Progress Analysis, Plan/actual % comparision based on activity confirmation

hello guyz,
I have to monitor the project progress based on activtiy confirmation, can anyone guide how can i see progress of project based on percentage with plan/actual dates comparison.
The business scenario is:
One top level WBS under which 2 WBS assign, each 2nd level WBS have one network assigned. The  second level WBSE represent individual site where i have to perform various internal activities without cost involvements, only dates and number of durations to be maintained in each internal activity with finish start relationship.
The structure is:
Root WBS (level 1)--SITE 1 WBS (level 2)--
SITE 2 WBS (level 2)
> (Network 001) -
> (Network 002)----
> 001 0010 (1st Internal activity 2 days) -
> 002 0010 (1st Internal activity 2 days)-
> 001 0010 (2nd Internal activity 4 days) -
> 002 0010 (2nd Internal activity 4 days)-
> 001 0010 (3rd Internal activity 1 days) -
> 002 0010 (3rd Internal activity 1 days)-
> 001 0010 (4th Internal activity 3 days) -
> 002 0010 (4th Internal activity 3 days)-
In the above project structure i have entered the start planed dates for each network / site. The system automatically calculate the planned end dates after scheduling.
In execution phase, i have also maintained actual dates on activity confirmation only.
Now i need assistance to see the project progress for each network site.
Regards
Saqib Usman

the problum is still there kindly provide assistance...
I have to monitor the project progress based on activtiy confirmation, can anyone guide how can i see progress of project based on percentage with plan/actual dates comparison.
The business scenario is:
One top level WBS under which 2 WBS assign, each 2nd level WBS have one network assigned. The second level WBSE represent individual site where i have to perform various internal activities without cost involvements, only dates and number of durations to be maintained in each internal activity with finish start relationship.
The structure is:
Root WBS (level 1)--SITE 1 WBS (level 2)--
SITE 2 WBS (level 2)
> (Network 001) -
> (Network 002)----
> 001 0010 (1st Internal activity 2 days) -
> 002 0010 (1st Internal activity 2 days)-
> 001 0010 (2nd Internal activity 4 days) -
> 002 0010 (2nd Internal activity 4 days)-
> 001 0010 (3rd Internal activity 1 days) -
> 002 0010 (3rd Internal activity 1 days)-
> 001 0010 (4th Internal activity 3 days) -
> 002 0010 (4th Internal activity 3 days)-
In the above project structure i have entered the start planed dates for each network / site. The system automatically calculate the planned end dates after scheduling.
In execution phase, i have also maintained actual dates on activity confirmation only.
Now i need assistance to see the project progress for each network site.
Regards
Saqib Usman

Similar Messages

  • Problem while running the Profit center Plan/Actual Report in Background

    Hi
    While executing the T.Code s_alr_87009722 (Profit Centre plan/Actual Comparision Report) on fourground it is giving all the profit centers/groups in the particular profit center group. But when i run the same report in back ground mode it is picking only the last profit center in that group. Please help me regarding the same.
    Regards
    Surya

    hi prakash ramu,
    even it is not working. it is directly talking me to spool request..
    i think it is not possible, while ur running the report in background.,
    any how if possible could u pls send me the code...
    thanks
    ramu

  • Request Got Deleted From 0PP_C01(Planned/Actual Comparison Order/Material)

    Hi experts,
    I am a newbie in the BW area.
    We have 0PP_C01(Planned/Actual Comparison Order/Material View) , 0PP_C03(Plan/Actual Comparison Operation/Work Center View) and 0PP_C05(Plan/Actual Comparison Material Consumption) activated in our production system.
    Few days before one data error happened during data load and accidentially, that particular request got deleted from the system.
    When we tried to load data again, it is not allowing since the request is missing and the update mode is delta update.
    Can any one guide me to retrieve the data back to the system??
    Thanks alot in advance
    Shobin

    Hi,
    You can try using PSA if that request it's still there.
    Otherwise, you will need to regenerate that request in source system (by filling setup tables with parameters) and update BW with a full load.
    Hope this helps.
    Regards,
    Diego

  • Commitments at activity level in report S_ALR_87013533 - Plan/Actual/Commit

    Hi All,
    When i executed the report S_ALR_87013533 - Plan/Actual/Commitment/Rem.Plan/Assigned, the commitments are shown at WBS level but not at activity level. Is there any setting required to see the commitments at the activity level?
    Where as the planned costs are shown against the activity in the same report.
    Please suggest the required settings if any?
    Regards,
    Ramana.

    HI Rifaee/Martina,
    In CJI5 the line items are shown under the WBS. But i would like to see the line items in the report.
    Even after running the report cjen the database is not updated for line itemwise commitment in the report.
    How to assign the PR/PO as account assignments to activity? Where do i need to do this setting? Please inform.
    Regards,
    Ramana

  • Cost Analysis: Planned Vs Actual Cost Variance for cost

    Hai
    Which is the standard cube for "Cost Analysis: Planned Vs Actual Cost Variance for cost"?
    Because i need these fields
    Cost Element
    Actual Cost
    Plan cost
    Debit Posting
    Credit Posting
    Controlling Area
    Cost Centre

    Hi nvr,
    Cost Element : Cost Element nothing but a which product your spending
    Actual Cost : How much amount your spend on particular product
    Plan cost : How much amount you need to spend on particular product
    Debit Posting : In Accounting they are doing one positng that is depend on Debit and Credit.
    Credit Posting:
    For Exp: your parchase one product RS.500/-
    In FI they are posted like this.
    Product Name DR.(Debit) 500
    to Cash                                      500 (Credit)
    here product name is debit posting
    cash is credit posting.
    Controlling Area : Which area your spending the money
    For Exp: You have Man.Company your doing some processes which process that cost is spend nothing but a Controlling Area.
    Cost Centre : cost Centre nothing but which process.
    Hope its' helps .
    Thanks and Regards,
    Venkat.

  • Planning Actual Monthly for activity input

    Hi All,
    can we make planning or actual by monthly using activity input? Should i use tcode CJ40 or CJR2 ? Please guide me in detail .
    Cheers,
    Nies

    Hi Pratap,
    I already choose CJR2 ...put WBS and CE ...i put in August...when i save it ...why the system distribute to other months and the distribution key default to 2...even in SPRO i create new profile and change the distribution key to 0...it always default to 2...
    I would like to do only for August..dont want to distribute to other months...
    what should i do?
    Cheers,
    nies

  • Estimation method of progress Analysis

    Hi,
    We are having following scenario.
    We are creating the project in PS. Then creating the PM order & assigning
    the order to WBS element.
    We want to use the Estimation method of progress analysis. Hence we havedefined Estimation method as default measurement method (both plan &
    actual )for following objects,
    1. WBS element
    2. Internal processed activity
    3. External processed activity
    4. General cost activity
    5. Order (Other than Network)
    For WBS element & all activities we are able to manually maintain planned
    POC & actual POC in CJ20n.
    But for PM order we are not able to manually maintain planned POC &
    Actual POC.
    Can you please let me know where we can manually maintain the planned &
    actual POC for PM Order.
    regards,
    Pradip Shelke

    /@#$%%%%@ wrote:
    > Can you please let me know where we can manually maintain the planned &
    > actual POC for PM Order.
    I do not think it is possible for order to use estimation method..
    Please go for Cost / Time / Work proportional

  • Comparing Progress analysis data saved in past periods

    Hi forum team,
    We are using PS in SAP R3 ECC 6.0 system
    With the intention to reviwe at later stage, we had saved 'Progress
    Analysis' report data (CNSE5)in 'Other selected version' in past periods
    i.e.in July, August etc.When we open these reports in November all its
    fields (Adj/Nonadj/Agg/Non Agg/PlanPOC/ActualPOC....) except actual
    cost shows current period (November) values.
    We thought this version copy would be a sort of screen shot but now it appears as a dynamic report.
    How can we save this report (cnse5) in ERP database as we save project version for comparision in future?
    Please suggest.
    Thanks,
    Mohan Parab

    Hi
    The standard method is KKA8. But you need to reverse the settlement.
    Or you should be able to delete  the data from RPSCO with Value type 32.
    But once you delete, you will be running the RA again for the last 10 Years? If so will you be settling it again? In that case how do you reconcile this with FI-CO and PA?
    Thanks
    psconsultant

  • How to view the results of progress analysis

    Dear Experts,
    I executed progress analysis for my project analysis in CNE1 for my project.
    After execution, PA has been completed for two WBS elements. But iam not able to see any POC values or costs.
    Where should I check and confirm that Progress analysis has been carried out successfully.
    Pls suggest.

    Hi,
    Run the transactio CNE5 for the project progress analysis ,you will get the following reports.
    The standard reports offer various values we can use to assess the progress of our project. The following fields are defined in the standard progress analysis reports:
    - Planned POC in percent
    - Actual POC in percent
    - Budget Cost of Work Schedule, BCWS
    - Budget Cost of Work Performed, BCWP
    - Cost variance (CV)
    - Schedule variance (SV)
    - Value index (CPI)
    - Estimated costs at completion (EAC)
    Regards,
    Raj

  • PS Progress Analysis -

    Dear Guru's,
    I am facing problem while executing the Progress Analysis report in SAP PS for one of our client. I am getting only the Schedule plan value and actual... rest of the column like BCWS, ACWS are comming blank which is important for client.
    If any body work on customer project pls suggest..
    Regards,
    Rupesh Kumar Singh

    Hi Shashank,
    Right now I'm facing the same problem, I've already implement the user exit but I would like to know if you have an example of the implementation, I still don't know where to find the info of the structures to calculate the POC.
    Thanks,
    Héctor

  • Progress analysis scenario

    Can some one help me with a sample scnario for Progress Analysis which can help in understanding what events will lead to Cost Variance or schedule Variance and will give me EAC, ETC etc.
    I have all the settings done for progress analysis, but I am getting same values for BCWP & ACWP.
    Also, how is Plan POC related to schedule/duration/period of the activity?
    Regards,
    VDS

    Dear Rupesh,
    please have a look at the SAP online documentation following this link:
    http://help.sap.com/saphelp_erp60/helpdata/en/b4/ba853488601e33e10000009b38f83b/frameset.htm
    Project Progress -> Progress Analysis:
    There you can find a list with the relevant KPI's, formulas and questions they will help to answer.
    Project Progress -> Progress Analysis Progress:
    There you can find a short scenario with a diagramm which explains the cost variance and schedule variance.
    The relation of the POC calculation to values like schedule/duration/period is depending on the measurement method which is used, as every measurement method uses different values as basis for the calculation. So a general answer can't be given on that.
    Kind regards,
    Dirk

  • S_ALR_87013340-PRCtr Group:plan/Actual Caomparison Report performance issue

    I'm trying to get the "actual line item" details from the S_ALR_87013340-PRCtr Group:plan/Actual Caomparison Report and I get a
    ABAP run time error. I tried to running for just one month and on several accts. please help to me. how to get the report.
    or how to improve the performance of this program.
    Thanks in Advance

    hi,
      first we need to know what part of the code is taking time. Do run time analysis using SE30 transaction to know what part of coding is taking more time. use can ST12 transaction to get more detailed analysis.
    Since this is standard SAP report also check any OSS note exist for the performance problem.

  • Report Plan/Actual IW33

    Hi all.
    In transaction IW33, Costs tab, report Plan/Actual, I need to add a field in layout. This field is 'Operation/Activity Number' (VORNR) which isn't possible select in ALV layout. Please, does somebody know how I can add this field?
    Thanks a lot.
    Marta.

    Marta;
    T-code standard that is impossible. Or you check in transaction reports (Logistics -> Plant Maintenance -> System Information -> Report Selection) or make a query.
    Regards.
    Luciano Nobrega

  • CATS INTEGRATION WITH PP AND PM MODULE ( TO FIND ACTUAL MANPOWER COSTING THROUGH ACTIVITY TYPE)

    Hi Experts,
    We have a scenario like, Client wants to track the actual manpower costing through activity type ( Ex: How much hours an employee worked on a particular work center to produce an “X” product, So that his actual cost should be loaded on that product.
    We have employee ( 1. Staff 2. Worker 3. Contract labor employee and apprentice from third party roll and staff and worker we plan to go with negative time management and for contract labor and apprentice will go with through cats.
    Since we are not going to run the payroll for contract labor employee and apprentice, we just maintaining the employee data as a group ( Ex: Group A,B,C etc.. Each group consists 20 or 30 employees, According to system each group as one employee and according to us each group consists as 20 or 30 employee.
    The Activity type as well cost center will be created by Co module, the same will be assigned in info type 0315, but still i want more input from experts on the same, since i am new to cross application time sheet configuration, could any one help me out to find the actual manpower costing in a better way.
    Regards,
    Prem

    Hi Experts,
    Can any one please reply on the same.
    How to arrive the exact manpower costing through activity type ?..
    Regards,
    Prem

  • How to avoid actual cost error log while confirm production order activity

    Hi
    I dont want to post actual activity cost via production order activity confirmation. But i want standard value keys for my production duration purpose. So,i defined activites(strd value key) in work center without assigning cost center to that work center. While i confirm in CO11N, system throws erro log as Actual cost calculation contain errors and allows me to confirm the activities. I am doing MB31 and all CO settlement activities also. But when i try to close the order it says error log exists,so closing of order is not possible. How to overcome this problem as i dont want to capture any cost of activites via production order,but i want confirmation only for production analysis.

    Hi
    Issue is resolved thru PP forum. Thanks for ur reply.
    Solution lies in Control key of routing and BOM costing relevancy.

Maybe you are looking for

  • How to hide custom fields in Shopping cart depening on user role

    Hi, We have some custom fields in shopping cart for basic view. Every thing works fine. Now client is asking to hide all the custom fields based on user role. I found some function module to fund roles. now my main problem is unable to find the cusot

  • XML data contains linebreaks in the tags - won't work with Flash

    Hello. I have a Flash file that draws upon an xml file for content. When I try to create that xml file using an Adobe Designer 7.0 pdf form, I get line breaks in the tags. You don't see them in Internet Explorer XML viewer but you do see them in Note

  • Date Parsing

    Hi, I have a string in mm/dd/yyyyy format. I want to convert this string in yyyy-mm-dd format. I am using simpledateformat to convert it into a Date object. It gives me "Thu Jan 26 00:00:00 EST 2006" this object. When i parse it again using SimpleDat

  • Program to create Bank Statement

    Hi There is a program to create Bank statement, so that it can be used for Electronic Bank statement processiong FEBA... I am not able to recollect that program. Can any help me in this regard. Points assured Kalyan

  • How to configure FTP in Process Flow

    I'm having troubles configuring an FTP activity in my process flow. Any clue how that should be done? The documentation does not tell that much. I added the following to my parameter list in "Activity Panel" /${Working.Host}=100.1.15.236/${Working.Us