Hi All
What is the significance of availability check field at schedule line level and requirement type level.
If I remove the check box at schedule line level, then there won't be any availability check carried out in the sales order, even though in requirement class it is checked. Is it for doing availability once the requirement is passed to MRP...
In make to stock scenario, no availability check is active at schedule line level.
scenario 1. stock is 0 in plant, when i place an order for 10 quantity, does system give any confirmed quantity on so and so date...or the confirmed quantity will be zero or as there is no availability check carried out, it confirms 10 quantity on customer requested delivery date and the time of creation of delivery, it gives an error message stating zero quantity is available. which one is correct in all the above.
In make to order scenario, no availability check is active at schedule line level.
order was created for 10 qty, as there is no availability check active, does the system give some date based on the lead times maintained in the material master or not?
Regards
Sree

Hi sreekar
The significance of availability check at schedule line level  is to determine weather availability check and TOR should be carried out for sales orders  or not. 
If you remove check box at schedule line level , availability check and TOR wont be  carried out at sales order level.
Coming to the scenario you said , make to stock , i think the availability check you are using is 01 make it 02. which is planned requirements. and stratergy group as 10. in MRP3 view in MMR. .
as the availability check u have put 01 & stratergy group as 10 availability check doesnt carry
coming to the scenario 2  , if the stock is 0 in plant and if you create a sales order, then the confirmed quantity should be 0 and that particular order will go to backorder processing.
sometimes it  confirms the ordered quantity as the  confirmed qunatity, and it gives a confiremed delivery date on which the stock is confirmed , but that date is a tentative date.
all these unconfirmed orders will go to backorders. once the qunatity is confirmed automatically , delivery date also will be done
Coming to scenario 3 , when you create MTO order there will be availability check checked at the schedule line level. can you tell wat is the schedule line you are getting is it CP or ND?
for schedule lines , ND - no availability check will be there , PD - availability check will be there
Note: plz check 1st the availability check you have entered in MMR , if it  is 01 make it as 02. and then run these cycles.
Reward points if useful and if Any queries let me know
Regards
Srinath
Edited by: sri nath on Mar 21, 2008 7:53 PM

Similar Messages

  • Multiple schedule lines as and whhen mat is available

    Dear Friends I have a requirement where in I want schedule line to be genrated in sales order for one item as and when qty is avaliable and we run an avail check
    for ex
    There is a need for 20 bags 10 is available   after a few days so 2 schedule lines one stating del not possible n req del date and 2nd stating stating when its available the remaining 20 is ava 30 days from now .........so when its available i want that schedule line seperately ...........how do i get the third schedule line
    Right now even if 10 is avalibale it gives me 1 schedule line stating 20  20  0 (confirmed qty)
    Please let m eknw how i could get new schedule lines  as and when the mat is available
    regards
    madddy

    Of course MR Reazzudin
    well this is a ticket that i have received the customer wants schedule lines to be generated for a material automatically everytime it is in stock..currently even if there is a part of the items are aavailable it shows one schedule line with confrd qty as zero
    i mean if the order is for 10 and if 2 are ava rite now
    there should be aschedule line for 2 first and then wheneger further qty is available there is should be a new schedule line
    I myself am not very clear wit the whole process in background
    further information that i can provide is schedule line used is ZCP
    Req class and type is ZCS made to order stock.
    Thnk u for your time.

  • Schedule line category and item category

    Hi all,
    Can some body explain what is the use and differences between Schedule line category and item category?
    Where exactly they come into picture when a sales cycle is done? it would be very helpful.
    Thanks in advance.
    Manu

    Hi,
    SCHEDULE LINE CATEGORY:-
    Schedule line Category determines the Schedule lines for the Line item, it will determine whether the Item is relevant for  Delivery or not
    Transfer of Requirements are also controlled
    Availability check at the Sales order is controlled with the Indicator set at SCHEDULE LINES
    For Third Party processing, the Purchase requisition is created based on the Setting at schedule lines
    Together with the ITEM CATEGORY , the schedule lines determine whether the Transaction is Relevant for MRP or not In the Transaction code VOV5
    ITEM CATEGORY:-
    Item category is a significant part in processing the sales document
    Item category determines whether particular item is relevant for Delivery ot not,
    Whether item is relevant for the  Billing
    In Determine the Availability and TOR Item category plays an important role, for example the Availability check at DELIVERY will be taken place based on  the DELIVERY ITEM CATEGORY
    Some Fnctionalities like OUTPUT, TEXT, PARTNER, INCOMPLETION are controlled
    DIP which in the ITEM CATEGORIES is the Main Integration Between SD and PS
    Thanks,
    santosh

  • Link between schedule Line Number and Delivery

    Is there a link between Schedule line Number and Delivery number ?
    Eg. Line item 10 with quantity 100. 
    has 5 schedule lines..with 5 different delivery dates.
    1 .  quanity 40
    2.   quantity 30
    3.   quantity 20
    4.   quanity  6
    5    quantity  4
    For schedule line 1, 2 deliveries were created,
    one      with quantity 20
    another with quantity 15
    quantity 5 is still not delivered.
    also schedule lines 2,3,4 and 5 are fully delivered.
    Is there any table, FM etc in SAP which will give me the link between the schedule line and delivery number ?
    Total deliveries created : 6. - But which delivery corresponds to which schedule line ?
    Please dont tell me to look VGBEL and VGPOS.. that will just give line item number 10.. I need to get the schedule line number.
    Also, RV_SCHEDULE_CHECK_DELIVERIES --> will give me the delivered quantity against each schedule line.
    My purpose is to create an ontime delivery report .
    a report which list each schedule lines, and tell, how many shipments were late/ontime/early etc..
    and for Late ones, how many days late has to be found.
    this is where i need the delivery.
    No. Of days Late = Actual GI Date - Planned GI Date.
    Actual GI date is in the delivery.
    Any suggestions ?
    Thank you in advance.

    Hi,
    Check in the below link.
    relation between VBEP-ETENR and LIKP-VBELN
    Thanks,
    Sree.

  • Check boxes that turn layers on and off

    hay all
    im fairly new to this part of adobe but i have a good understanding
    what i need i to be able to have check boxes that turn layers on and off when the tick is shown and when it is not
    i know this is possible through scripting but i dont have the ability as of yet to carry out the scripting
    is someone able to write a basic script for me or help me to understand what i need
    i want the script to be for when a check box is clicked (mouse up) that a layer that was oringaly turned off to be turned on (electricalplan)
    once the tick is removed i need the layer to turn off again
    i need to do this for mulitple layers (about 10)
    so i would just use the same script for each replacing the name with the correct name.
    i also need the check boxes to work together so that i can have multiple turned on at the one time (electricalplan) (sewerplan) (waterplan)

    Do you know how to access fields with JavaScript? I access the script way of the check box properties and selecting the actions tab.
    Do you know how to set the optional value for a check box? Yes    
    Can more than one layer be displayed at a time? Yes
    Do you want to toggle the OCG by name or element number in the OCG array? I would like to toggle by name

  • [svn] 3787: Added FxTextArea, FxTextInput, and TextView class-level examples to the Component Explorer.

    Revision: 3787
    Author: [email protected]
    Date: 2008-10-21 12:16:28 -0700 (Tue, 21 Oct 2008)
    Log Message:
    Added FxTextArea, FxTextInput, and TextView class-level examples to the Component Explorer.
    Modified Paths:
    flex/sdk/trunk/samples/explorer/explorer.xml

    One workaround is to turn off automation:
    File-->Options, Advanced tab, General Section, uncheck "Enable Automation Events"
    However, you will loose the ability to configure callouts, and all of the commands in the Process Engineering tab.
    Another workaround is to change the loop number of the shape you are editing before changing its type. Then change the loop number back to the correct loop number.
    This is another example of the pernicious philosophy of trying to help the user do what the programmers think the user is trying to do that started in Excel 2000 (where you can no longer tell excel that you want a scatter plot - it will force the plot
    to be a line plot under certain circumstances).
    I suppose another option would be to modify the master and swap the text and subtype shapes in the indicator to use the subtype property for the loop number and then use the text for the instrument type. I guess this is what MS was trying to implement, but
    didn't explain it well enough to their programmers.

  • How to do budgeting at activity level and WBS element level in project syst

    Dear GURU's,
    Can any one please suggest me how to do budgeting at activity level and WBS element level in project systems, friends please I required set by step process.
    I need how to do this configuration to map this scenario.
    Regards,
    Bhanu

    Hi Bhanu,
    Use this link :
    http://help.sap.com/saphelp_45b/helpdata/en/86/98853478616434e10000009b38f83b/frameset.htm
    after page opens , click on BUDGET MANAGEMENT , There you will find each and every step you want .
    Thanks ,
    Dhruv Kumar Malhotra

  • Valuation at plant level and company code level

    Hi,
    Can someone explain me the difference between the valuation at plant level and company code level with a real world example?
    Regards,
    Malsha Kalubowila

    Hi,
    Inventory can be valuated at two levels either at company code level or at plant level. If you select valuation at company code level, all materials across all the plants will have same material price since valuation is at only company code level.
    Say for example Company code 1000 is buying a material which unit price is Rs. 10 from a vendor who supplies to two different plant A & B of company code 1000.  Assume Plant A is situated near vendor premises itself (so freight cost is Re 1 extra)  whereas plant B is situated at far away from vendor place (so freight cost rs 2 extra) and both cases freight cost is borne by the company and not by vendor.
    Assuming you have selected valuation at plant level, now in plant A same material will be valauted at Rs. 11 (10 +1) whereas at plant B it is valuated at Rs. 12 (10+2).
    Whereas if you have selected valuation at company code level, price will not be valuated at plant level rather at company code level which will get updated at moving average price in this case.
    So it is always best practice to select valuation at plant level rather than at company code level.
    Reg
    Karthikeyan G

  • Mismatch in InStock Quantity in Item Master at Item level and W/H Level

    Hi,
          All,
                I get some mismatch in 'InStock Quantity' at Item level and W/H Level, in Item Master.
               for Some Item and mismatch increases day by day.
    ex:          At one total item Instock Qty : 100
                   but in W/H 1 InStock Qty :   -80
                   in W/H2  InStock Qty :   -2
    Please give me reason for such a problem and also, solution to overcome this problem
    Thanks
    Vivek Kumar Gaurav

    Dear Gordon,
    Thanks for replying me.Yes,there are multiple add-ons are running on client. There is no work done with SAP inventory. So you can consider that it's a problem of vanilla SAP B1.
    Warm Regards
    Vivek Kumar Gaurav

  • Schedule Line Category and Availability checks

    Hi Folks,
    A generic question.
    Wanted to know, how would availability check results influenced if only Item category and MRP type are maintained and not the scheduled line categories.
    Was trying to figure a strange Availability check behavior of non-confirmation for one item category and confirmation for another- item x location being same. The ATP checks settings are maintained and called from GATP. (not R/3 and R/3 customization is not imported too).
    Regards

    closing

  • What is the direct link between Schedule Line item and Delivery line item?

    Hi SAP SD Gurus,
    The question is simple.  I would like to calculate the Open order quantity for a particular month based on the Schedule Line Date.
    I am taking all the Schedule lines falling below the running date of the month and sum up that and look for the deliveries happened for that Schedule lines.
    I am unable to link that Schedule line with that Delivery line item.
    The only link is Schedule Line Number in VBEP table which is not available in LIPS.  I would like sum up the Schdule line Quantities and Subtract the sum of the Delivery quantities which will give me the Open orders for the particular day of the month.
    Can anyone help me to link this VBEP table to LIPS table to connect the Schedule line number with the Delivery line item?
    Thanks in advance for your help..
    Augustine

    Anuj,
    I am aware of the Functional Modules. 
    I wanted to know for this Schedule Line, this is Delivery document created.
    Where in SAP through Tables it is linked?  Because, I need to source the Tables to calulate the open orders by way of external report through Business Object.
    The table link from VBEP to LIPS is not directly linked.  It is linked from Sales order line item level.  Because we are capturing all the Sales order Line tiems through the Delivery Status which is not equalled to C. But if there are partial deliveries against the Scheuld Line item level, we need to identify.  The only common joint should be Scheldule line number which is not available in LIPS.
    If we are developing report inside SAP, we can use the said Functional Modules to capture through Structures VBEPD.  Since it is a external reporting , we need to give correct tables and the joints.  Hence I am looking for any other way to solve this.
    Thanks
    Augustine Ponraj

  • Availability check problem - with item category(TAN and TANN)

    Hi All,
    We have a problem with the availability check in the standard order. Suppose if I give the item category as TAN, the availabilty check is green for that line item. If I change the item category from TAN to TANN, then the availabilty check is red.
    How Item categories influence the availability check? Is availability check also depend on customer?
    Thanks & Regards,
    Anil.

    Hi ,
    please check in this path.
    Customer Relationship Management>Basic Functions>Availability Check>Assign ATP Profile to Item Category
    In this step you assign the ATP profile to an item category:
    1. Choose the relevant item category.
    2. Enter the name of the ATP profile in the ATP profile field.
    If this field is empty,  no availability check is carried out.
    ATP profile-
    1. A key that is assigned to the item category of a sales transaction item to control whether availability check takes place for this item.
    2. If availability check is carried out in SAP Advanced Planner and Optimizer (SAP APO), the name of the requirements profile in SAP APO is used for the ATP profile in CRM Online to carry out the following functions in SAP APO:
    -ATP check
    -Transfer of requirements
    -Delivery scheduling
    -Transportation scheduling
    Hope it will useful.
    thanks
    Hemant ghiya

  • Schedule Line Cat and Passing of Reqs:  Credit Hold Situation

    Business need is for orders that are on credit hold to not pass requirements to create a purchase req. after MRP is executed. I realize that this can be controlled by the Schedule Line Category. So, I would have schedule line category of “XX” on the sales order line. Is there a way for the schedule line category to be changed to a different value (which will allow the passing of requirements to MRP) after the order is released from Credit Hold? How do we get the schedule line category to change on the sales order once the order is removed from credit hold? Can this be accomplished through standard configuration?

    Hi Tom,
      You can use the reason for rejection at the item level.
      But for this you have to maintain somne configuration.Goto sprosd-sales-sales document item--define reson for rejection.
      Here for a particular reason for rejection just put tick under blc column.
      This means the order doesn't require billing.
      Now put the same reason for rejection in your item level.The status of the order would change from open to completed.
      Completed status means that there are no requirements left for this order.
      There will be no requirements in MD04 as well.
      When you want to process the order again just remove the reson for rejection and proceed.
      But there is one problem with this solution.In future if you want to find this order in VA05 ,it will not appear because the status is completed.It would be difficult to find the orders where you put the reason for rejection.
    The only way to find those orders is thru tables.
    Goto SE16 and table VBAP .field is ABGRU.
    In the selectio screen of VBAP put ABGRU and you will get all the orders.
    Reward points if it helps
    Regards
    Karan
    Message was edited by:
            Karan Bhatia

  • Availability check on storages in sales order and delivery documents

    Hi all,
    I'm verifying if it's possible to find a standard or a custom solution for this type of problem:
    I have a scenario in which there are more storages relevant for MRP (ex. 01, 02, 03, 04), and, in if I check availability in sales order or delivery (using checking rules "A" or "B") with setting which considering storages location inspection in availability check control, system check if there's stock available on all these storages.
    I'm trying to verify if it's possible to consider only some on these storages (ex. 01 and 03 only) in sales order and delivery documents availablity check.
    I know that in sales order storage location field is normally filled only using exit, but i don't know if it's possible to do, using a user exit, check availability considering only some storages and not all. At delivery level i have tried to use stock strategy, but this functionality don't have consequences on availability check, also if it's relevant during good issue phase.
    Any suggestion will be appreciated.
    Regards
    Gianpaolo

    Hi Gianpaolo,
    We had some issues with availability check on a Customer Site.
    I don't remember right now if we had to exclude storage locations from MRP to take them out from ATP, but I guess Shiva is 100% correct.
    At the end, what was done was to always "force" a unique storage location in the sales order item, which will be the storage location used for shipping of the delivery of course.
    If you use WM in your plant, then you will have no problem in having a unique storage location, so no problem.
    Anyway you are correct in your analysis, if the Storage location is not informed in the sales order item, then all the plant stock is taken in account for ATP.
    Best Regards,
    Franck
    Freelance Logistics SAP Consultant

  • MCHB,MARD - Stock available at plant level and storage location level

    Hi ,
    How to determine how much stock available at Storage location level and Plant level. (Lot is not maintained).
    In MCHB-Stock at lot level is shown.
    In MARD-Stock at Storage Location level is shown lncluding
    the stock maintaned at the lot level.
    If i want to know the stock which is not maintained in Lot, i.e, Stocks directly maintained at Storage location / Plant.
    Do I need to subtract the MCHB Value from MARD Value ?
    Is there any other way available to find the stocks which is not maintained at lot level.
    Regards
    Prasath

    Hi prashant,
    What do u mean by stock maintained at SL level without batch level.  Do u mean that some materials are subjected to batch management and some or not?
    If that is the case, for all batch managed materials, u can see the stock at batch level and also same is summed up at SL level.  But still what ever u are getting from MARD table isstock at SL level only.
    If u have activated batch management for any material, it will always be shown at lot level also.
    hope this clarfifies query
    award points if found useful

Maybe you are looking for

  • After changing from my 3S to a 5, I use much more data than before why?

    My Iphone5 uses an accessive amount of data, a lot more than my 3S and I am on the internet the same amount to time.. any clues of why?

  • Paid job: convert .stl file into .xml to import into FCP. Anyone?

    I need someone to convert my two .stl files (subtitles) exported from DVD SP and convert them into files (.xml?) compatible with Final Cut Pro. I need to Import these files into FCP and burn a Quicktime file with subtitles. I can pay someone (not mil

  • How to recover missing movie icons

    Is there a way to recover movie icons for the iPad?  I can't remember if they were on the screen when I first them or not...ugh. 

  • Query to slow

    I am using query to get number of stores and products grouped by Region it takes 5 hours I would like to get the result faster: select p.regionId ,count(distinct s.storeId ) ,count (distinct p.productId) from products p, stores s where p.regionId = s

  • HT6114 error message on mav download

    tried to download maverick 98% downloaded then came up with error message in red and now cant download as message keeps showing next to it any help please