Assignment of WC in WBS element

Hi all,
Can we assign workcenter on WBS element

Hello,
          1st we should be clear that what is the functionality of work center?
Work Center is an Organisational unit that specifies where and by whom an operation is to be executed
In SAP PS work centers used for workforce / resource / capacity planning /scheduling a work . That all is possible in activities and process.
So we  need activity to assing work center not the WBS.
Thanks

Similar Messages

  • Assigning GL accounts to WBS elements

    Hi,
    Where can we assign GL accounts to WBS elements in Config or in the system ( TX )?
    issue is that when an expense is booked it is accepting any GL account while booking the expenses.
    Kindly help
    Thanks,
    Tanya

    Hi Tanya,
    I think, you want to ensure that you need to allow only specific GL codes to be posted to WBS. If yes, then this can be achieved by using validation functionaliy (t code OPSI). In validation you can specify a set of cost elements, which are allowed for postings to WBS.
    Normally all GL codes, which have been created as cost element in controlling can be posted to WBS.
    Award points, if useful.
    Regards
    Rakesh Pawaskar
    Message was edited by:
            Rakesh Pawaskar

  • BAPI to assign budget to a WBS element.

    hi,
    I need to find BAPI to assign budget to a WBS element in a project.
    The transaction to do this is CJ30.
    Its imp...
    Please help..
    Thanks & Regards
    Shabari

    Look at BAPI_RESERVATION_CREATE1
    rgd
    Frédéric
    (next time search the BAPI with transaction BAPI or in ifr.sap.com)

  • Assign Multiple equipments to WBS element

    Hi all,
    Can anybody tell me how to assign mutilple equipment to single WBS elements. As far as i know we can assign only one equipment to WBS element.
    My requirements is to assign more than one equipment to particular WBS elements. How should i do?
    Please help me
    Thanks

    Hi to the best of my knowledge you can not assign more than one equipment to a WBS in standard SAP
    It would all depend on how you structure your project in the past I have seen
    Project with first level WBS and then folliowing on from there you can have multiple WBS elements below this one for each equipment. This would then allow for reporting etc at both levels of the WBS.
    If you can supply a little more information I will try and help further.
    Jim

  • Assign activity type  to WBS element  without network

    Hi There,
    I have a customer business scenario where I have to assign activites to WBS element  without network.
    can any one help me on that..
    Thanks,
    Paritosh

    Hi Thomas,
    Thanks for your information. I have created customer Project with one network and multiple WBS.
    But another issue related to project RBB & DIP profile. I have a scenario it like quantity should be updated from DIP profile in quotation and billing price should take from sales condition record.
    After booking activity base cost directly from KB21N and it is showing in line item. Still when I am trying to run transaction with DP82 to update sales base price system is giving me a message "No expenditure item found" although in WBS level showing all the cost/quantity.
    Can any one tell why I am getting message and how to correct it?
    Paritosh

  • Creation of Documents and assigning it to WBS Elements

    Hi all,
    I have a question regarding creation of documents.
    I am using T-code CV01N.....
    How to create the document and how to assign it to a WBS Element?
    Do we have any BAPIs or FM available for this?
    Thanks in advance....

    Hi Raj,
    Documents can be created/checkin  from WBS/activity without going to CV01N. For this, you need to have the DMS configured.
    Another way, Create document using transaction CV01N and attach manually in WBS/activity from Project Builder.
    Srinivasan Desingh

  • Issue on distribution of quantity to WBS elements in invoice

    Hi SAP Gurus,
    I have an issue with the distribution of quantity to WBS elemements in SAP.
    There is a purchase order with 6 line items. For the first line item a quantity of 3 is ordered and the same quantity of 3 is assigned to 7 WBS elements in the account assignment tab. There were 3 invoices created for this line item. For a particular WBS element a quantity of 1.050 was assigned and when we drilled down through the 3 invoices we found only a quantity of 1.028 is assigned to this Particular WBS element. Can someone please tell me as to why this mismatch has happened.
    Thanks in advance

    Hi Raman,
    I am sorry but this is not the case . There are 7 WBS elements used for this PO. The quantity is distributed to 7 wbs elements as follows.
                                          Percentage                    Quantity
    1st WBS element-                 8.7                             0.261
    2nd WBS element                 17.4                            0.522
    3rd WBS element                  18.2                            0.546
    4th WBS element                  8.8                             0.264
    5th WBS element                   6.4                             0.192
    6th WBS element                   5.5                             0.165
    7th WBS element                   35                              1.050
    This is the assigned structure in the PO for all the 7 WBS elements. But when you look into the 3 invoices a quantity of 1.028 has been distributed to 7th WBS element and a quantity of 0.214 has been assigned to 5th WBS element which is causing the mismatch
    Also in the 2nd and 3rd invoices only 6 wbs elements are used. Can you please tell me as to why there is a WBS element missing in the 2nd and 3rd invoices if the splitting is happening automatically.
    Regards,
    Dwarik

  • Problem while assigning service activity to WBS

    when i assign service activity to WBS element without filling any fields (like Purchase groupand Material group) it is going straight to Service Specifications.
    if we fill the service specifications and save the project we can save the project with out any errors
    i require entry of PurchaseGroup and Material Group is mandatory
    and then system should go to Service specifications
    Please advice

    Hi,
    Just check in Network profile, on Activity tab (TC: OPUU). You must have maintained required details like Material group, Purchasing group etc in Service activity section. Whenever you create a service activity these values get defaulted in activty. Let me know if it solves your problem.
    Reward points if helpful.
    Regards
    Message was edited by:
            Shrikant Rakate

  • We want to post actual cost through statistical WBS elements.

    when we do the posting on Costcenter assigned to a Statistical WBS element (2nd level), I was in the opinion that, the actual cost posted on the Costcenter of statistical WBS (2nd level) will reflect to the top WBS element (which is non-statistical in 1st level).
    But, I cannot able to see the actual cost in the 1st level WBS which also a Billing element (with this, finally we want to  do the Resource Related Billing).
    So expalin me how to bring actual cost posted on the costcenter of a Statistical WBS, to top WBS element which is non-statistical.

    U can book the actual cost from Procurement Cycle or by direct Invoice posting using FI transaction.
    Procurement Cycle:
    When you create PR or PO user Account Assignment Q or P and maintain WBS element. When u do GR or service entry actual cost is captured on the Project (WBS element).
    Using FI Transaction:
    When there is no PO and to book the cost u can use  F-43  to post actual cost (via Invoice) and mention WBS element.
    U can check the Actual Cost using Line item report CJI3 or S_ALR_87013532.
    Venkat

  • Depreciation to WBS Element

    hai,
    Is it possible to post depreciation to WBS element. And also i want to know, whether it is possible to assign the asset to WBS element in time dependent tab in AS01.
    Can any one guide me on this.
    govind.

    Hello
    Yes this is possible as of release 4.7. Note 684659  - FAQs about account assignment objects as of Release 4.7 -  will provide you with all the detailed information.
    Regards
    Javier

  • Material no link with WBS element

    Hello Expert,
    Any chance that this requirement can be set up? I tried to check config but nothing shows to achieve this.
    Objective is that when user select material no during PR creation,  the respective wbs will be defaulted as well during PR creation.
    Thanks in advance.
    Rgds,

    Hi,
    I think there is no stander way for same,
    can you check from PS side,
    I think In PS we can assign Material code to WBS element,that thing may help you,please check from PS consultant
    Regards
    Kailas Ugale

  • Invoice posting error with WBS element

    I have created purchase order with account assignment category P with WBS element. Quantity 2 numbers and unit price 10000Rs. I checked WBS element in this u201CAVAC Availability control activeu201D check box is selected. Now I am trying to post invoice for this PO with amount 25000Rs with tax amount 1200Rs but getting an error saying u201Cavailability controlu201D cannot post invoice.  Help me in this regard
    GP

    Hi,
    It would be a great help if you would send the error code from the error message.
    Kind Regards,
    Arminda Jack

  • Derivation of Cost Center from WBS element MAster data at the time of invc.

    dear all,
    during invoice postings with wbs element account assignment system do not derive assigned cost center from wbs element master data.
    how can the system derive the cost center automatically??
    Is there any BADI available to this issue.
    regards
    saqib

    Dear,
    WBS is Real and cost center in the master data is for statistical postings i.e. responsible cost center in WBS.
    How to make substitution (OKC9) deriving the cost center in document line items / invoice posting etc.
    Kindly give detail process for its configuration steps and is there any BADI available which can be useful in this regards?
    Regards,
    Saqib Usman

  • Maintaining Budgets for WBS element.

    Hi all,
    My operating concern currency is USD while my company code currency is CAD.
    When I am assigning budgets t my WBS element using tcode CJ30, it displaying the currency as USD. However, I want it to be displayed as CAD.
    What needs to be done for this?

    Hi,
    You can enter the budget either in controlling area currency, object currency or transaction currency. You can define your WBS to be managed in CAD, and set the profile to object currency (OPS9), for example.
    Regards,
    Eli

  • Functional Area for WBS Element

    Hi Friends
    While posting Invoices in SRM 7.0 for WBS elements the Functional Area is sometimes picked up from WBS element directly and sometimes from Responsible Cost Center of the WBS.
    Also in cases when we have split account assignment with CC and WBS elements then many times only the COST Center Functional Area is passed for all the account assignment split.
    E.G. we have 1 line item with 10000 value and Account Assignment is split in 4 parts 1 CC and 3 WBS element. For this functional are of the Cost Center is passed for all four account assignments rather than passing 4 different functional areas based on each cost element.
    Can someone help me understand how the standard functionality works or is there any specific condition in which the responsible cost center Functional Area is picked up instead of WBS element Functional Area.
    There are some documents where in case of split accounts system is passing separate functional area for each account assignment. So i am not able to conclude what is the standard function to determine Functional Area.
    Regards
    Ushir

    Hi Akash,
    The scenario you mentioned is correct it will pick up the CC functional area in case there is no functional are on WBS but in our case that is not the case. For all the WBS we have the functional area maintained but still some times the functional area is picked up from responsible cost center of the WBS.
    The problem is we are not able to replicate this in Q or D environment. The documents posted by users in production are pointing to some wrong Functional Area and its not correct.
    Regards
    Ushir

Maybe you are looking for

  • Hi i need help in report painter

    Hi   In Report painter how to enable the option to check the set/hierarchy node option in ‘general data selection’. it always displays in disabled mode. how can we do it?   really i need to add one field in special purpose ledger , business area from

  • OInvoice Business Object XML Schema question

    I am trying to produce an xml file based on the oInvoices business object to use in an EDI translation.  I am running Sap Business One 2005 A SP:01 PL:03.  I used one of the sample programs in the SDK Samples folder to produce an XML schema of the oI

  • Change manually the defaulted Tax code in PO

    Hello! I would like to know if it is possible to change manually the tax code in the PO item defulted from the PIR. Currently the field is display only. I checked the screen layout definition but I didnt find the Tax code field there. Thank you very

  • Appointment - End Date/Time to be default sames as Start Date/Time

    When a sales rep chooses a "start date/time" to schedule an appointment in CRM, can the "end date/time" be updated as same as "start date/time"? E.g. Select Start Time: 4/5/2010 10:00AM, then the End Time: 4/5/2010 11:00AM should default to the selec

  • Output module to bridge cc

    hi ive installed the output mode to bridge cc and can see it but it wont work ??