Availability check of PRT

Hi,
I have created equipment as PRT, & assigned to routing, also made necessary settings for availability check of PRT during order creation & release. I created & released a production order & reserved work center capacity & PRT assigned. When I created a new order in the same period system is showing no availability of work center but showing all PRT are available. I am expecting that system should give the message that PRT is not available.
Please suggest.
Thanks & Regards,
Suhas

Hi,
For ensuring availability of PRT's in Order , pls check / maintain following settings :
Go to OPJK -
>Select Plant & Order type & business function
1     Check availability during order creation
or
2     Check availability during order release
then go to PRT availability Tab,
where you need to check for tick in check box no check.If tick is there remove it and maintain checking rule  as
01     Status check
or
02     Status check and inventory audit
Maintain any of the above as per your requirement.This you need to maintain for each & every order type you want to control availability check for PRT's.
Try with above settings.
Hope this fulfills your requirement.
Still any doubt revert back.
Regards,
Tejas

Similar Messages

  • PRT Availability check quantity information in production order

    Hi
    Material PRT availability check is carried out in Production Order. This gives me the information like PRT is available or PRT is missing. It does not show how much is available or how much is missing like it shows for Material availability.
    I understand that there may be the reason behind this.
    But i want to know is it possible to get the quantity information also in the availability check of PRT in Production Order.

    HI
    As per my knowledge Its not possible to check the quantity of PRT at the time of Production order....You will have to seperately check the same.
    Regards,
    Anand.

  • PRT availability check

    Hi all,
    In the PRT availability check, my user wants the inventory to be checked for some specific storage locations alone.
    Is there any settings available to restrict for some specific storage locations alone in PRT Check.

    dear,
    In spro (OPJJ) check which checling rule has the following setting
    storage location check - No storage loc check box is not active?
    that combination of checking rule and checking group should be used for PRT.
    See the more information as below
    Availability checking in SAP
    Ave checking is done in SD/PP/MM....hence it is made of two parts
    Checking rule and checking group
    Checking rule(CR) is decided by the function. like for SD it is A, for PP module it is PP...
    Checking group(CG) is the value you enter in MRP3 view for a material in the plant level
    Hence combination of CR and CG will control how the material is to be checked for availability, in we define in Customizing what are the elements to be considered. like Stock, receipts like PO, issues like reservation from production order...
    in OPJJ you can see the details of whether storage location stock to be considered or plant level stock to be considered.
    if you activate the check no storage loc insp then stock is considered as plant level, if you uncheck it stock will be considered for ATP @ stocrage loc level mainatined in the transaction during ATP check.

  • Work Order Material Availability Check Customizing

    Hi,
    I am currently trying to set up material availability check in the work order before saving. I am testing it by entering a material in the work order for which there is zero stock. Then clicking on ORDER > FUNCTIONS > AVAILABILITY > CHECK STOCK MATERIAL. However SAP would return 'All checked materials in order 100000317 are available' in status bar.
    My customizing is as follows:
    Define Checking Rules (SPRO):
    PM     Checking rule for plant maintenance
    Define Scope of Check (OPJJ):
       Availability Check: 01 (Daily Requirements)
       Checking Rule: PM (Checking rule for plant maintenance)
       Availability check: 2 (Check availability during order release)
        Stocks
        Include safety stock: X
        StockIn Transfer: X
        Incl. quality insp. stock: X
        Replenishment lead time
        Check without RLT: X
        In/outward movement
        Incl. purchase orders: X
        Incl. purchase requisitions: X
        Incl. dependant reqs: X
        Include reservations: X
        Include sales reqmts: X
        Include deliveries: X
        Incl. planned orders: X (check all planned o)
        Incl. production orders: X (take all production)
    Define Scope of Check (OIOI):
       Plant: (Corresponds to Work Order)
       Order Type: (Corresponds to Work Order)
       Check material availability when saving order: X
       Check rule: 02 (Corresponds to material being used)
       Release Material: 3 (No release if parts are missing)
       PRT Availability: No check
       Capacity Availability: No check
    I would appreciate if you could indicate if I am missing something in the customizing or if there is some sort of error. I would like SAP to display a system message on the status bar stating that this material is not available once the user enters this material.
    Regards,
    Nikolai

    I'am facing the almost the same problem. Could anyone tell me:
    1. How to make material availability check work  during Work Order creation?
    My requirement is Work Order can not be created when it has missing parts. I have set the config to '3' can not created when is has missing parts, but it still does not work.
    I have implemented SAP Notes 1148139 on my system (SAP ECC 6 Ehp 5) also, but still does not have any effect.
    I must not set the config Res./Purch Doc creation to 'immediately', because it does not fit to my user requirement. Is there anyone knows how to solve this requirement?
    2. How to make  information message/ Availability check screen appear when sparepart is missing, without clicking Availability Check button? for example: appear when clicking Save button.
    Thank you
    -amoonra-

  • Availability check during confirmation

    Hi all,
         I need material availability check do be done during confirmation of a order instead of order release...Where do i have to make the configuration change..???
    Regards,
    Joseph.

    Hi,
    As per standard practice, it is always suggested to do availability check at the time of order create / release. However, still if your client is not willing for the same then set no availability check for material, capacity & PRT in OPJK & also in Material master MRP-3 Availability check you can put as no check (KP) case to case basis.
    Also if you want to prevent errors in Goods movements at the time of confirmation then you need to maintain following config. setting :
    GO to OPK4--> Select your Plant & Material -> Individual Entry General (Tab)--> Error Handling / logs ---> Maintain tick in check boxes Goods Movements & Termination of Incorrect Goods Movements.
    However, this config. will work in case you use backflush for components & control key with Auto GR functionality. So that your GI, confirmation & GR all will be linked. System will prevent errors in GI & GR while confirmation with this config.
    Hope this helps.
    Regards,
    Tejas

  • Availability check during creation and release

    Hi Everybody,
    I am need of your expertise, The requirement is "when I try convert planned order to production order for a sales document", I am getting error say " Error during availability check". When I check the log it says "No control data maintained for checking group  XX and Checking rule $$".
    Do anyone have any kind of idea, what is this control data about?
    Thanks in advance.
    Esh

    Hi
    Please go to spro
    production >> shop floor control>> operation>> Availability check>> define checking rule
    first maintain checking rule
    go to T : code OPJK to maintain order control
    Maintain checking rule
    go to matl availablity , PRT check, Capacity check
    U can see option tick on   no avail check
    ths may help u
    Please reward points
    Rgds
    Sunil

  • Availability check in PM order

    Hi,
    In a PM refurbishment order with components, when I press the 'Availibility Check' button before release of the order, I am getting the message "No check exists for planning (item: 0010, mat.:XXXXX" (Message no. C2119). I have already maintained the configuration for the plant and the order type in Maintenance and Service Orders-Functions and settings for order types-Availability check for material, PRTs and capacities-Define inspection control as 1 (Check during order creation) and component check type as 1 (check against preliminary planning) and collective conversion as 1 (User decides on creation if material is missing) for material availibility. Checking rule is PM (Checking rule for plant maintenance).
    Please tell me what I am missing and what additional configuration I need to maintain. Our business purpose is to ultimately perform an ATP check before the components are committed from the warehouse for consumption after order release. But before that I need to ensure that the availability check is working correctly and not giving error as above.
    Thanks and regards,
    Abhijit

    Hello
    You have to mantain the additional Availabilty Check 02 for 'Release' control parameters
    Plant Maintenance and Customer Service -> Maintenance and Service Processing -> Maintenance and Services Orders-> Functions and Settings for Order Types -> Availability Check for Material, PRTs and Capacities -> Define Inspection Control.
    Then
    Availabilty Check 02
    Checking Rule:Which your using earlier
    Release Material:2
    Regards,
    Rakesh

  • Creation of Sale Order for configurable material with availability check.

    Hi,
    We have a scenario in which the material is configurable. The configurable material (X) has few variants (Ex: X1, X2, X3, X4, X5). While booking the sale order, we use the material number (X).
    Further, the material planning is done for the variants X1, X2, X3, X4, X5. The standard variants are planned for production in advance.
    1.     While booking the sale order, we want the availability check of the stock (type matching to happen). What needs to be done in configuration?
    2.     While booking the sale order, there is a possibility that the configuration selected will not match with any of the standard variants due to some additional requirements of the optional features, in such cases how to link the standard variants to the sale order & create requirement for additional requirements.
    Regards,
    Umesh

    Hi Umesh,
               1.Create material master for configurable material and variants in mm01.
               2.Maintain BOM for the configurable material in CS01
               3. Configur the variant configuration steps
                  a. Create charecteristics T.code CT04
                  b. Create values and assign classes
                  c. assign the values to charecteristics
                  d . Maitain dependence  T.code CU01
                  e.create configuration profile t.code CU41
                  f.stimulate the configuration profile.
    4. Do the availability check configuration through this path
    IMG --> Sales and distribution > Basic functions ,> Availabilty check and Transfer of requirements.
    5. Maintain the Availbility check field and MRP views in the material masters other wise you sit with PP people and do that
    I hope it will help you
    Regards,
    Murali.

  • Availability Check not working for Item Cat TANN or YG05 in Btch Split

    Currently working on implementing Automatic Batch Determination (BD) project and one fine piece is holding up the implementation (make or break for project).
    In our QA System:
      - In inventory we have a quantity of 2 for a material: 1 in one batch and 1 in another batch.
      - Create an order with 2 line items with the same material number for a quantity of 1 each.  Line item category is TANN
      - When you generate the delivery the batch determination causes the items to split (even though you have a quantity of 1 in the line item).
      - When you go into the delivery and open up the 1st line item and look at the 900001 line, BD chooses the 1st batch for a quantity of 1.  Line item category is YG05.
      - When you open up the 2nd line item and look at the 900002 line, BD chooses the 1st batch again, NOT the 2nd batch which it should.
    If I change the line item category on the Sales Order to TAN and generate the delivery, BD correctly assigns the 1st batch to the 900001 line item and the 2nd batch to the 900002 line item.  Which is correct.
    Now for the strange part.  The TANN item category and BD works find in our DEV Sandbox, but NOT in our QAS system.
    I have spent two days now trying to find out where Availability Check is assigned specifically to Item  Categories and any differences between our DEV Sandbox and our QA systems to no avail.
    Our customers need the ability to be able to put the same material number on multiple lines of a sales order due to special pricing per customer within an order.
    Can anyone direct me to some configuration or transaction that controls Availability Checking by Item Category.  I have checked the 0VLP transaction and they are identical between our DEV and QA system for the TANN and YG05 categories.
    Any help will be greatly appreciated.

    In VOV6 the 'CP' Schedule Line Cat. has the Availability flag check.  There were a few areas where I found an "Availability" flag and made sure there were all set.
    But, I did finally find out what the error was:
    Logistics Exec -> Shipping -> Basic Shipping Functions -> Avail Check and Transfer of Requirements -> Transfer of Requirements -> Determination Of Requirement Types Using  Transactions
    There are entries by Item Category.  For
    I/C = TANN
    MRP type = PD
    the Requirement Type was missing (if you look at the entry for TAN/PD you see an 11 in the RqTy column).
    So I entered a 11 (Delivery Requirement) into the field and now the Availability Check works and I am getting the correct Batches and quantities during Batch Determination.
    There is no entry for the YG05 batch split, so I guess the system just uses the Item Category of the main line item.
    Thanks for the responses.  Sorry to bother you I should have figured this out earlier.
    Scott.

  • Longer time for Material Availability check while creation of prd order.

    Hi guys,
    I am facing a weird problem while creating production orders thru CO01.
    I enter the component and plant and I am also using the forward scheduling option.
    for some reason, SAP is taking a long time for material availability check when I hit the release button.
    Sometimes its taking more than an hour. Its happening with few specific BOM's, and I have checked the master data but I could hardly find a problem in master data.
    Can someone suggest me some tips ??
    Thanks & Regards,
    Sashivardhan

    Hi,
    Please check the Availability check control maintained for Components it should be 01 or 02. Also check the issue storage location maintained or not. You can maintain issue storage location in BOM in Status/lng text tab in Production Storage Location.
    Hope this will help.
    Regards,
    Navin

  • Availability Check at Storage Location Level.

    Hi All,
    Currrently we have the availability check functionality happenin at the plant level. If the stock is available in the plant, then the sales order is getting confirmed. But, the requirement is if the stock is insufficient then system should check all storage locations attached to the plant. Can someone please guide as to how this can be achieved?
    Regards,
    Raghav

    Hi
    This is not a standard SAP functionality. Either you have to input the storage location manually in the sales order or to automate this,  you have to enhance the functionality using a userexit.
    Thanks,
    Ravi

  • Availibility check at Storage location level

    Dear all,
    we have implemented inventory management ( not wm and lean wm ) , my business scenerio is when i am creating the STO the availibility check is carried out which is considering all the storage locations of supplying site
    e.g  SL01 - Unrestritrd Use
           SL02 - Damage
           SL03 - Resrved
    My client requiremnt is when availibility check should carried out it should conside only one storage location i.e SL01 - Unrestricted use stock and should not considere Stock of other storage location except SL01.
    What configuration need to be done
    Thanks and Regards
    tara

    Dear,
    Check at: http://www.sap-img.com/sap-sd/configuring-availability-check-through-checking-groups.htm
    http://sap.ittoolbox.com/groups/technical-functional/sap-log-pp/availability-check-storage-location-1283776..
    Regards,
    Syed Hussain.

  • Reserve stock in availability check

    Dear Gurus
    I have one requirement. I have searched forum but I didn't get anything which helps me.
    I have a material A with 5 quantity in storage location 1064. When I create sale order of this material with 3 quantity system reserves this stock against this sale order.It will remain reserve until i reject this order. Thee are many open sale orders against which stock is reserved. I have to find out orders with VA05 and reject them. If i create new order of same material with 3 quantity system will only confirm 2.
    My requirement is that when i press availability check button system should only check available stock, no stock reserve. When i create delivery system should copy available stock. In short there must be only availability check, No stock reservation.

    Dear moazzamjii
    My requirement is that when i press availability check button system should only check available stock, no stock reserve.
    If this is your requirement you go to OVZ9 in that just flag the iinclude sales requirements in the in/out movements.
    Check and revert
    Thanks&Regards
    Raghu.k

  • Sales orders with availability check?

    Is there any transaction code to generate list of sales order /open orders with respect to availability check ( with the combination of organizational data)?.  will anyone share your expertise pl.

    Have you tried with VA05 where you can see tabs like
    -  Open Order quantity (quantity not yet despatched),
    -  Confirmed Quantity
    -  Status of the order (Partially delivered, Being processed etc)
    thanks
    G. Lakshmipathi

  • CRM Availability Check not working for certain Item Category

    Hi there,
    I have a situation where for certain order type/item category combinations, the availability check on the same material is not working.
    The check is set up to happen in SAP ECC.
    I have checked the config. under SPRO->CRM->Basic Functions->Availability Check->Availability Check using SAP ECC
    as per many SDN posts on this, and everything looks fine.
    The new item category, which was a copy of an existing one, works (i.e. gives availability) for certain order types, but not others.
    If I create the same order directly in ECC, it works correctly every time.
    I searched the code (from consultants who set it up originally) and can see nothing specific to the order type/ item category.
    I also put a breakpoint on AVAILABILTY_CHECK function module in SAP ECC - it is not being hit, in the case where check is not successful.
    Breakpoints in MV45AFZZ (Sales Order userexit) also not being hit, but they are hit for the Order/item category combination when it works successfully.
    Any suggestions on where else this could be configured would be appreciated!
    thanks,
    David

    Hi David,
    One 'simple' reason for this could be that the copied item category does not have the
    ATP Profile set up in the item category in the IMG. Make sure you have an ATP profile assigned in the area 'ATP Profile' in the item category.
    Please see as well the SCN Wiki link:
    Availability Check CRM-BTX-BF-ATP - CRM - SCN Wiki
    Best regards
    Christophe