Budget Exceeded error while changing in Account Assignment

Hi,
The user is facing an error while changing the Accounts assignment category to "Assets" in a PR. The PR was created with AAC as "U" for all the line items. The user is changing that to "A". After that he provides the asset number then the error is coming as below:
Item 010 Order 0809/A15 budget exceeded
Message no. BP604
Diagnosis
In document item 010 Order 0809/A15, budget for fiscal year 2010 was exceeded by 6,630.00 INR.
The valuation price for that particular line item is Rs 6630.00. I have not changed the other line items.
Need the suggestion.
JK

I think there some settings in Budgeting, n Finance people are more familiar with those settings. Normally, if u craete a Purchasing doc. PR or PO or GR/ IR from MM side, with account assnt., the relevant budget()which is created for that commitment item) will updated with the document value. There may be settings with delivery date or so. check with your FI guys
umakanth

Similar Messages

  • Budget exceed error while unreleasing the service entry.

    Hi experts,
    My problem is the systm generating budget exceed error while unreleasing the entry sheet in current fiscal year.
    Entry sheet is released in privious fiscal year. User want to reverse this in current year. All budget(actual/commitment) are carryforwarded to current year. While unreleasing the entry sheet, system throwing the budget exceed error. There is suficent budget in current fiscal year.
    Request you to pl suggest what might be the cause of problem.
    Regards
    shrikant

    Hi
    Thanks for reply
    For WBS element A-101.01
    For year 2009
    current budget is  100000
    Distrubutable budget is 100000
    Assigned budget is  100000
    For year 2010
    current budget is  300000
    Distrubutable budget is 300000
    Assigned budget is  200000
    Service PO created in 2009 year for amount 20000/-. Service Entry sheet created  and released in 2009 .Vendor invoice has not be generated. Error budget exceed is raised for year 2009 while reversing the service entry sheet in current posting date.(privious posting period /year closed).

  • Budget Exceed error while settlement in PS T-Code CJ88

    Hi Guru's,
    I have created structure upto 6 level and i have done planning and budgeting at 6th level only, and actual cost is also posted at 6th level.
    When i am setteling that amount  at 5th level WBS using T-Code CJ88 then it is giving Budget exceed error of that particular amount as budget is also available at higher level WBS as accumalation of budget at 6th level is going to higher level WBS as i am following buttom-up approach.
    Please suggest.
    Regards,
    Ambuj

    Hi Rajesh,
    When you distribute budget to lower level WBS, the budget is only available at the lower level (availability is checked as: Budget - Distributed Budget - Assigned) regardless of whether it is shown at the superior level or not.
    AVAC status is activated automatically on WBS where budget is distirbuted and released (provide you have maintained Activation Type 1 in Budget Profile OPS9). Please check if AVAC status is active on your 5th level WBS. If it is active then the system will throw the error as SAP standard behavior. You can remove this status from 5th level WBS via CJBW.
    You may need to look at your budget configuration accordingly.
    Regards,
    Ammar

  • Budget exceeded error while deleting CAPEX Purchase order

    Hello All,
    We've created purchase order with WBS element for some materials & account assgn P. This however needs to now be deleted as there has been mistake in th PO.
    But while trying to delete the PO the system gives an error message " WBS element XXXX.XXX.. budget exceeded"
    I've tried deleting the PR first and then the PO which works fine, BUT we are not able to create another PO as the error of Budget exceeded is seen here as well.
    Please advice on how to delete the PO.
    Regards,
    ManojR

    Hi,
    Please read note 178837 which gives information on how to check the real assigned value.
    I would like you to run report ZKAOIDE0 from Note 100409 to remove
    the data which is not linked to a valid purchase order or requisition.
    After running the report then run transaction CJEN to reconstruct the
    project.  Then run report RKANBU01 after completing the reconstruction.
    The problem is probably that  a purchase order has the deletion indicator set but it still appears in table COOI.
    I hope this helps!.
    Best Regards,
    Arminda Jack

  • Network budget exceeded error while creating Goods receipt/Invoice

    Hi,
    I created project , wbs element, and network and released the project...i created a Po using this network...after that i went to CJ30 and allocated budget for WBS element..I activated availablity control check and define the tolerance limits for all transaction groups (++) with usage as 3(Error message) but i am not getting any error message while creating GRN/Invoice...what setting i have to made to check the budget availablity at the time of goods receipt creation and invoice creation....
    Thanks
    regards
    Dinesh.a

    Hi Dinesh,
    First of all you check whether you have assigned the budget profile in Network Profile or not. 
    Question for you: I want to hide out Account Assignment Element for first 2 levels of WBS Element and i want to consider from 3rd level onwards for specific project profile.  Any Idea.
    regards.

  • Budget Exceed error while returning material

    Hi,
    We have this scenario:
    budget is allocated at top WBSE.
    actuals are booked on 2nd level WBSE.
    Tolerance limits: ++ 90% warning
                               ++ 100% error
    Budget profile:
    Activation Type: 1
    Overall: yes
    Releases: yes
    Now,
    We have overall & released budget = 4,320,000.
    and assigned value = 3,895,085.
    Error is coming when we are returning a material from activity:
    "network activity budget exceeded" message no. BP601
    Diagnosis:
    "Payment Budget for WBSE TAT-PR09-06.01 on network activity has been exceeded by 215049.39."
    Kindly help.
    Thanks,
    Harsh.

    Hi,
    Top WBS TAT-PR09-06.1 has original budget and released the same amount i.e. 4320000
    Its System status = PREL BUDG ISBD AVAC
    Then there are three 2nd level WBSE each having one network each:
    TAT-PR09-06.1.01
    System Status = REL  AUC  AVAC
    Network Sys. Status = ACAS MACM PRC  REL
    TAT-PR09-06.1.02
    System Status = REL  AUC  AVAC
    Network Sys. Status = ACAS CSER MACM PRC  REL
    TAT-PR09-06.1.03
    System Status = REL  AUC  AVAC NTUP
    Network Sys. Status = ACAS MACM PRC  REL
    Reservations are there for all Materials in all network activities with reservation relevance indicator set to immediately.
    Error started coming to end user when he tried to send material back to general stock. This material in in network activity under TAT-PR09-06.1.03 WBSE.
    After that our Sr. consultant (he moved to another project right now) made that activity to TECO and asked the end user to create another activity and work on it.
    This is all i know.
    Thanks & Regards,
    Harsh.

  • Item 001 WBS budget exceeded error while posting cat7

    Dear Experts
    We have implemented the following modules
    PS , CO , HR
    The project system has number of projects ,
    the time booking is done using cats , the actual labour cost is entered in the cats sheet it self in the price column.
    for cost posting after the data is posted to HR system , we are using cat7 to post the data to controlling and PS module.
    Mostly all the data is transported , but for some WBS i am getting the following error
    Item 001 WBS element <wbs element name> budget exceeded  and the system is not allowing to post data to controlling for this wbs .
    What is the relavance of this error in context of HR ?
    This error is related to which module , PS , HR or CO?
    How do i reslove this issue.
    Regards
    sameer

    Hi,
    Check the budget Limit and allocation of WBS elemet.
    Tcode - CJ30 ,CJ31.
    Check the budget avaialability control as well.I think the message is coming from availability control.
    check transactoin CN41,CJBN.
    check this link
    http://www.sap-img.com/ps001.htm
    Manoj.

  • Budget exceeded error message

    Hi,
    We are in SRM 5.0 ECS, with support pack 11.
    When a PO is created with account assignment category project statistical (WBS element), with value exactly matching the budget availability, PO gets created, however if tried doing any changes to the PO, it gives an error message - WBS element budget exceeded.
    How it can be avoided.
    Rgds,
    Madhan

    Hi Madhan,
    Have a look at the following OSS Notes:
    Note 1068860 - Extended classic:Budget check errors on trying to change PO
    Note 1292419 - Budget exceeded error while changing a SRM purchase order
    Thanks,
    Pradeep

  • "Budget Exceeded" error not appearing at the time of changing PR but appearing at the time of PO change.

    Dear All,
    At the time of PR value change after creation of PO budget exceeded error is not appearing even though the PR value exceeds the budget. But at the time of changing the same value in PO, budget exceeded error is appearing.
    List of steps:
    PR created.
    PR released
    PO created with reference to PR and released.
    PR value changed to a value more than the available budget - No budget exceeded error.
    PO value changed in accordance with the PR - System throwing the budget exceeded error.
    Now the issue is why the system bypassed the budget exceeded error at the time of PR value change and only giving the error at the time of PO value change. Also, we observed that while changing the quantity in PR which results in exceeding budget, system is giving the error. But while changing the value system is not giving the budget exceeded error.
    Your inputs will be highly appreciated. Thanks in advance.

    Hello Saurabh,
    Thank you for your inputs. Below is the output of CJI5.
    Ref,Doc Category  Debit Date     Oty       Object    Cost Elem.   Val/CO Area Crcy   Total Qty.     UM
    PREQ                  28.05.2014    WBS     XXXXXX    XXXXXX           0.00                         0            EA
    POrd                    28.05.2014    WBS                                       14,000.00                1000          EA
    From the above output i think system is not capturing the PR commitment. I'm not sure as i'm basically into MM and  dont know much about PS.
    Why the system is stopping with budget exceeded error at the time of PR creation and not giving any error while changing the PR value after PO creation. System is giving budget exceeded error if quantity is changed in PR. Please explain the standard system behavior and suggest how to enable control at the time of PR value change.
    Thanks in advance.

  • Budget Exceed Error during creating of Purchase order in reference to PR

    Hi,
    I am getting the subject error (Budget Exceed Error) every time when I want to create a purchase order related to purchase requisition of my project.
    Issue is that after release the project when the purchase requisition has created for non stock item under activity I found in transaction CJ31 the assign value has already updated.
    Let say my budget is 400 US$, and the purchase requisition has created for 380 US$. Now when I check with CJ31I found the assigned value is 380. Now If I create a purchase order it throws an error that budget exceed.
    The tolerance limits are following:
    SA     ZSA01     Budget Profile Overall AVAC     ++     1     90,00
    SA     ZSA01     Budget Profile Overall AVAC     ++     3     100,00
    SA     ZSA01     Budget Profile Overall AVAC     01     1     90,00
    SA     ZSA01     Budget Profile Overall AVAC     01     3     100,00
    Please advice what will be the proposed solution for the above issue.
    Thanks in advance.
    With Regards,

    Your budget is 400$ and PR value is 380$ but you have not mentiond what is the tax value ?
    when u r creating PO at that time system will check the budget against PO value considering taxes also.
    eg. 380$+tax value.
    after considering taxes your total PO value imay be getting updated more that 400$.
    Explre you error by clicking on error information you get the exact diffrence in budget and PO value.
    Hope this will sove your problem, reply after doing this.

  • Budget Exceeded error with message No BP 602

    Hi Experts,
    I am facing a budget exceeding error: Ntwk actvty 6000001 0020 budget exceded year 2009.
    following is the settings
    Availability control against: Overall                        
    Availability control against: Budget                         
    Availability Control in the Controlling Area Currency:       
    Activation type: Automatic activation during budget allocation
    Usage level in %:  0,00
    The project is P.0001
    Top lvl P.0001
    WBS P.0001.1
    Network Activity (External services) 6000001 0010 PR-($40000) PO($20000) & Service entery done with same amount($20000).
    Network Activity (External services) 6000001 0020 PR-($1)
    Actual   $20000
    Commitment 20001
    Assigned 40001
    Available $49
    Now we updated the budget as below:
    The original budget was 40050 in IM then modified to 45050 and distributed in CJ30.
    When we try to update the Service PR with 49 or more dollars, gives error in commitments and when the log checked, the budget exceeding message is there, if the PR updated with 48 USD, it gives the budge is exhausted.
    40050(Old Budget)-40001 (assigned) = 49 USD. Which means, the supplement of the  5000USD is not considered.
    Run the CJEN and CJBN to reconstruct the project but no use.
    Please help me out where to check and what went wrong. its in client prd.
    Regards,
    Ganesh

    Hi,
    You said in reports and in CJ31 , it is showing 60049 as available. I am confused here......including additional budget , total budget you gave is 45000. Then how it can show 60049 which more than Original Budget ?
    Have you distributed additional budget to the WBSE for which Service P.R is being raised ?
    What is distributable budget at the level of the WBSE for which P.R is being created in CJ30 ?
    What Is available budget against the WBSE for which P.R is being created in S_ALR_87013558. ?
    May be it will be of saome help for you.
    Thanks
    Saikishore.Ganga

  • How to change a account assignment in and cost distrubution on cost center

    Hi Expert
    Can any one let me know how to change the account assignment and cost distribution on the cost center.
    When I am going to change it I could see it is grayed out . Why it is so .Is there any configuration for this in view that
    no body can change the account assignment.
    Regards
    NTT

    Hi
    As per me system will  not allow to change you account assignment in Po
    for additional info check following link
    [Change of Account Assignment in PO while adopting released PR.;
    Regards
    kailas Ugale

  • FF16 always fails to sync, it always shows "Sync encountered an error while syncing: Incorrect account name or password. Sync will automatically retry this."

    I'm having this problem since few releases ago, whenever I start FF, it always fails to sync, showing this line on the bottom "Sync encountered an error while syncing: Incorrect account name or password. Sync will automatically retry this action". First thought that the prob was incorrect credentials, but I can freely log-in https://account.services.mozilla.com I tried unlinking and linking my device again, it still happens.
    I waited thinking that they'll fix this, from a release to another, today updated to the last version and it still happened.
    Firefox: ~16.02
    Windows 7 Ult SP1
    http://img853.imageshack.us/img853/4070/ffsyncprob.png
    Awaiting reply,
    Thanks.

    I am having this problem with FF 19.0.2 on Win 7 Pro. The sequence of events is:
    1. Start Firefox. Get the error bar about incorrect account name or password EVERY time. I close the bar. If I wait a while and then ask FF to try again the error bar reappears.
    2. Click on preferences from the bar, and get a dialog "Your password was rejected by the server, please update your password." I click "update" and then am prompted for the master password for the security device. I enter that and am presented with an "update password" dialog.
    3. Enter my old password and click "update password." Receive error message "Password incorrect, please try again." I click update again and get the message "Your password has been changed."
    4. However now Sync no longer seems to be set up. I go through the setup ritual again, and find I am back where I started.
    I have cleared cookies, tried everything in safe mode, and unlinked and relinked the computer. I have verified I have the right password entered at [https://account.services.mozilla.com/ https://account.services.mozilla.com/] None of this helped. The problem is still there, even in safe mode.

  • Error while creating customer account sites from backend

    I am creating Customer Account Sites using the TCA API from Toad.
    I am getting the following error
    The operating unit is either invalid or it cannot be derived. Please verify your Multi-Org profile options.
    The Operating unit has been defined.
    I am using the following code:
    DECLARE
    p_cust_acct_site_rec hz_cust_account_site_v2pub.cust_acct_site_rec_type;
    x_return_status VARCHAR2(2000);
    x_msg_count NUMBER;
    x_msg_data VARCHAR2(2000);
    x_cust_acct_site_id NUMBER;
    BEGIN
    p_cust_acct_site_rec.cust_account_id := 9462;
    p_cust_acct_site_rec.party_site_id := 5473;
    --p_cust_acct_site_rec.language := 'US';
    p_cust_acct_site_rec.org_id := 126;
    p_cust_acct_site_rec.created_by_module := 'TCA-EXAMPLE';
    hz_cust_account_site_v2pub.create_cust_acct_site(
    'T',
    p_cust_acct_site_rec,
    x_cust_acct_site_id,
    x_return_status,
    x_msg_count,
    x_msg_data);
    dbms_output.put_line(SubStr('x_return_status =
    '||x_return_status,1,255));
    dbms_output.put_line('x_msg_count = '||TO_CHAR(x_msg_count));
    dbms_output.put_line(SubStr('x_msg_data = '||x_msg_data,1,255));
    IF x_msg_count >1 THEN
    FOR I IN 1..x_msg_count
    LOOP
    dbms_output.put_line(I||'. '||SubStr(FND_MSG_PUB.Get(p_encoded =>
    FND_API.G_FALSE ), 1, 255));
    END LOOP;
    END IF;
    END;
    Thanks and Regards,
    K tanna

    Duplicate post.
    Error while creating customer account sites
    Error while creating customer account sites

  • I get an error while changing modules pop up when opening Lr. There is no import button to use and if I try to load the default catalog I get the error message again essentially making Lr completely unusable for me! please help

    When launching Lr i get the initial screen to come up followed by an "error while changing modules" pop up. I have uninstalled and re-downloaded, followed all the suggested trouble shooting fixes and still nothing. When the app starts it has the basic info boxes but without any options in them (i.e. no import button or any buttons at all for that matter).All my other creative cloud apps seem to be working fine but Lr won't. Please help

    Ah, see, you said you had done it differently before.
    > and I tried to add a toolbox button by navigating to AcroPDF.dll.
    You'll need to reinstall Reader if the libraries aren't registered. You can't register them manually.
    Perhaps if you posted some of your code (where it creates the objects, etc.) we might be able to give you some more advice. You're sure you aren't trying to use anything outside of the AxAcroPDFLib.AxAcroPDF class?

Maybe you are looking for