Dear Expert,
Our client make budget for every finacial year. How do I map in SAP-FI? Anybody is having documents?
Regds,
PK
Moderator: Budget is managed either in PSM-FM or via planning module in CO (with no availablity control)

Hi,
Good evening and greetings,
If you are using Investment Management then it can be controlled using the Investment Measure...IM is the best module to control the CAPEX requirement.
Please reward points if found useful
Thanking you
With kindest regards
Ramesh Padmanabhan

Similar Messages

  • Budget control - Assigned funds are less than payment budget for fiscal year in document item

    Dear Experts,
    We are using Former budgeting, when ever we run the transaction FMBV getting the following message to a particular user.
    Budgeting
    Assigned funds are xxxx BHD less than payment budget for fiscal year
    2014 in document item XXXX /XXXXX .
    And also when purchasing creates the PO getting similar message to a particular user.
    Purchase order 450000XXXX
    Assigned funds are XXXX BHD less than the commitment budget for
    fiscal year 2014 in document item 010 XXXX /XXXXX .
    How to know where these users were maintained.
    Thanks for the help

    Hello Itai,
    Sorry for my late reply. Have you been able to find a solution for this?
    If not, please update, otherwise please make this thread as answered.
    Sorry for the delay...
    Kind regards, Mar.

  • Close budget for previous years

    Hi,
    The system Iu2019m working on has commitments management active, so when I create a purchase requisition or purchase order, the budget is affected. Iu2019ve noticed that the field that determines the year relevant for budget availability is the delivery date (EEIND).
    So if I make a purchase requisition today, with a delivery date of 2007, for instance, it will affect the budget from 2007 year. I donu2019t want this to happen. Is there any way to u201Ccloseu201D the year budget and donu2019t allow any more values to affect the budget for previous years?
    Thanks for any help.

    Hello,
    Please check the budget profile.
    In budget profile, you will have how many previous years or future years you can budgeted. Try to reduce one year for previous years.
    Regards,
    Ravi

  • Query for getting data for every quarter for financial year

    Hi,
    My problem is I need to get the data for every quarter for financial year and also I need data for every week for financial year.
    For example for financial year 2012-13, Apr2012 to Jun2012 would be Q1, Jul2012 to Sep2012 would be Q2 and so on. Total 8quarters should come upto Apr2013.
    In the same way  1st apr 2012 to 7th apr 2012 would be week1, 8th apr to 15th apr would be week2 and son on. How to write a query for this scenario in oracle. Can anybody help me on this. very urgent..
    Thanks in advance.

    lakmesri wrote:
    Hi,
    My problem is I need to get the data for every quarter for financial year and also I need data for every week for financial year.
    For example for financial year 2012-13, Apr2012 to Jun2012 would be Q1, Jul2012 to Sep2012 would be Q2 and so on. Total 8quarters should come upto Apr2013.
    In the same way  1st apr 2012 to 7th apr 2012 would be week1, 8th apr to 15th apr would be week2 and son on. How to write a query for this scenario in oracle. Can anybody help me on this. very urgent..
    Thanks in advance.
    How can you get 8 quarters within a year ? I'b be concerned here.
    lakmesri wrote:
    Hi,
    In the same way  1st apr 2012 to 7th apr 2012 would be week1, 8th apr to 15th apr would be week2 and son on. How to write a query for this scenario in oracle. Can anybody help me on this. very urgent..
    Thanks in advance.
    First, that question is really not clearly asked. Second how could it be urgent ? You even did not tell us your Oracle version, did not show any tables descr, output sample nor any effort on your side to work on.
    Nicolas.

  • Program to clear (delete) budget for single year

    Hi,
    I need to delete wbs' budget for a single year .
    I implemented Sap note Note 1145955 (Orders, WBS elements: Deleting budget, resetting status) and run program ZDELPRBU to delete the budget, but the program clears the budget of every year. The only selections are: project, wbe, and budget profile.
    How can I delete the budget for year 2010 (or another one)?
    Is there an alternative program which let choose the year?
    Thanks
    Edited by: Stifler on Sep 7, 2010 6:00 PM

    Hi There
    I have done this on Cost centres quite a while back.  What I did was create a plan version and input 1.00 in it.  I then copied the 1.00 version to the one I wanted to delete with 'overwrite' options ticked.
    This may help you.
    Kind regards
    Dawn

  • In internal order budget can we maintain for calander year

    Hi,
    my client presently  doing their planning and budgeting  in internal order for financial year but
    they need the planning and Budgeting figures as per calendar year in the SAP  can any body sujest me.
    Thanks & Regards
    Ram

    Hi Den,
    You can do the budget carryforward of internal orders to the next year in the year end closing by TC KOCO.
    Further information is available at
    http://help.sap.com/saphelp_47x200/helpdata/en/96/248f38661fca77e10000009b38f842/frameset.htm
    I hope this helps..
    Regards,
    Suraj

  • Item 000 RN1D25 /4105140000 / commitment budget for year 2011 exceeded (

    Dear All,
    Iam using FR32 for Budget Uploading in ( Funds Management ) at the time of uploading it is giving like this message
    Item 000 RN1D25 /4105140000 / commitment budget for year 2011 exceeded
    In document item 000 RN1D25 /4105140000 /, commitment budget for fiscal year 2011was exceeded by 1,650.00 INR.
    Pls give me the solution as soon as possible.
    Thanks & Regards
    Vijay

    Dear Mr/Ms,
    Thank you very much, i have cleared the issue.
    Vijay

  • SQL Query to find cumulative values for a Financial Year

    Dear users,
    My requirement is to create a SQL query for a table/view where I have day-wise data. I want to find out cumulative values for financial year by giving any date. It should add the values from start of financial year till that date in the financial year.
    I think creating a view of such type will post heavy burden on resources since accuimulation will be done for each day upto that day.
    Thanks

    Dear users,
    My requirement is to create a SQL query for a
    table/view where I have day-wise data. I want to
    find out cumulative values for financial year by
    giving any date. It should add the values from start
    of financial year till that date in the financial
    year.
    I think creating a view of such type will post heavy
    burden on resources since accuimulation will be done
    for each day upto that day.
    ThanksKumar's solution will serve yours purpose but m not agreed
    I think creating a view of such type will post heavy
    burden on resources since accuimulation will be done
    for each day upto that day. Khurram

  • Budget effected for current year for changing a PO of last year

    Dear Controlling firends,
    I am a MM guy and facing the titled difficulty. The problem is ,suppose a Po had been created in last fiscal year and at that time budget for last year has been consumed as committed. But now when I am changing that particular PO ,even trying to reduce the PO Value than the original one ,it is observed that the revised value is being again showing as committed from this year, current budget. That means the system is treating this change in amount as a new PO of the current year. My FICO collegue is not able to figure out what is the wrong in such behaviour .
    Will some one look into it aand find the solution as it is badly required to be solved without which everything is being messed up.
    Anticipating immediate response from expert CO SDNers.
    Dhruba

    Are you on 11.1.1.x or 11.1.2.x?
    If in 11.1.1.x then you can add asymmetric columns,
    if you are on 11.1.2.x version then you can "add column" with specific members from dimensions, here is little more info:
    Setting Row and Column Layout
    Cheers..!!!
    Rahul S.

  • Error while mantain budget  for project

    Hi,
    I maintained budget for project CJ30 in IDES as follows:
    1. Sellect all Item --> copy view --> choose planned total
    2. Entry: Percentage = 100%, Overwrite option
    2. All values is copied from Column Planned Total  to column Budget
    3. Save
    4. Error message:
    Item WBS element A-60000 budget exceeded
    Message no. BP604
    Diagnosis
    In document item WBS element A-60000, budget  for fiscal year 2008 was exceeded by 2.763,26 EUR.
    can anybody help me to solve the problem?
    Thank you
    Long

    Hai Long,
    For getting BCWS , you should maintain Progress version. DO following in config settings..
    1) Project Sys -
    Progress -
    Progress analysis -
    Maintain Progress version.
    2) Select Progress version 100 and copy the same and give new name.
    3) Go to details.
    4) Select option 3 ( if basis for Progress is Budget) 4 ( If it is planned cost) for Earned Value Basis.
    5) Select option 2 ( if basis for Progress is Budget) 7 ( If it is planned cost) for POC weighting.
    6) Save it.
    7) In your project select Progress tab in detail screen of WBSE and Activity and select above Progress version, select select cost propotional ( Or as suitable for ur requirement) plan and actual ( it is adviseable to have plan and actual same always to have clarity in results)
    8) Schedule and see report in CN41N.
    Please post your observations
    Thanks
    Saikishore Ganga.

  • Time type Initialization based on financial year instead of calendar year.

    Hi All,
    I'm facing this problem. By using time type i'm capturing the no of worked days for a calendar year. This Time Type is used for calculating Privilege Leave which will be divided by 20 in the year end for Quota calculation. But when I run PT60 for the period 31.03.2014 to 01.04.2014. The Time types are automatically getting Initialized.
    Here Time Evaluation is running based on financial year not as calendar year ? How to change the same to calendar year.
    Already I have searched few solution here. As per the below link
    PT60 generating for financial year but not for calendar year . But i'm facing the same issue.
    Please suggest me the solution for this.
    Regards
    Jagan

    Hi Vivek and sikandar,
    Thanks for the immediate response.
    The Time evaluation is running for Financial year (Apr - mar). But I need it to be run for Calendar Year. I gave PL Quota Time Type as an Example. But its happening to all the Time types.
    Pls suggest me how to run Time evaluation for calendar year.
    Please see the screenshot below (Time Type 9t01, 9t78, 9t80)
    All the above three time types are getting initialized on April, but i want this to happen on 1st Jan.
    I'll share my PCR if needed.
    On 31.03.2015
    On 01.04.2015
    Thanks and Regards
    Jagan

  • How to find compensation data for the year

    Dear All,
    Scenario:
    A company wants to know the comepnsation data for financial year 2009-2010.
    Problem: I couldnot find a single report which can provide the compensation of an employee for the year.
    We are trying to build a report however needs input if anyone has done that:
    Table which stores this data is PS_COMPENSATION.
    Problem is : it stores data in effective date.
    How to then convert it into a year -April 2010 to March 2011
    For example: cases
    a. existing employee: whose effective comp data will be less than April 2010
    - Plus, there are pay rate changes between April 2010 to march 2011. (Pay rate change can happen on any date of the month)
    - How can I add them to find the Compensation as per comp page from 1st April to 31st march 2011

    I'm afraid what you're looking for is not likely to be a trivial task. If you have all of the modules required for the "Report Total Compensation" product, then you should take a look at the associated PeopleBook. I think you will have to be on HRMS 9.0 at a minimum, and using Payroll for North America and Benefits Administration.
    To create a custom solution, you may have to consider a variety of other factors such job status--leave, terminated, terminated with pay, etc.--hourly vs. salaried, part time vs. full time, multi-job, variable compensation. It will depend entirely on the specific features that are being used at your site.
    If you provide a very detailed example of the output you are looking for with sample data, someone might be willing to offer a solution.
    Regards,
    Bob

  • Budget for orders

    Hi,
    while creating the budget for overall plan for 2007, 2008 yrs, we are getting the error message that In document item Order 15555, budget  for fiscal year 2006 was exceeded by 50000 INR
    That amount is the actual postings in the 2006 year for that order.
    how we can rectify the error message.
    Regards,
    Suresh.

    Hi,
    Even though i am getting the same error message for that order.
    And one more i am not able get the Budget profile field in the active mode for the process orders and maintenace order to assign the budget profile.
    Actually i need to give a buget of funds for the stores and consumption and repair and maintenace expences to get the control on those expences while raising the purchase requisitions.  But these orders are catageoried under maintenance order.
    Whether the Budget of the funds are staisfying the customer need or not? if not what way i have to approch.
    Pl. help me.
    Regards,
    Suresh.

  • Disco+ 10g - Financial Year Total Problem (ye old ORA-00979)

    Hi, I'm pretty much a newbie to Disco+.
    I have created a crosstab report for the Jul06-Jun07 financial year. The report is to display a monthly count of the number of times (days) each month an employee participates in a specified meeting type (query condition), with sub-total (column) at each QTR and Total (column) for financial year.
    - Row item is "Emp.EmpName"
    - Column items (calculated in EUL) are "Meeting.MeetYear", "Meeting.MeetQtr",
    "Meeting.MeetMonth".
    - Data points are calculation "CountMeets" being:
    NVL(COUNT_DISTINCT(EmpMeetDateID),0), where EmpMeetDateID is a concatenation
    of Emp.EmpName & Meeting.MeetDate & Meeting.MeetType.
    The report produces correct monthly and quarterly totals, but when I try to add in the grand total at right (financial year total), Disco+ generates ORA-00979 not a GROUP BY expression.
    Here'e hoping someone can give greatly appreciated guidance.
    Thanks
    Rick

    Well actually your response is helpful,
    but would you care to clarify where in the IDE you should adjust what?
    Thanks so much!

  • On financial site which worked perfectly in IE for many years, I get immediate timeout error after entering my ID and password. Does not happen every time and multiple retries do not work.

    I have used the PrimeVest web site to keep track of my IRA for several years now. For most of that time I have used Internet Explorer and have had no trouble. I have a link to that site pasted onto an Excel spread sheet and I click on that link daily to get my present balance. I have been doing it this way for years and have had no trouble while using Internet Explorer.
    I recently installed the Firefox browser on my new laptop and have switched to using it as my default browser. When I click on that link now and enter my account number and password, sometimes it works OK in Firefox and sometimes it gives me a message saying "Your session has timed out. Please Log In Again." I have tried multiple times to re-enter the account number and password but always get the same message. Closing Firefox and reopening it produces the same result. I have even tried shutting the computer completely down and restarting it, but I got the same result. I can not find any pattern or reason to the days when I can use Firefox and the ones when I can not. The only way I have been able to log on to this site on those days is to past the link into Internet Explorer.
    I do the same thing with several other financial sites and have not had any trouble with them and Firefox.

    Thanks for the response.
    I attempted to remove cookies, but I can not identify any of the cookies on the list with the PrimeVest web site. No PrimeVest, no PVs, nothing that looks like it came from them.
    I have also reported the problem to PrimeVest and their tech did answer. He suggested erasing the browsing history (temporary internet files), which I did with no effect. He also had me check for the correct starting page address, which was OK. He stated that they are aware of a problem and it is on their list. No indication of how far down that list though. His only cure was to use IE for now, which I was already doing. Perhaps he can tell me which cookies to remove.

Maybe you are looking for