Availability control not activated - Real Internal Orders

Hi Experts,
I have created one order type with Object class overhead, budget profile 0000001. Defined  Tolerance Limits for Availability Control.   And I have created one order and maintained budget. If postings are exceeding the budget, system is simply saving it not giving any alerts.  I have done KO30, system showing the message "Availability control not activated in any further objects".  Where I  am missing the configurations?
Regards,
Rajeswari

Hi,
Check whether the commitment management has been activated.
Check in transaction OKKP for Order management & commitment mangement active in controlling area level.Check the company code assignment also in controlling area.
Then check the activation of the Activate Open-Item Management in Order Types in Tcode KOAO.
whether commitment mangement tick is active against the order type.
Activate the availability control as automatic orelse activate when you assign budget in KO22 transaction.
Check both the setting.In some case it may not work in DEV server if you active later,Transport request to QAS & check it will work.
Regards,
Raj

Similar Messages

  • Can we create a Budget & Availability Control for revenues with internal orders?

    Dear SAP Gurus,
    I have created an expense budget with the help of an internal order and have assigned the same to an expense GL (cost element). I have done all the necessary system settings and the system gives an error message when the F-02 document posting exceeds the budget.
    My query is, I want to replicate the the above for revenue postings. I have done the same system settings for revenue posting however the system does not give an error when the budget amount is exceeded.
    Can I please get some assistance with this requirement?
    Best Regards,
    Akshay

    Hi Akshay,
    System will not give the error in the case of Revenue GL. Because all the revenue GL will be hit for credit. It means it will update negative against the budget available. It means
    Current Budget-(-Revenue Budget)= Current Budget + Revenue Budget= Available Budget
    Because of this system will never give the error.
    Regards,
    Ankit Agarwal

  • Depreciation posting to real internal order in ECC 6.0

    Hello SAP experts,
    Our business scenario is we want to post the depreciation calculated on asset to Real Internal Order and not Cost Center.   We are implementing in ECC 6.0.
    Q1 - what are the basic configuration required
    Q2 - Internal order created will have which object - Overhead or Production or Investment.
    Please reply .
    abhay

    Dear Abhay,
    You can check the Screen Lay out rules for your asset master data under Logical Field Group - Time Dependent Data. Normally you don't have Internal Order as a selection option for posting depreciation. However check there if you can insert field group for internal order as well there.
    Regards,
    Sanjay

  • Real internal orders to statistical

    Hi Gurus,
    Could you please let me know if we can change the already existing real internal orders to statistical orders.
    If so, please provide me the information on where we can do it.
    Thanks
    Sri

    Hi Sri,
    Go to transaction code KOT2_OPA and double click on the order type, i guess you are using order layout, if so click on the button "field selection", which take you to another screen, scroll down and you would find a field "Identifier for statistical order", for this field select the radio button under Input, this would allow you to select the Statistical order button while creating the internal order.
    For changing the settlment profile to 90, would not allow you to settle the costs to any object. Please keep in mind, if you have orders with balance, changing the settlement profile to 90 would not allow you to settle the costs to the receiver and the order would always balance and this might impact your reports.
    Let me know if you have further question.
    Thanks.
    Best Regards,
    gj

  • Amount in PR not reflected on Internal Order .

    HI SAP,
    When i creating a PR i got sap message said "Do Not assign any objects in cost accounting to account XXXXXXXX ". Then i just press enter because it just a warning from SAP.
    My total Valution Price in PR is 10K. My PR is using Account Assignment A and have internal order (BUDGET)
    After saving. i check my internal order report (S_ALR_87013019), than i noticed that my total amount in PR is not reflected on My internal Order list.
    is there any condition missing ?

    >
    Nizamkz wrote:
    > HI SAP,
    >
    > When i creating a PR i got sap message said "Do Not assign any objects in cost accounting to account XXXXXXXX ". Then i just press enter because it just a warning from SAP.
    >
    > My total Valution Price in PR is 10K. My PR is using Account Assignment A and have internal order (BUDGET)
    >
    > After saving. i check my internal order report (S_ALR_87013019), than i noticed that my total amount in PR is not reflected on My internal Order list.
    >
    > is there any condition missing ?
    The above warning message meant that your cost accounting is not configured for this account, in this case your account was not linked with internal orders, thats why it did not pick up the price there. You need to consult with FI to get this account fixed, or use some other account which is linked to internal order.

  • REAL INTERNAL ORDER

    hi
    I created a real internal order for CWIP and order is half completed, what will be treatement for month end closing.
    This order will be continue for 3 months. please explain detail process.
    thanks
    sapian

    1. Go to KO88 give order number, period, fiscal year  and asset valuation date, and select processing type as automatic and executive.
    The order costs are transferred from relevant expense account to CWIP account. 
    2. If you want to transfer this CWIP account to main asset account, again go to KO88 and take processing type as full settlement and executive
    This time, cost are transferred from CWIP to main asset. 
    If you want to keep amount only in CWIP upto the completion of total work, run full settlement only after three months.
    Regards
    Radha

  • Actual and Commitments values are not Appearing in Internal order report

    Hi
    We have done budget in KO22 for Internal Order and active the availability controle after that we made PO with the same IO and with account assignment category 'A' and GR also happened.
    So when we run the report (S_ALR_87013019 - List: Budget/Actual/Commitments ), system is not showing Actual and Commitments values...
    Please help me in this regard...
    Thanks,
    Saisri

    Hi,
    Here we are giving internal order in PO with account assignment category 'A'
    In case of Account assignment category 'K'  it is showing the Actual values in Report.
    Why is it showing Actal /commitment values incase of 'K'  ?
    Why it is not showing when we select the 'A' category ?
    Please provide me answer about my queries...plz
    Thanks,
    Saisri

  • Buget Availability check on PR for Internal Order

    Dear experts,
    Is there any configuration in SAP where we can check the PR Valuation price against the Budget availability in Internal Order?
    Thank you

    Dear YEN,
    We need to set up
    Define Tolerance Limits for Availability Control
    in Customization to keep a check in on the valuation amount in the Purchase Requisition/Purchase Order/etc...
    Controlling Area
    As maintained in your organization
    Profile
    As maintained in your organization
    Availability-control activity group as
    ++     All activity groups
    Availability control action
    1     Warning
    2     Warning with MAIL to person responsible
    3     Error message
    Usage in Percentage
    eg 80%
    90%
    Give points if above data was Helpful
    Thanks and regards,
    Vikat Verlekar

  • Budget controlling for PO using internal order

    Dear experts ,
    can anyone tell me the step by step procedure to have a budget controlling on PO based on budget ?
    Regards
    anis

    Dear Anis,
    Create Statistical IO and assign budget to them. Then at the PO enter A at the Account assignment or K and you enter the IO number.
    If you want the system to check for budget go to SPRO -> Controlling -> Internal Orders -> Budgeting and Availability Control you define Budget RPofile etc and at the selection 'Define Tolerance Limits for Availability Control' you define for you Company code how the system reacts during PO creation. You give tolerances to display messages if the budget is close to depletion etc
    Bare in mind that PO create commitments and when the invoices are posted the amount becomes actual. You can check report S_ALR_87013019.
    Hope it helps. Generally i have used it, it is very good solution and easy to implement.
    BR

  • How to confirm activity for Internal order having object class PRODUCTION

    Hi,
    We have Internal order which has object class PRODUCTION. In it material and labour cost got confirmed
    Here my doubt is how can I check the activity confirmation details in the system (Not CO15)
    In otherwords how can I display internal order activity confirmation
    I ll be grateful anybody answer quickly
    Regards
    Sneha

    Hi Sneha
    1. You can use KB21N - Screen variant ALL
    2. If you want to check any postings on this Interna order - Use KOB1
    Regards
    Ajay M

  • Plant not populating in internal order

    Hi All,
    When we release a serivce order in CRM-Service, system is creating internal order. But it is not populating plant field in internal order. We have done the customizing of linking service organization to plant in CRM. Could you please let me know if there are some other configurations/enhancements to be done to derive plant field for internal order in ECC?
    Regards
    Suresh

    If plant is maintained in Customer-Material Info Master & Customer Master, it will be defaulted in Sales Order.
    But incase of Plant being maintained in Material Master, it is a common practice that it requires to be maintained in Sales Otder. If before entering the Material, Plant is maintained at Header level in sales Order, it will default in Line items, else it is required to be maintained for all Line Item.
    This is Stansdard SAP.
    Regards,
    Rajesh Banka
    Reward points if helpful.

  • Zrps (copy of vprs) not active in sales order in order to post it to copa

    Hi All,
    Our company is selling products to its other entities (in other parts of the world) who are not in SAP.
    We should be selling to them at 110% of the actual cost.
    I copied VPRS to ZRPS. In the Pricing Procedure, i placed ZRPS on top, followed by ZPRI (it has condition record for 110%), ZNOR (manual condition type, where in if the user wants to enter a price manually, then can enter).
    lf the cost of the material is $30, in the PP, ZRPS is inactive with $30, ZPRI is active with $33, no ZNOR. and the rest below to it looks beautiful with the totals.
    But what's the problem is, in order to get ZRPS into COPA it has to be active, and it is not active in current situation. As ZRPS is mapped into I/C COGS in COPA as this can be seen at the time of billing.
    I want this ZRPS to be active in order to get this solved. I also added VPRS at the bottom. It has a red bomb with $0 value. It did nt work either.
    Hope I am clear.
    Please suggest me on this or any other solution.
    Thanks in advance.
    Regards,
    Vamsi.

    Kindly check at you Item Category in VOV7 whether Determine Cost checkbox is activate or not.
    As before maintaining Condition Type in the Pricing procedure ,it should be activated at Item Category level.
    Best regards,
    Ankur

  • Controlling Release status on Internal Orders

    I'm creating a new Internal Order type, and I want to ensure the settlement rule has been maintained (or it has system status SETC) before it can be released.
    The settlement rule is not an option you can set in the field maintenance screen, and I can't see anywhere else I can ensure this has been done.
    Is there anyway I can stop it being released before this has been maintained - I'll only do it if it is achievable within standard SAP, so I don't want to add ABAP/GuiXT etc to achieve this
    We are on SAP v4.7
    thanks
    Graham

    Dear,
    Just do following steps.
    Use transaction KOT2 to create internal order type and if you have already created then enter into it.
    Here you will see the Field Selection in the bottom of the screen, go into it and hide the field Identifier for statistical order so that user creating order might not select this because it states that if order is statistical then there will be no need for settlement.
    So that we are hiding this field on order creation screen for not allowing user to select this and when order is not statistical then Settlement Rules have to be create or system will not allow to save the Order.
    Moreover don't authorize user to change the order type to ensure the best development of the process.
    Regards,
    Chintan Joshi.

  • G/L account not populated for Internal orders

    Hello All,
    PO amendment creation with reference to a PO of type Internal Order(Y) is prompting to enter the G/L account,
    where as when we do the same for a Cost center(k) , it automatically gets it.
    so i want to know does it is lacking of some configuration, or to fulfill this requirment , i need to put some code in required place.
    regards,
    Nitin

    Hi Nitin,
    If you want to determine the G/L account, I can presume that you are using a material code that has defined a valuation class.
    Then, it is only to customise the Account modification for the Account assignment category "F - Internal Order".
    Go to SRO > Materials Management > Purchasing > Account Assignment > Maintian Account Assignment Categories.
    Then, double click on "F - Order".
    In the next screen, in the Detail Information section, populate a value in the "Acct modification" field, i.e. VBR.
    After that, the G/L account will be determined in the PO.
    But, if you are not using a material code, make sure that your material group has defined a valuation class.
    Check this in SPRO > Materials Management > Purchasing > Material Master > Entry Aids for Items Without a Materials Master.
    There, check the material group that you are testing and check if the "Valuation class" field has a value.
    If this has a value, then, the G/L account can be determined once the customising mentioned above can be done.
    I hope this help.
    Kind regards,
    Sandra

  • Goods receipt not possible against internal order

    Hi Experts
    Internal order  error, PO has been raised against this internal order  when a good receipt was attempted to be posted it was blocked saying the Internal  code was not recognised.Please give your valuable suggestions
    Regards
    Ayub

    Hi Dear,
                In your case please check the following points:
    1. Check if the Internal Order is released.
    2. Check if the PO created is in refrence with the PR(Generated Automatically Via Internal Order).
    3. Check back if the Internal Order is not Technically Completed, If TECO done then Please remove the TECO.
    Hope it will help you.
    Regards,
    Yawar Khan