Assignment between network , activity , person , planned number of hours

Hi
In CJ20N , we are doing person assignment against activity
Against activity , in internal tab , we are entering the planned no of hours in the field Work
Similarly , against each person , we enter the splitted time
I need to know , in which Table , we can find the relationship between network , activity , person , planned number of hours (at that person level)
rgds
sandeep

Hi Sandeep ,
AFVC, table for activity
KBED, table for main capacity.
KBEZ, for Split
KPER, person assignment of each period.
There is a correction report ZKBED_DEL of note 542941, You get more details of the relationships of the tables above, if you view (or debug) the codes.
Kind regards,
Zhenbo

Similar Messages

  • Splits (Person Assignment) in Network Activity

    Hello Experts,
    I have planned 10 hrs work in a network activity. After that , In the person assignment tab of Network Activity, I have assigned a person and gave work as 15 hrs.
    When I press enter, I got an information message " The work of all the splits is greater than the work in the operation"
    How can I make this information message as error message? I could not find in the configuration.
    Any thoughts would be appreciated.
    Regards
    Srinivasan Desingh

    Hi Srini,
    Any message if you want to change that from warning or error and vice versa......you have to change  the message category in the customozation of " Define system  message attributes".
    SAP provides these kind of customization for puchasing, process order, inventory and some other function modules.... Unfortunately PS module doesnot have this option.
    But it is possible to do so....with the help of ABAP consultant.
    Here are some of the inputs....
    Goto SE80...ABAP workbench
    Call for Repository browser
    and then enter package and CY and drill down box which is appear in the left side of your screen.
    You can see your message 411 at the right hand part...
    With the help of ABAPer...it is possible to do so...
    Hope it will helpful for some extent.
    Regards
    Vetri

  • Why do my contact photos keep getting assigned to the wrong person/number?

    This has happened to me twice recently:  my phone rings and the wrong contact photo appears with the wrong phone number.  All my contact photos are assigned to the wrong person/phone number.  Any ideas on what's going on?  Thanks!

    Thanks for your reply.
    Can I get this straight in my mind? Does this mean that I will have to put ALL the photos stored on my Laptop into ONE  large folder, then divide it up into sub-folders? Then I can copy each sub-folder?
    Sorry to sound stupid, but most things I try on my ipod don't seem to work for me. I think I am getting a bit old for all this.....lol.
    .......Actually thinking back, a while back I did click on my main folder called "Nikon" and that did copy everything in it, but just in one whole lot, ie 1,000 photos.........................so nothing was sub-divided into folders, ie. holiday 2010, holiday 2011. Is that another problem I have created for myself?
    Thanks for your patience.

  • Activity dependant planning and Activity independent planning

    Hello gurus,
                     Can anyone please explain the difference between the Activity Dependant Planning and Activity Independant Planning with some examples
    thanks
    rihana
    Please, search Web

    Hi Rihana,
    Activity indipendent planning : Activity-independent cost planning covers both primary and secondary costs, but does not refer to a specific activity type.  Eg : internal and external distribution
    Activity-dependent planning : Activity-dependent planning of primary and secondary costs, on the other hand, enables you to plan both fixed and variable costs. You may require this functionality if your costing system uses flexible standard costing based on marginal costs. In this release you can carry out flexible standard costing based on full costs.
    This means fixed costs are used to calculate the cost rates and are in effect converted to variable costs.
    Regards,
    Shivalli

  • BAPI to upload Person Assignment data under network activity

    Hello All!
    Can anybody tell me the appropriate BAPI that can upload the data of Person Assignment tab under network activity of Project System(TCode:cj20n)? I.E. data like Split Person Date Time Work Un and others data.
    Thanks in advance.
    Regards.
    Sarbajit

    Hi Majumdar,
    you can find it by running transaction ST05 against CJ20N.
    try bapi-
    BAPI_PROJECT_MAINTAIN
    Regards,
    NaPPy

  • Network 4004391 requires assignment to an activity number

    Hi
    I have created PR in PS WBS > Network > Internal Activity > by assignininh material to this Internal activity. While doing this system took to me on settlement rule credation screen for the activity.
    Previously it was not system was not taking me to this screen.
    Can any body tell me why ?
    I alredy maintained settlment profile for the network type having defaule settlment to WBS. And now system status of activity is CRTD SETC SETM
    PR created succesfully.
    Now when converting PR into PO i am getting folowing error message.
    Network 4004391 requires assignment to an activity number.
    Message no. KI292
    Diagnosis
    The given network cannot be assigned without specifying an activity number.
    Procedure
    Enter the number of the network activity required.
    please reply ASAP.
    regards,
    Pradeep

    Hi Viren,
    As i am creating PR from PS my a/c assignment category is Q and config for doc type is fine.
    I am facing this issue only in QUALITY system, in develoment and production system all is working fine.
    Even though settlement profile is attached to network type why system is taking me to settlement rule cteation screen while creating activity ? As i alredy maintained settlement profile then settlement rule shuld be created automatically and system should not take me to that scrren.
    And for the PO i am taking reference of the created PR so alredy theres is reference of a/c assignment WBS > Network > acitivity as it is created through PS.
    As i said i am facing this issue only in QA and not DEV and PROD i am not able to identify the reason.
    regards,

  • SAP Message No-KL 294 Network Activity with invalid Internal Number

    Hi,
    I am getting System Error:NETWORK ACTIVITY WITH INVALID INTERNAL NUMBER" while doing MIGO.
    I have checked network activity assigned to PO is exist but this shows some internal Number "Plan no.f.oper." which does not exist.
    Please let me know how should i solve this error.
    thanks
    Sunil

    Hi Sunil.
    Did you get any response from SAP?
    I have as similar or maybe the same problem.
    And I found out:
    When I create the purchase request out of the Project-Builder (CJ20n) - SAP seems to lose the entry of the field 'AUFPL' in the table 'EBKN'.
    In these rare cases (this problem is only in about 2-3 % of our purchase requests) the network elements still exist - so they are not deleted or something like that.
    I created a routine, in which I read the entry of 'AUFPL' with the corresponding network number out of table 'EBKN' as key, to correct these wrong purchase requests.
    But I didn't find the reason for the problem, yet.
    Every advice would be great,.
    Best regards,
    Marc

  • Trying to find the Network Activity number from the CATSPS table

    Hi Experts
    I am trying to build a report to show unprocessed time on Network Activities. The time is entered via CAT2 and transferred to CATSPS via the CATA job.
    Once the data hits the table, an internal system number is given to activity.
    I have the following example:
    Say I have three Network Activities all linked to the same Network and WBS as follows:
    Network   Activity #
    43000121  0001
    43000121  0002
    43000121  MTS
    When I post time against the 2nd and 3rd NWAu2019s, CATSPS has the following entries:
    RNPLNR               RAUFPL                RAPLZL
    000043000121    0000000182         00000002
    000043000121    0000000182         00000003
    Now the RAPLZL field has no visual link to the NWA.
    Does anyone know of the Internal table that holds the link between the RAPLZL field and the Activity that is represents.
    I have already looked at PLPO (no entries).
    Any other suggestions would be appreciated.
    Thank you in advance

    Match the entries RAUFPL, RAPLZL of CATSPS with AUFPL, APLZL of AFVC table, you will get the activity number(VORNR)

  • How to check plan line items for plan cost at network activity level?

    Dear all,
    How to check plan line items for plan cost at network activity level? The plan cost is done in network activity in CJ20N.
    I am not able to check using CJI4 or CJI9 report.
    Kindly advise.
    Thanks and regards,
    Jessie

    Hi Jess,
    Have you checked the navigation part which is being displayed on left hand side of report S_ALR_87013565 and S_ALR_87013533.? There you have option to check transaction currency and object currency when you double click on it.
    In case if it is not being displayed under navigation. Then you can bring them on from transaction code CJE2. For eg: Report group for S_ALR_87013533 is 12KST1C. Double click on it and it will open up to do changes in report layout and many more. There you also have options to bring on transaction currency too. Similarly, you can check for other report groups as well just by checking the report description.
    But I am not sure if suits your requirements. Wait for other experts to comment on this.
    Regards,
    Amit

  • Assignment of default activity type to individual person

    Hi All,
    I have following scenario.
    One maintenance order is created with one operation. Three persons are assigned to the same operation. All these three persons are having different per hour rate and so having different activity types.
    I have mentioned all these 3 activity types in assigned workcenter.
    But while executing in maintenance order I can assign only one activity type in operation tab and so the same is appearing during time confirmation as default.
    I need respective activity types to be appeared by default for each of persons. How can be achived this?
    Sundar

    Hi,
    As 3 different activity types are having 3 different per hour rate, it would better to define sub operations based on the activity type & assign the activity types separately for each sub operations.
    Regards,
    Maheswaran.

  • FM / BAPI - CJ20N - updating person assignments on network activity

    Hi,
    I am looking for a FM / BAPI to update person assignments on network activity (which is already created), can some one suggest me is there any FM / BAPI / any other method to update those.
    Regards,
    Prasad Sreerama.

    Hi Sanjeev,
    I have to update person's through inbound program, it would be great if i get any FM / BAPI for this.
    Regards,
    Prasad Sreerama.

  • Link between Contract line and the Billing Plan number

    Hi All,
    I have a requirement which needs a link between the Contract Line item and its Billing Plan Number. I basically have to find out the contracts which have a billing block. So a invoice would not have been created to that line item.
    Please let me know if such a link exists.
    Thanks in advance,
    jr.

    Hello
    In table <b>VBKD </b>(Sales Document: Business Data) you will find the link between the contract (VBELN) and the billing plan (FPLNR). If POSNR = '000000' then this is the billing plan of the contract header.
    The billing block can be found in VBAK-FAKSK.
    Finally, billing plan details can be found in table FPLA. If FPLA-RFPLN is filled then the item billing plan is linked to the header billing plan.
    Regards
      Uwe

  • Email notification for the Activity Person Assigned

    Hi,
    I have a query from my client. They want to know the possibility of sending an email notification to the Person Assigned to an activity. Once the activity is REL, system should be able to send email (Outlook email or SAP mail) having the task details to the Person Assigned to that activity.
    Any suggestions/inputs are welcome.
    Best Regards,
    Mohammed

    Hi,
    You have to go for a ABAP development that trigger uppon activity REL.
    Thanks & regards,
    SL

  • Secondary costs planning on network activity

    Is possible to plan secondary costs on network activity (without activity type on work center)?
    Thanx

    Hello Keshav
    I have in CO Area currency          CHF
    In Company Code I have             EUR
    Then object currency for network activity                   field  AFVGD-OWAER  is                            u201CEURu201D
    For Material planning in networks Currency Key     field  TKA01-WAERS is                               u201CCHFu201D
    Before reporting, I would like see the above currencies as equal using CJ20N.
    Thanks
    Salvo50
    Edited by: Salvo50 on Nov 7, 2011 11:33 AM

  • Network activity when switching between documents

    We have a user with InDesign CS5.5 on a Mac. Here's the scenario:
    -The user has a document with many linked images in multiple libraries (document is stored on the network).
    -The user opens a second document or a blank document.
    When the user switchs from the blank document to the "big" document, it takes 5-7 seconds to switch over. Opening the Activity Monitor in Mac OS shows that a lot of network activity is going on during the swtich between documents. It looks like it re-downloads the whole document each time. Switching from the "big" document to the blank one is pretty instantaneous. Is something trying to "update" the whole document each time the user switches tabs?

    That's what I'm thinking, but it wasn't doing that before and isn't doing it on other computers.

Maybe you are looking for

  • Calculating the size of each record in a table?

    Hi to all, I trying to create histograms based on the unique record sizes in a particular table. However , in order to do that I need to calculate the size of each record in the table (in kilobytes preferably) and to get a list of unique record sizes

  • Button to extract pages

    myexportFunc = app.trustedFunction(function(){ ////Get Naming Convention var cRtn = app.response('Enter naming convention for section:'); ////Save to current location. Get path of current doc var testing = this.path; var test = testing.split('/'); va

  • Photo scanning issue

    i can not scan photos from my kodak printer from photshop..it is reading an old printer that is no longer installed...kodak states it is with the software from adobe?can someone  please help...thanks

  • Netstream Object

    "The NetStream class opens a one-way streaming connection between a   Flash Player or AIR application  and Flash Media Server, or between a Flash Player   or AIR application and the local file system.   A NetStream object is a channel within a  NetCo

  • Complete URL of an iView Component !!

    Environment : EP 6.0 Sp2 Following is the complete url of an iview ... http://<servername>:<port>/irj/servlet/prt/portal/prtroot/<componentName>.default I am using the following code to get the url ... IPortalUrlGenerator portalGen = null; IUrlGenera