishwakarma

    Project new features
    Oracle Project Foundation
    New Concurrent Process
    ADM: Purge Obsolete Projects Data
    Oracle Project Costing
    Federal Budgetary Accounting for Project Expenditures via Subledger Accounting
    Contingency Worker Clearing Projects to allow CWK to charge multiple projects
    Additional Project Information in Oracle Time and Labor (Project Name and Task Name)
    Federal Budgetary Accounting for Project Revenue
    Additional journal entries are available in Subledger Accounting for the required Federal Budgetary entries.
    Date Effective Funds Consumption
    Project Type option that requires cost and event transaction dates to fall within the agreement start and end dates.
    Transactions are only billed against the agreement if the entire transaction amount can be funded (no partial recognition) for both revenue and invoicing.
    Without enabling this option, revenue generation supports partial billing for transactions.
    New Parameters for MGT: Invoice Review
    Project Status
    Project Closed After Date
    Project Range
    New Parameters for MGT: Unbilled Receivables Aging
    Project Status
    Project Closed After Date
    Project Range
    Oracle Project Management New Audit Process for Project Performance Reporting Setup
    AUD: Project Performance Reporting Setup
    New Parameters for Refresh Project Performance Data Process
    Actual or All Amounts (Plan and Actual)
    Workplan Version
    Financial Plan Version
    Workplan EnhancementsAbility to Delete Published Workplan Versions (except the latest published version, baseline version, and workplan versions included in a program hierarchy) Usability Enhancements
    Update Work Breakdown Structure page is now obsolete.
    View, maintain, and update a workplan structure from the Update Tasks page.
    Where no latest published workplan version exists, the current working version displays on the Update Tasks page when navigating to the Workplan Tasks.
    Indent or outdent multiple workplan tasks in a single step.
    Confirmation, information, and warning messages appear on HTML pages during Apply Latest Progress as well as the Submit Progress processes. Messages include status information during processing and the availability of the latest progress information.
    New Public API for Creating, Maintaining, and Deleting Programs New set of public API procedures:
    Designate a project as a program and indicate whether projects linked to the program can belong to multiple programs.
    Create links from a program to one or more projects
    Update links from a program to one or more projects
    Delete links from a program to one or more projects
    Budgeting And Forecasting Enhancements Enhanced Automatic Calculation and Derivation Logic
    For plan lines that do not have a specified a quantity, the amount is no longer copied to the quantity field with the rate value set to 1.
    Rate now has a lower precedence than quantity and amount in automatic calculations.  The rate will be re-derived when the quantity, rate and amount are entered at the same time for a plan line.
    When the burden multiplier is overridden by updates to the raw cost or burden cost, subsequent calculations of the burden cost will use the override burden multiplier.  The same is true when the markup percent is updated by changes to plan line components:  the override markup percentage will be used in revenue calculations.
    Enhanced Handling of Override Rates on Budget / Forecast Lines
    Override rates for a planning transaction on Edit Budget and Edit Forecast pages.
    o   Raw Cost Rateo   Budened Cost Rateo   Bill Rate
    Override rates are applied to all existing and new periodic lines for the planning transaction.
    Average rates fields on these pages are now disabled for entry and are used for display only.
    Simplified Addition of Planning Elements and Resources
    New but unbudgeted tasks and resources can be added to a budget or forecast version.
    Add either all new tasks and planning resources or new tasks only to the current plan version.
    Self Service Expenditure Inquiry
    Ability to drill into expenditure details from the Financials tab.
    Reporting Pack for Generation and Distribution of XML Publisher Reports
    A reporting pack is a set of report templates and recipients by project role.
    The Generate Reporting Pack concurrent program emails the reports generated from the report templates based on pre-defined intervals.
    The report template establishes each report’s layout and content.
    New reports templates are configured using XML Publisher tools.
    New or modified reports can be added to an existing reporting pack or be used to create an entirely new report set.
    Predefined data definition files that contain XML tags for performance measures and project data are provided.
    Predefined Reports:
    Project Change Document Report
    Project Committed Cost Report
    Project Cost Detail Report
    Project Cost Labor Report
    Project Cost Summary Report
    Project Earned Value Report
    Project Financial Summary Report
    Project Forecast Summary Report
    Project Revenue At Risk Report
    Budget Integration with Federal Budget Execution and/or 3rd Party Budget
    The budget integration workflow supports integration with the Federal Budget Execution module..
    The workflow can be customized to interface budget lines to external budgeting applications.
    Microsoft Project 2007 Certification
    Integration with Microsoft Project 2007 is supported.
    Project Performance Reporting: Additional MeasuresYTD, QTD and At Completion calculated measures are available on the following pages:
    Performance Overview Period-to-Date
    Summary/Analysis
    Task Summary/Analysis Resource Summary/Analysis
    Project Performance Reporting: Inter-Project Revenue / Billing AmountsInter project revenue / billing amounts are available on the following pages:
    Project List View Workplan Cost
    Exception Reporting Performance Overview
    Task Summary/Analysis Resource Summary/Analysis
    Period-to-Date Summary/Analysis
    Supplier Cost DashboardSubcontractor Payment ControlsSupport for Pay when Paid Scenarios
    A new “Pay when Paid” payment term for subcontracts automatically places holds on all subcontractor invoices under that subcontract until the corresponding customer payment is received.
    Subcontract Payment Controls workbench allows project manager to manage the holds, with visibility into both the customer invoices and the related subcontractor invoices.
    Workflow notifications about the receipt of the customer payment allow the project manager to automatically or manually release the subcontract invoice.
    Associations between the customer invoices and the subcontractor invoices may be automatically maintained based on the billing of project expenditures for cost-plus contracts, or may be manually maintained for fixed price contracts.
    Payment Controls for Subcontract Deliverables
    Support for the tracking and monitoring of subcontract deliverables that place automatic holds on subcontractor invoices in the case of noncompliance.
    Oracle Procurement Contracts allow a subcontract administrator to specify payment impact controls that will take effect when a subcontract deliverable is not met.
    From the Subcontractor Payment Controls workbench, the project manager can view a checklist of the all the current subcontract deliverables, to assist in evaluating the subcontractor status prior to releasing monthly progress payments.
    Oracle Project Resource ManagementResource Search Enhancements
    Resource Search by Email Address
    Resource Search by Person Type
    Streamlined Navigation on Staffing Home
    Cross Validation of Project and Assignment Dates
    Requirement start dates are equal to or greater than the project start date and less than the project end date and that finish dates are equal to or less than the project end date but greater than the project start date.
    Assignments cannot be added beyond the project end date.
    A project team role end date cannot be beyond the project end date. If the roles are created before the project end dates are entered, users will receive an error if they later try to enter an end date that is earlier than the end date for existing roles.
    When project transaction dates are moved corresponding assignment dates are validated against the new project dates. If the new project transaction dates fall outside the dates for existing assignments, users are given an option to shift the assignment dates or cancel the date adjustment.
    Defaulting of Work Patterns’ From and To Dates
    Work pattern from and to dates will default from the requirement start and end dates.
    Improved Exception Handling of Maintain Project Resources Process
    PRC: Maintain Project Resources delivers improved exception handling and notification when it encounters errors while processing employee records.
    New Public APIs for Resource ManagementThe new PJR APIs fall into the following four categories:
    Requirement Public APIs
    Assignment Public APIs
    Candidate Public APIs
    Competence Public APIs
    Organization Authority: Obsolete Forecast Authority
    Removes the forecast authority functionality from the organization authority form
    Removes existing security data relating to forecast authority.
    Replaces the PJR forecast functionality with the new HTML based forecasting functionality. The new forecasting functionality has its own security mechanism and does not honor the old forecast authority model.
    Improves the performance of security calls to organization authority because the existing security data is being removed.
    Oracle Grants AccountingAward Budgeting Enhancements Budget period validations
    Budget periods will not be validated across award budgets when those awards fund a single project.
    Flexibility to establish award budgets based on the actual duration of the award, while not being confined based on the existing budgets already established for the project.
    Automatic summarization of project budgets
    With the new budget period validations, automatically summarize to a project budget viewable in Project Status Inquiry.
    Two profile options have been added to identify the budget entry methods that will be used to summarize the project budgets.
    Budget Line Sorting Option
    Sort budget lines by Resource name, or by effective dates for budgets with date range periods.  Provides the flexibility to view the budget lines by period or by budgeted resource.
    Award Status Inquiry Enhancements View by budget period
    Allows the Find Award Status window to be limited to a single period, range of periods, or inception to date for a particular award.
    Reflects the budget periods entered on the award budget.
    GL and PA Date Parameters on Find Expenditure Items window
    GL and PA date parameters have been added to the Find Expenditure Items window.
    GL Date Parameters on Find Commitments window
    GL Date parameters have been added to the Find Commitments window.
    KKG

  • Compare Oracle Project Management and Primavera

    Hi All,
    We are using Primavera today and it is not integrated to Oracle.
    We are also currently implementing Oracle Projects Management (R12.1.3) and trying to evaluate if Primavera can be replaced by Projects Management. Based upon my little experience with Primavera - I see some advantages of Primavera over Projects Management e.g.
    a. Primavera is more user friendly than Oracle Projects Management.
    Primavera: easy to create workplan; configurable views; generate reports with gantt charts
    b. Primavera has scheduling engine to derive schedules based upon dates/duration/logic while Project Managment does not have it.
    c. Gantt charts are better in Primavera than Oracle Projects Management.
    Has anyone also done similar kind of analysis and evaluated the need of Primavera integration with Oracle Projects Management? I would appreciate if you can share your inputs.
    Thanks,
    Nitin

    Hi,
    I have used both the product. For project management i would suggest to use primavera for the same reason u mentioned.
    the only disadvanage in primavera is it is not integrated with ERP.
    Now oracle provide a AIA PIP integration package to integrate Primavera with oracle Projects(Limited integration). Use primaver for Project managment and oracle for Project Costing and Billing
    Govind

  • REPORT-12KST1A or T-CODE 'CJE0'   Adding a column in predefined report

    hi guru's
    Please let me know how to insert a new column in the (PROJECT SYSTEMS )
    report 12KTST1A . for that reason i copied that report in customising but
    i cant able to edit that because it is generating automatically.
    The path to get to this report is:
    Accounting
    Capital investment management
    Investment projects
    Information system
    Report selection
    Costs
    Budget-related
    Budget/Actual/Commitmt/Rem.Plan/Assigned
    Then (after entering Cntl Area & DB prof), we narrow data using "Dynamic selection" icon & check Company code. Then enter valid company & save.
    Then enter project range, then execute.
    OR
    T-CODE "CJE0".
    is there any procedure to insert a column .
    I have not used Report Writer/Report Painter previously
    Thanks in advance for any and all help!
    regards,
    satheesh.
    Edited by: satheesh sath on Jan 15, 2008 5:40 AM

    I have solved it myself by adding few lines in stored procedure. Would like to share the solution, so that it will be helpful for others.
    Open the stored procedure which we are using for the default "List of Incidents" reports.
    Add the below under SELECT
    SupportGroup = ISNULL(TierQueuesDS.DisplayName, TierQueuesEnum.IncidentTierQueuesValue),
    TierQueuesEnum.IncidentTierQueuesId AS TierQueuesId,
    Classification = ISNULL(ClassificationDS.DisplayName, ClassificationEnum.IncidentClassificationValue),
    ClassificationEnum.IncidentClassificationId AS ClassificationId,
    Add the below under FROM
     LEFT OUTER JOIN
     dbo.IncidentTierQueuesvw AS TierQueuesEnum
     ON TierQueuesEnum.IncidentTierQueuesId = I.TierQueue_IncidentTierQueuesId 
     LEFT OUTER JOIN
     dbo.DisplayStringDimvw TierQueuesDS
     ON TierQueuesEnum.EnumTypeId=TierQueuesDS.BaseManagedEntityId
     AND TierQueuesDS.LanguageCode = @LanguageCode
     LEFT OUTER JOIN
     dbo.IncidentClassificationvw AS ClassificationEnum
     ON ClassificationEnum.IncidentClassificationId = I.Classification_IncidentClassificationId 
     LEFT OUTER JOIN
     dbo.DisplayStringDimvw ClassificationDS
     ON ClassificationEnum.EnumTypeId=ClassificationDS.BaseManagedEntityId
     AND ClassificationDS.LanguageCode = @LanguageCode
    Then open the report from Report Builder and add new column in the design. Add Support Group and Classification as a column in the report.
    Thanks & Regards, Dinesh

  • Attribute Functions in Oracle Project Management Setup

    I have been trying to find the functionality and applicability of the menu option " Attribute Functions" that is available in Oracle Project Management Setup.
    I have used attribute groups and context to create view / placeholders to capture additional information related to the project, but have not been able to figure out the applicability of Attribute Functions.
    Please help me if anyone has used it or know how to use it.

    Hi,
    Refer Oracle Project Management User Guide. (Section 2: Workplan and Progress Management)
    Oracle Projects archives all submitted task and workplan progress. You can correct
    submitted progress records and create backdated progress records.
    Backdating Progress
    ============
    You can create backdated progress records to fill gaps in the progress history of a task
    or project. You can select any non-cycle progress date prior to the system date and enter
    progress for this past date.
    For example, you can enter backdated progress for a Friday in the past even if a project
    has a progress cycle with Monday as the reporting day.
    You enter an As of Date, progress status, a brief overview, comments, and physical
    percent complete when you enter backdated progress.
    Backdated progress transactions are for informational purposes
    ~Sumit

  • Adding new column to production database

    I have to add a new timestamp column, that defaults to the current date/time, to an existing production database. The table is large - 150M records. I am trying to understand the ramifications of adding a new column to a table this large that gets hit often, mostly with inserts and reads. The column does allow null values and I am not going back and populating existing records with a value. Basically, I am looking for some best practice guidelines - how to prepare, what to expect, what other processes should be followed along with this schema update.

    Radiators wrote:
    Thanks, I have not found any %TYPE or %ROWTYPE dependencies on the table I am altering. But at the same time I do not understand how these types of dependencies would invalidate packages. I wouldn't be breaking any %TYPE dependency because I am not dropping columns, only adding a new one. And according to documentation for %ROWTYPE - "If columns are later added to or dropped from the table, your code can keep working without changes." Can you point me to Oracle documentation that describes your concern in detail? Thanks.you can test it yourself
    SQL> CREATE TABLE abc (c1 NUMBER);
    Table created.
    SQL> INSERT INTO abc
      2       VALUES (99);
    1 row created.
    SQL> CREATE OR REPLACE PROCEDURE test_proc
      2  AS
      3     v   abc%ROWTYPE;
      4  BEGIN
      5     SELECT c1
      6       INTO v
      7       FROM abc
      8       WHERE ROWNUM = 1;
      9  END;
    10  /
    Procedure created.
    SQL> SELECT object_name, status
      2    FROM user_objects
      3   WHERE object_name = 'TEST_PROC';
    OBJECT_NAME                STATUS
    TEST_PROC                    VALID
    SQL> ALTER TABLE abc ADD (c2 VARCHAR2(10));
    Table altered.
    SQL> SELECT object_name, status
      2    FROM user_objects
      3   WHERE object_name = 'TEST_PROC';
    OBJECT_NAME                 STATUS
    TEST_PROC                     INVALID
    SQL> you should also consider the chance that some where if people are using "select * into" using this table, which will fail since you added new column. i don't see any unusual performance bottlenecks by adding a new column. in case of the backups, yes the earlier backups will not have the column. if you restore it, you will see earlier table structure itself. i have one specific question. why are you not attempting this in development/test environment first? even if it is a simple insert, it's always important to do it in test environments before attempting on production db. one thing for sure i know is, after adding column, you will have to recompile all the invalid dependencies. i think, it's better if you attempt it in test db and come up with any issues you see rather than asking a general question where problematic scenarios are plenty and rarely unknown before hand.

  • Adding Additional Columns in LOV,That column capturing values from function

    My requirement:
    Adding Additional Columns in LOV,That column values capturing values returned by function.....
    Give me the ides to achieve this...

    Hi Subramaniam,
    If your requirement is to call a Database function then please make use of the below code ,
    import java.sql.CallableStatement;
    import java.sql.SQLException;
    import oracle.apps.fnd.framework.server.OADBTransactionImpl;
    OAApplicationModule oaapplicationmodule = oapagecontext.getApplicationModule(oawebbean);
    OADBTransactionImpl txn = (OADBTransactionImpl)oaapplicationmodule.getOADBTransaction();
    CallableStatement cs = txn.createCallableStatement ("begin :1 := xxpackageName.xxfunctionname(:2,:3); end;",-1);//Replace your function Name
    try
    cs.registerOutParameter(1, Types.VARCHAR);
    cs.setString(2,InputParam1); // InputParam1 is the name of variable captured from the OAF page and passed into function as input parameter
    cs.setString(3,InputParam2); //InputParam2 is the name of variable captured from the OAF page and passed into function as input parameter
    String outParamValue = null; // outParamValue will capture the value returned by function .
    cs.execute();
    outParamValue = cs.getString(1);
    catch(SQLException sqle)
    throw new RuntimeException(sqle);
    finally
    cs.close();
    Let me know if its not clear .
    Keerthi
    Edited by: keerthioaf on Nov 23, 2012 5:17 AM

  • MSP Integration with Oracle Projects

    Hi Dina,
    Does the integration between MSP and Oracle Projects work without any issues in R 12.1.3? We've tried using it in the past with R 12.0.6 but have to say the experience was not good. It used to work at times and fail on other times. Most of the times the first time import from MSP to Oracle Project used to work but subsequent changes to the WBS used to give issues while trying to import into Oracle Projects (even though the link to the Oracle Project existed in MSP).
    One of our new customers (Construction Company) wants to create the WBS in MSP (Microsoft Project ver 2003 or 2007) and then import it into Oracle Projects to track progress, effort and cost. Any changes to the WBS (which happens frequently) will be done in MSP and imported back into Oracle Projects. Does the above mentioned requirement work consistently in R 12.1.3? Please let us know.
    Thanks
    Regards,
    Sri

    The MSP integration requirements that you describe should work in the latest versions of 11i e.g. (FP.M RUP4) as well as R12.1.3.
    My experience is that providing all scheduling is done in MSP then the integration functionality works well.
    The recommended process flow for MSP integration is:-
    •     Oracle Projects: A project manager creates a project in Oracle Projects from a project template containing information for deliverables, work breakdown structures, and resource assignments
    •     MSP: The unscheduled resource and workplan data is downloaded to Microsoft Project for scheduling
    •     MSP: The project is scheduled in Microsoft Project based on task assignments, task dependencies, task constraints, and other attributes
    •     MSP: The scheduled workplan data is uploaded to Oracle Projects for publishing
    •     Oracle Projects: The project workplan is published in Oracle Projects
    •     Oracle Projects: After the workplan is published, the project is accessible to all team members working on the project. Team members work on their assignments and report their progress in Oracle Projects
    •     Oracle Projects: The team members' progress on the tasks is collected for updating the project plan
    •     Oracle Projects: The project plan is updated with the team members' progress
    •     MSP: The project is now unscheduled. The unscheduled project plan is downloaded to Microsoft Project for rescheduling
    •     MSP: The project plan is rescheduled in Microsoft Project and the task information is updated
    •     Oracle Projects: The rescheduled workplan is uploaded to Oracle Projects for publication
    Andy.

  • Oracle Projects integration to Primavera

    Hi,
    We are integrating Oracle Projects to Primavera for a construction client.
    We are able to:
    - Send project header and wbs information from Oracle Projects to Primavera
    - Send activity and resource assignment from Primavera to Oracle
    However, when we enter actual efforts and dates in Primavera, we are NOT able to interface this information back to Oracle Projects.
    All setups as per 'E15794-01_PIP Integration pack.pdf' document and Project Management User Guide are done.
    Has anyone done a Oracle Projects-Primavera integration, or has any clue? Thanks for your help in advance.
    Regards
    Balaji

    Hi Dean and Dina,
    Thanks for your answers. Following is the missing info:
    - Yes, we are using the AIA PIP
    - We are using 'Workplan enabled' projects for integration with a 'Partially Shared Structure'
    - In integration options, we are only integrating 'Workplan' with a 'Working Version'
    - We are trying to send only progress information from P6 to Oracle Projects, not the time card info
    Iniitially, when trying to send progress from P6 to Oracle Projects, we were getting the error - 'You cannot update a published version of the workplan'
    However, after checking the following flags, we stopped getting any errors in AIA/middleware and still not getting any data into Oracle Projects:
    Projects --> Setup --> Integration settings:
    Integrate - Workplan - Send Task - Current Working Version
    Integrate - Workplan - Receive Task
    Workplan --> setup:
    Allow Physical Percent Complete Collection
    Allow Physical Percent Complete Overrides
    Thanks for your help.

  • Dina, Differenc Betn R12 Oracle Projects Vs Oracle 11g Fusion Project Portf

    Hi Dina / Experts,
    Can anyone of you help me in getting the product features differences between R12 Oracle Project Suite Vs Oracel 1Fusion 11g Project Portfolio Management?
    can you please provide me reference document / link / RCD / PPT if possible..which helps in understanding exact differences?
    Thanks
    :-)

    Hi Chris, Steve,
    Not sure how it is working for you, but what I trying to is to reuse the sharable base adf bc model in multiple projects (using jdev 11.1.1.1.0). Basically, i have the following structure
    1. Base Model project (first workspace): that has an ADF Library deployment profile. In this project, I made sure that the project -> Project Properties -> Business Components -> Options-> Copy Package XML files to ClassPath is checked.
    2. Another MODEL project (Second workspace): I don't have any view controller project here. I can add the adf library (created in #1) through the resource palette to my second model project that is in a separate workspace, but when i try to create a new entity in this project that is based on an old entity, the wizard does not show any base entities that were packaged in the base model project that was created in #1.
    Do you have any tips? In additon to the links you mentioned above, I have gone through the following, but of no avail. I would appreciate any help.
    Difference between adding and importing BC4J
    http://radio-weblogs.com/0118231/stories/2005/08/11/differenceBetweenAddingAndImportingBusinessComponents.html
    Working with Libraries of Reusable Business Components
    http://download.oracle.com/docs/cd/B32110_01/web.1013/b25947/bcadvgen.htm#CHEFECGD
    http://technology.amis.nl/blog/215/organization-of-bc4j-domain-eo-and-business-vo-package
    http://radio-weblogs.com/0118231/2005/09/29.html
    Thanks,
    AJ

  • Oracle Projects for Exploration and Drilling

    Do oracle projects can be used for exploration and drilling in oil and gas company?
    What are modules which can cover these operations? Please Help

    Hi
    Oracle Projects suite can be used for that industry. You could set each exploration initiative as a single project, track its execution and actual costs versus the schedule and cost budget.
    At minimum you will need Projects Costing. You might also explore the added value of Project Management.
    Dina

  • Budgetary Control and Oracle Projects

    Budgetary control for Oracle Projects was mooted as future functionality in 11i. Is this now a reality, and in which release of 11i?
    Thanks

    Budgetary Control has been added to Projects as part of MiniPack H. The documentation can be found on MetaLink. However, the docuementation does not provide a step by step set guide so I'm having trouble testing this new feature. If you find anyone who has more information regarding budgetary controls and funds check, please let me know.

  • Adding a printer to Oracle Apps 10.7 NCA

    I have a newbie question concerning adding a printer to Oracle
    Applications.. I would like to know if there is any special setup required
    to make a printer available within the Application, or is it just a matter
    of adding the printer to the network?
    Thanks in advance,
    GM
    null

    Hi,
    You need to register the printer and the path in the description column (for reference)in the system Administration responsibility.
    The navigation is
    Install--> Printer->Register
    Once the printer is registered choose the type and attach the style and the driver for that printer.
    The print styles will give you the layout on the number of columns and rows to be printed.
    The driver will have initialization string which have been defined as default ones but the same can be changed depending on the printer which you are operating (like HP etc.)
    You can choose the one which have already been defined or create your own types.
    These strings have a bearing on the way the outputs are printed.
    Normally all printers whether they are stand alone or network printers are registered.
    I hope I have made myself clear.
    Thanks and Regards,
    Raj..

Maybe you are looking for

  • How to print JTextArea??

    I am trying to print JTextArea which has more than one page of text. When there is more than one page of text in JTextArea, it only prints what is there on first page eventhough it print multiple pages. Here is the code I am using. Let me know if you

  • How can I know if my podcast is still under review a week after its submission ?

    I had a podcast that had been approved by Apple ; this podcast had enough success so I had to change my host for another one. Changing the feed of a podcast that can be found in iTunes isn't possible. So I submitted another feed, with same content fo

  • How can I configure a mysql-database for new cms install?

    I just install a mac os x server on os x 10.8.4, but can't create a database to install a cms, how can I do this ? How cann I access the database from admin window or else ?

  • Memory problem, but there is enough space - virus? pls help!

    Since yesterday I am unable to download anyfile, I always get a message saying that there is not enough free disk space, but I happen to have 3GB space still left. I can't save any textedit document, it takes forever to reboot and when I connect my u

  • Element GRP is not available in the container

    Hi All, I am getting a error ''Element GRP is not available in the container'' whenever I try to create a PR and the workflow is triggered. I am using a custom rule to determine the approver. The workflow is not able to determine the agent and return