Automatic Material Issue on Activity Confirmation

Dear All,
I am trying to setup the system so that on internal activity confirmation material assigned to the activity is automatically Issued to the WBS.
Issue:
BS, but when i confirm the activity system does not issue the material automatically when stock is available as unrestricted stock in the correspondign WBS.
When there is stock available in the Storage location mentioned in CJ20N for the material automatic GI happens on activity confirmation.
Can you please let me know why is system not issuing the material available as unrestricted stock on the corresponding WBS??
Warm Regards,
Jatinder

Dear Gokul, Srikant,
Fine i can use CN25 for confirmation.
Requirement is that i want to track stock on WBS level, and then issue it to Network/Activity from WBS stock? is this not possible via activity confirmation??
Is it that if i want to automatically post GI on activity confirmation, it is not possible from Project/WBS stock?
Warm Regards,
Jatinder

Similar Messages

  • Batch wise actual material consumption and activity cost

    hi
    my client is steel industry, client requirement is heat wise actual material and machine cost. Heat is a batch number, how i can check batch wise actual material consumption and machine cost.
    regards
    imdad

    Hi Imdad
    Whats the batch definition in your case?? have you designed One batch per Prod order or One batch per GR?
    If its one batch per Prod order - you can directly see the prod order.. however, chances are less for this as Steel company might be using PCC i.e. repetitive mfg
    If its one batch per GR - Then you will have to track using the Confirmation no because each Confirmation will trigger the Goods Issue and Activity Confirmations...
    Using Table AFRU - You can track the individual Confirmation no and also the Activity Qty confirmed....COSS / COSSD will have the Activity Cost
    If any goods mvt are posted during the Confirmation, you would see a Mat Doc No populated in the field "Mat Doc"
    Br, Ajay M

  • Automatic goods issue when the activity is confirmed not happening

    Dear all,
    I am facing one issue. I have attached a backflush item to the activity. The stock is also available for that material. But when i do the activity confirmation that material is not getting issued automatically.
    Can anybody tell me what could be the reason.
    Regards,
    Sudhir Kesarkar

    Thanks jibat,
    As you suhggested i have checked in cogi. The error appearing there is 'Maintain valuation type'. This occured because the material is split valuated and we have to maintain the valuation type. But is there any way to automatically flow valuation type to the material attached to the activity.
    Regards,
    Sudhir

  • Automatic goods issue for outbound delivery, during the transfer order confirmation

    Hello,
    Could you please advise how to realize automatic goods issue for outbound delivery, during the transfer order confirmation in the WMS.
    Now after creation of outbound delivery, i can't post the goods issue. Before i have to make the transfer order and confrim it and only after this i can post the goods issue in the VL02 t-code.
    Could you please advise - what i have to customize that to make automatic GI for outb. delivery (i mean with creation material document) during the TO confrimation.
    Thanks in advance.

    Hi Iiya
    Check the below setting, might be helpful

  • Activity confirmation issue

    Dear Gurus,
    We are facing issue in confirmation of Activity such as power , steam. As in process industry output is variable.
    accordingly at the time of confirmation activity viz power , steam should varies is it possible?
    In transaction cor6 we can enter manually units actually consumed.
    My second query is
    In T-code CORK and COID  How to / where to enter actually consumed unit of Power and steam in screen? As users  are using all the 3 T-code for confirmation.
    Please guide me as we are facing cost variance in Process order confirmation due to activity.
    Regards,
    J.H.Pert

    COID is just reporting transaction.
    COR6N is single screen entry transaction
    CORK is header confirmation
    When you do confirmation using CORK, all the confirmable phases in the order gets confirmed to the yield qty mentioned in the screen, this also take care of activity confirmation.No option to post activity seperately.
    cor6 you can post actual activities seperately

  • Automatic goods issue of components upon creation of Production Order

    Hello gurus.
    The business would like to have the components in a Production Order automatically issued (with Movement Type 261) upon the creation of a Production Order.
    I was investigating this possibility under the Production Scheduling Profile option in IMG, but there is no automatic action for this.
    Do you know of another way this could be achieved? I'd like to do this preferably without having to implement User Exits or Batch Jobs.

    Fernando,
    Automatic goods issue is not possible.
    But you can certainly think of backflushing the components while confirming the order with CO15 or CO11N.
    Make the required settings in material master, work center or routing. It will get copied to the order.
    The same can be maintained in the order too.
    There is one more option available in 'Define confirmation parameters' T code OPK4.
    Execute the above T code.
    In 'Generally valid settings', mark 'All components' under 'Goods moveemnt'.
    Also in 'General individual entry'  under 'Error handlings/ logs' mark ''Goods movement'  & if required mark 'Termination for incorrect goods movement' so that if any problem arises with the GI/ GR, the termination would be terminated.
    Hope this helps you.
    SmanS

  • Material Issue to Shopfloor

    Hi Expert,
    The scenario is, in the begining of the month production personnel takes the material from central store to shopfloor storage location & consume in different different process orders. If required he repeat the same activity during the month.
    To get the material from the central store, production guys provide them a reservation slip. Which movement type should be use at the time of creation of reservation? should we use movt type 201 or 311? what is the complete process flow for creating reservation to consumption?
    In my case Exicse register will update through Movt type 261.
    Thanx in advance....
    Regards,
    neha

    Hi experts,I have one clarification, recently SAP implemented in my company.
    I have raise the process order in COR1 – consumption based bill of material qty automatically assign in if backflushing is active in mvnt.type : 261. So
    1.what is the way of material issue against the process order to store person?
    2.If it damaged ( scrap )for any packing material during process what is the way of return the items? 
    3.If I need excess packing material in the same process order what is the way followed for production and store person?

  • Progress Analysis, Plan/actual % comparision based on activity confirmation

    hello guyz,
    I have to monitor the project progress based on activtiy confirmation, can anyone guide how can i see progress of project based on percentage with plan/actual dates comparison.
    The business scenario is:
    One top level WBS under which 2 WBS assign, each 2nd level WBS have one network assigned. The  second level WBSE represent individual site where i have to perform various internal activities without cost involvements, only dates and number of durations to be maintained in each internal activity with finish start relationship.
    The structure is:
    Root WBS (level 1)--SITE 1 WBS (level 2)--
    SITE 2 WBS (level 2)
    > (Network 001) -
    > (Network 002)----
    > 001 0010 (1st Internal activity 2 days) -
    > 002 0010 (1st Internal activity 2 days)-
    > 001 0010 (2nd Internal activity 4 days) -
    > 002 0010 (2nd Internal activity 4 days)-
    > 001 0010 (3rd Internal activity 1 days) -
    > 002 0010 (3rd Internal activity 1 days)-
    > 001 0010 (4th Internal activity 3 days) -
    > 002 0010 (4th Internal activity 3 days)-
    In the above project structure i have entered the start planed dates for each network / site. The system automatically calculate the planned end dates after scheduling.
    In execution phase, i have also maintained actual dates on activity confirmation only.
    Now i need assistance to see the project progress for each network site.
    Regards
    Saqib Usman

    the problum is still there kindly provide assistance...
    I have to monitor the project progress based on activtiy confirmation, can anyone guide how can i see progress of project based on percentage with plan/actual dates comparison.
    The business scenario is:
    One top level WBS under which 2 WBS assign, each 2nd level WBS have one network assigned. The second level WBSE represent individual site where i have to perform various internal activities without cost involvements, only dates and number of durations to be maintained in each internal activity with finish start relationship.
    The structure is:
    Root WBS (level 1)--SITE 1 WBS (level 2)--
    SITE 2 WBS (level 2)
    > (Network 001) -
    > (Network 002)----
    > 001 0010 (1st Internal activity 2 days) -
    > 002 0010 (1st Internal activity 2 days)-
    > 001 0010 (2nd Internal activity 4 days) -
    > 002 0010 (2nd Internal activity 4 days)-
    > 001 0010 (3rd Internal activity 1 days) -
    > 002 0010 (3rd Internal activity 1 days)-
    > 001 0010 (4th Internal activity 3 days) -
    > 002 0010 (4th Internal activity 3 days)-
    In the above project structure i have entered the start planed dates for each network / site. The system automatically calculate the planned end dates after scheduling.
    In execution phase, i have also maintained actual dates on activity confirmation only.
    Now i need assistance to see the project progress for each network site.
    Regards
    Saqib Usman

  • Line item issue in order confirmation

    Hi folks..!!!
      i have an issue regarding order confirmation. while i am trying to display a sale order that line item quantity and somo more data's are printing in second line. i need those data's has to be print in same line in line i.e  item , material and material description displaying row...
    while in layout they done for item, material , material desc are in one TEXT element i.e ITEM_LINE and Quantity and some more fields  are in other TEXT element i.e ITEM_LINE_PRICE_QUANTITY, i think becoz of this quantity is display in second line.. could you plz solve this issue..
    ITEM     MATERIAL     QTY      DESCRIPTION   PRICE....
    10           ABC                           DEMO       
                                    10PC                                 2113
    i need output like this...
    ITEM     MATERIAL     QTY      DESCRIPTION   PRICE....
    10           ABC             10PC          DEMO         2133

    hi ,
    u r using script or form ?
    if u r using script ...
    in tag column put "=" ... so it will cont with the prev line...
    in case u r using smartforms ... keep all the values in single text element ...
    is there any problem in putting them in single column ?

  • Tolerence limit for Goods issue while CO11N Confirmation

    Hi,
    We are creating the production order which continues for 1 to 5 days, and partial confirmation is done for the order e,g production order 100, partial confirmation 5,10,20 etc.
    Now while order confirmation, we do the goods movement by which raw material issue against order, but some material issue in different units, like cement issue in BAG, KG etc, due to this at final partial confirmation some times system is issuing the message goods movement failed and in transaction 'COGI' it is showing the error as 'RE Reserved quant. exceeded by 0.010 TO : 40007510 XXXX XXXX XXXX004002'  is there any option for this to allow some excess quanity by providng the tolerence limit, or is there any badi or user exit for this to rounding  the values at the time of final issue.
    Regards,
    Zafar 

    Hi Zafar,
    You can define underdelivery/overdelivery tolerance in Work scheduling view for the material master.
    Added to that, you can define if the tolerance is checked in order confirmation parameter (OPK4 ).
    Thanks and regards,
    Suraj Kamble

  • Material Issue to cost center which are not allocated to ML

    Dear Experts,
    We have a senario, Material issue to the cost center and through activity type the cost updated in production order, Client wants when reu  CKMLCP the same should  be updated in ML, and also revaluate actual activity price and updated in cost center.
    Please help to solve the issue.
    Thank you

    Hi Nuki
    I hope this material is not price control = 3/S (standard) and also the cost center is not productive type.
    If you consume material with standard price to production cost center it will start a looping in activity calculation and at month end there will balance in this cost center.
    Well I hope I helped you.
    Regards

  • Material issued towards vendor

    Hi
    1.Stores material issued towards vendor which can be deducted from his invoice.
    2.Vendor involves in a activity/work
           Eg. Construction
    3. Cement bag cost should be bare by vendor, but he avails it from stores, which can be settled against his bill
    Question
    1.How to capture the goods issue in MIGO to control the vendor invoice.
    Note : Vendor is one time.
    Please guide.
    Regards
    Sr

    It not clear ? Why u give mat to venmdor . Iis it Subcontracting Process .If not proceed as follows
    U need to create the vendor as a customer , Do delivery and PGI, Bill the customer , and when customet gives the amout , clear the customer .
    OR
    1.Stores material issued towards vendor which can be deducted from his invoice.( CREATE SEPERATE CR MEMO FOR THE SAME - INVOIVE POST AND CREATE CR MEMO)
    2.Vendor involves in a activity/work
    Eg. Construction
    3. Cement bag cost should be bare by vendor, but he avails it from stores, which can be settled against his bill
    Question
    1.How to capture the goods issue in MIGO to control the vendor invoice.(CREATE RETURN PO - ITEM TICKED RETURN, DO MIGO -161 MVT TYPE , cr memo)
    Note : Vendor is one time.
    Please guide.
    Regards
    Sr
    rewdzzz

  • Activity confirmation concept

    Dears
    Can you any body explain me the concept behind the activity confirmation in QM
    My understanding i  am sharing here i request some expert review on this
    1. The purpose of activity confirmation is for record quality cost
    2. If we have two different task to do a inspection for a material (1-Inspection by machine, 2-labor for cleaning after inspections) so we need to define two activity by the T code:KL01
    3. After defining activity price planing by t Code: KP26 (For the above created activity for one hour how amount is required)
    4.Now when RR is happening we have to do the activity confirmation(for example 1-Inspection by machine how may hour we utilize to make inspection,2-labor for cleaning how many hour we utilize this activity also to finish the inspection)
    5.Now QM cost report will give you for activity one  how many cost incurred so far ,and also for the second activity also
    Pls correct me if my concept is wrong
    Thanks in advance
    Faisal

    Hi expert
    any advice on this will be highly greatfull
    Faisal

  • Picking List / Material issue slip

    Kindly let me know the process of printing a Picking list / Issue Slip for a material issue from a DBM Service order.

    Dear Babudhar,
    There are no standard actions delivered to print any picking lists along with DBM 6.0.
    An event call be built in (to print the list) which could be linked to Confirm event as a subsequent event. So, as soon as the order if confirmed, the new event can print the list for you.
    Hope this info helps.
    Best regards,
    Harsha

  • Activity Confirmation

    Hello all,
    Scenario is- A FERT material assigned in the project which creates WBS reservation. FG is produced by production order and then delivered from Project stock.
    Before delivery of the FERT, I want to check the activity confirmation to which FERT is assigned.
    I have a WBS number as an input to call the BAPI, in the user exit for deivery @ save.
    Which BAPI shall I call in to check the activity and reservation stauts for perticular WBS? and which FM will be useful to perform the confirmation of perticular activity?
    Please reply..
    Thanks and Regards

    Hi,
    Make use of the folowing BAPIs 
    1) BAPI_PROJECT_GETINFO - get all the activities for the mentioned WBS.
    2) BAPI_BUS2002_GET_STATUS - get the status of required activity. Not sure how to derive the activity to which the component is assigned out of the all activities for WBS.
    3) BAPI_NETWORK_CONF_ADD - to confirm the activity.
    Regards
    Sejo