Component materials incorrectly assigned to superior operation in process order

One of my manufacturing facilities is having a problem with components not printing on process order output.
In all cases, the master recipes themselves look fine when reviewed in C203.  The components are properly allocated to phases (not superior operations).  But when the process orders are generated, certain components are being assigned in the process orders themselves to the first superior operation, instead of to the phase that is indicated in the master recipe.  Here is an example.
Here is the master recipe operation information as seen in C203:
And here is the material assignment list as seen in C203.  Note that component material MM6030 is assigned to Phase 0035:
But when the process order is created, that same component material MM6030 is now assigned to superior operation 0001:
Here is some additional information that I was able to eke out of the folks at the manufacturing facility:
The operations in the master recipe did NOT originally contain operation 0001.  It was added to the recipe in C202 after the recipe was initially saved.
Component Material MM6030 was not originally part of the BOM.  It was added via C202 after the recipe was initially saved.  A different material was originally in its place, and was assigned to a different phase.  After the MM6030 was added to the BOM, the assignment field was blank, and the user assigned it to phase 0035.
Has anyone ever encountered a similar issue?  If so, how was it resolved?

Hi ,
Possibility  , in C202 , user may have changes the BOM first and re-assign the phase  but in process order level Read PP master did not call
Another possibility manually change the process order component and assign this in Phase in COR2 .Please check  whether it has been added manually in order level . 
Regards
JH

Similar Messages

  • Add component and Delete Operation in Process order Using COR2

    Hello,
    I need to update any process order (Add components in it and delete some operations of it) on the save of the process order.
    Transaction for change PO: COR2.
    I have found a badi to change in process order (WORKORDER_UPDATE) Method: BEFORE_UPDATE.
    But this badi has all the parameters as Importing. Hence we can not change them.
    If we use field symbols in this badi to change the values,will it make any other issues?
    I have also identified a user exit EXIT_SAPLCOBT_001 but this exit is called very late in the processing, and you cannot change data into that user exit ...check Note (86553 - Documentation on user exits).
    Kindly post your valuable comments and answers.
    Thanks in advance.
    Edited by: Nitin Nyati on Sep 1, 2010 1:09 PM

    Hi ,
    Possibility  , in C202 , user may have changes the BOM first and re-assign the phase  but in process order level Read PP master did not call
    Another possibility manually change the process order component and assign this in Phase in COR2 .Please check  whether it has been added manually in order level . 
    Regards
    JH

  • Scheduling issue for splitted operations in process order

    Hello All,
    I am facing problem after scheduling splitted operation in process order. The scenario is as follows.
    In process order there are 5 operations. 10, 20, 30, 40 and 50. Out of the above operations 30 is splitted and two different resources are assigned to it. Control key assigned to splitted operation (30) is also scheduling relevant. Now the flow of operations will be as below.
    1. Operation 10
    2. Operation 20
    3. Operation 30 - Operations is splitted (Resource used is A), qty to be produced - 10 kg.
    a. Operation 32 - Quantity of operation 32 is changed to 5 kg. Resource used is B.
    b. Operation 34 - Quantity of operation 34 is changed to 5 kg. Resource used is C.
    4. Operation 40
    5. Operation 50
    Relationship exists between opearion 10-20, 20-30, 40-50 and between 30,32, 34 with 40. But there is no relationship exists between splitted operations 32 and 34 with any of the previous operations for eg. 10 & 20.
    Issue is after scheduling all operations relationship remains maintained between operations 32, 34, 40 & 50. As operation 30 is splitted to two different operations equally total time for scheduling gets reduced but after scheduling of all operations all previous operations before operations 30 does not get resceduled? Scheduling type maintained for order is Backward Scheduling.
    Please check this and guide me how all operations before operation 30 can be rescheduled as per changed timing of operations 32 and 34.
    Best Regards.
    Edited by: Avinash Mohite on Mar 19, 2010 12:43 PM
    Edited by: Avinash Mohite on Mar 19, 2010 3:14 PM

    Hi,
    I hope u r doing in this way:
    In the capacity header screen enter individual capacity as 2. then click on Got( on top of same screen) and go to individual capacites. Enter the names of two individual capacities, for example 1 and 2. These are the names of two work centres where u r splitting ur operation.
    Double Click on operation 0030 and go to tab 'splitting' . Tick on ' required splitting' and enter maximum no. of splits as 2.Then go to capacity requirements assignment tab. enter the individual capacity as 1 and 2 and enter the splitted quanitites.Save and reschedule .
    Check and revert.
    Regards.

  • Custom exit or badi for changing the user fields in operation of process order

    Hi all
        I want to find a exit or badi to set default value to the user fields in operation of process order when COR1.
        I have tried exit 'PPCO0001', but this exit is call after commit work, so I can not change any thing
        I also tried to use badi 'workorder_update', 'before_update', but all parameters in this BADI are importing, can't be changed, I've tried to change it and then program dump.
        Do you have any solution for this question?
    Thanks

    Do a Implicit Enhancement at the PBO of this subscreen.

  • Phases/operation in process order does not exist

    phases/operation in process order does not exist  this error coming when cor6n is using.why?

    HI
    After creating Master recipe in C201, under the operations tab you need to define the operations involved in recipe . along with the operation column  there is phase indicator column is there which is to be selected whether this operation is phase or not...
    Check and revert
    Regards
    Anupam Sharma

  • Error:Assign handling Unit from one Process order to another process order

    Hi Experts,
    I am facing different issues in assigning handling unit from one process order to another.
    Business process:
    1. Two similar Process Orders are existing in the system
    2. Delivery is created for first process order using LP10 for one or more components
    3. TO is created in foreground using VL06P
    4. TO is confirmed by providing in stock available Handling Unit (HU) / storage Unit details Using LT12
    5. Customized transaction is used to reassign newly created HU (created in previous step) from first process order to second process order. As a result many steps are performed in background for delinking the HU from first process order to second process order (including creation of different TOs)
    I am facing different issues in the process:
    1. Sometimes while confirming the TO in step 4: error is received as "Reservation item 0065 with material 4013959300300 does not exist" OR "Reservation item with material does not exist"
    2. If the TO is confirmed in step 4. I am facing error in step 5 as "Warehouse number  does not exist (new selection required)"
    Both these errors are standard errors and I could not find much information on them in SCN also.
    If anyone can throw light on any of them then it would be great.
    Please let me know if any additional information is required.
    Thanks
    Harsh Aggarwal

    Hi Manish
    Thanks for your response. Actually, the customized program is used only in fifth step and not till TO confirmation so that error is not related to Customized program. However, in some cases I am able to do the confirmation but the error is received in 5th step i.e. Warehouse number  does not exist (new selection required)"
    Any further guidance you can provide. I will ask ABAP to check the customized program but the error seems to be a standard error.

  • Phase/operation  in process order 1000028 does not exist (please check entr

    Dear All
    Kindly help me out in the following scenario
    I am entering confirmation through COR6N, after selecting process order no. system is giving this error when i click on actual data. However there is only one phase and one operation in master recipe. Furthermore earlier I ran MRP, generated capacity requirements, converted planned order into process order, dispatched process order via CM22-leveling and now i am trying to enter phase confirmation.
    waiting for your response..
    Regards
    Navaid

    Hi,
    Please check your operation/phase control key in your recipe (C202), may be it will be PI07 (no confirmation).
    If yes, you can enter the phase number manually in COR6N
    Thanks,
    JK

  • Cost of materials Issued to be captured against a process order

    Dear Gurus,
    I Issue Some consumables for cleaning purpose before the start of an order. This consumables are Issued against manual reservations raised by production department. But We want the cost of these consumables to be billed to the process order batch (cost of the product). But I do not want to maintain thses materials in the BOM of the product.
    What is the best way to do it.
    Regards
    Sri.

    Dear
    User T.Code : MB1A and Movement Type : 261 and enter, then enter the production order and below you can enter teh mateirals that are to be issued. Once you post it the cost of the consumables are captured on this production order.
    While Creating a Reservation in MB21 your production people can create the reservation against the production order with the materials that are to be issued.
    Hope the above helps.
    Edited by: Addy on Apr 7, 2010 10:55 AM

  • Using Component scrap differently in MRP and in production/process orders

    Hello Gurus,
    We use Component scrap in our BOMs.
    MRP calculates the requirements including the scrap and that is fine. Is there a way that when we create production/process orders the components' required quantity will not include the scrap automatically? We don't want the components to be issued with the additional scrap, but rather issue the scrap by request only if required.
    Thanks

    Not possible.
    The SAP logic is tht procurement of RM and Production & consumption has to be in line. Functionally tht is ideal

  • Assigning Components to Operations in Maintenance Orders

    Dear Masters,
    I want to assign the component reservation to the operation number in the maintenance order (i.e., In a breakdown order if I reserve a material component it should ask me for the operation number to which I want to link it to). Can anybody help me with this?
    Please do help its a bit urgent. Thanks in advance.
    Chin2

    Hi Pushpa,
    Thanks for taking time to reply to my question. I thinking you might be laughing at this stupid question of mine but sometimes the mind stops working.
    Thanks once again.
    Chin2

  • Assigning mic in operations of production order for newly inserted oprt

    Hi, Please advise how to assign mic to the newly inserted operation of the prod order?i mean say 3 operations copied form master data. we added a 4th operation manully. i want to assign new inspection characterstics to the 4th opration. plese advse.

    Dear Raju
    1) Go to CA02
    2) go to header
    3) Maintain inspection Point as 150
    4) Maintain partial Lot Assign as partial lot assignment according to plant default
    5) At Operation level maintain a QM work center ( testing ) with Control key QM04 ( as per your requirement)
    6) double click on the control key and go to Quality Management : Inspection points
    7) Maintain Inspection point completion : Quantity , Valuation and confirmation ( as per your need , you can select other options also) press F1 and see the impact of each
    8) choose time related and keep Tfac 1 and Unit as HR ( As needed)
    9) You can select quantity - related also and then maintain the quantity.
    10) Select the QM operation and maintain in the MIC
    Regards
    Gajesh

  • How to analyse actual cost for each operation in Process/Production Order?

    Hi all,
    IN SAP, I know that we can analyze plan cost for Operation in Process Order/ Production Order.
    However, I can not analyze Actual cost for Operation .
    I know the object when I good issue material is ORDER, not OPERATION.
    But, as requirement of users, they want to analyze actual cost for each Operation.
    CAn SAP do this analyze?
    If Yes, What should I do in SAP to have this reports?
    THanks in advance,
    Emily Nguyen

    Hi Emily,
    as I see from one other message that you're using material ledger. Then your expectation is apparently to also see the actual costs of materials in your production order by operation.
    This is not supported. Actual material costs are handed up in material ledger multi-level settlement from one material to the next, bypassing the production orders.
    That means the production order will always contain the material costs valuated at plan price, not at actual price.
    For activity prices that might be better, when you revalue the orders at actual activity prices with CON2. But even there I am not sure that it will always be assigned correctly to the operations.
    There is currently an enhancement in development, the operation level costing. But that will affect more the planned cost side not the actuals. Might be interesting to learn more about your requirements and the use case behind.
    best regards,
                      Udo

  • Can we assign process order in MB21 RESEVATION for extra material

    Sir,
    in Production sometimes we required extra raw material but already we issues raw material against  process order then that time where we assign extra raw material in process order or where we check costing of extra material qnty aginst process order.
         can we asssign extra material against process order in MB21 with movement type 261

    Dear,
    It is not possible to create the manual reservation against the order for 261 movement type. Because system generate the automatic reservation for an order whcih can not be modified. Better you go for component or operation scarp to plan the extra requirement. MB21 you create the reservation with 311 movement here you give reference of an order also maintain the long text for same. By this you can transfer the extra consumption from main storage location to production storage location. And issue material against the order with MB1A 261 against the oder as unplanned consumption.
    Hope clear to you.
    Regards,
    R.Brahmankar

  • Adding Distribution KEY (GLEI) to a new Component at Process order Create

    Hello Experts.
    We have a Process Order where all components have the GLEI Distribution Key assigned.  FOr this particular Process order, our Scheduler routinely adds an additional Material Component (with a specific batch number to save operators from having to key in the batch number when reorting production).  The problem is, that when she adds this additional component, the Distribution Key field is greyed out so we cannot assign the GLEI key.  This causes the demand for that particular item to show on dates that dont work for us.  Should it be possible to manually assign the GLEI key to components at the Process Order create stage? 
    *Note, I have also tried adding the extra component at the Planned order stage, and while the screen allows me to enter all of the details (including Distribution key), when I save the Planned order, the new component does not get saved.
    Any help would be greatly appreciated.

    closing thread

  • Table/Structure for process order's auto batch determined component.

    Hi PP Gurus,
    We're struggling to get the Structure/Table name where data pertaining to process order component which is batch managed and automatically batch determined goes. We know RESB is the table where it gets updated after saving Process order. But we want the structure/table name before saving the Released Process order. Can anybody please help to get it?
    Thanks,
    Abu Arbab

    Abuarab,
    I think it will in structure CAUFVD. Following are the enchancements available as of ECC 6.0,
    PPCO0001  Application development: PP orders
    PPCO0002  Check exit for setting delete mark / deletion indicator
    PPCO0003  Check exit for order changes from sales order
    PPCO0004  Sort and processing exit: Mass processing orders
    PPCO0005  Storage location/backflushing when order is created
    PPCO0006  Enhancement to specify defaults for fields in order hea
    PPCO0007  Exit when saving production order
    PPCO0008  Enhancement in the adding and changing of components
    PPCO0009  Enhancement in goods movements for prod. process order
    PPCO0010  Enhancement in make-to-order production - Unit of measu
    PPCO0012  Production Order: Display/Change Order Header Data
    PPCO0013  Change priorities of selection crit. for batch determin
    PPCO0014  Select process orders for external relationships
    PPCO0015  Additional check for document links from BOMs
    PPCO0016  Additional check for document links from master data
    PPCO0017  Additional check for online processing of document link
    PPCO0018  Check for changes to production order header
    PPCO0019  Checks for changes to order operations
    PPCO0020  Process order: Display/change order header data
    PPCO0021  Release Control for Automatic Batch Determination
    PPCO0022  Determination of Production Memo
    PPCO0023  Checks Changes to Order Components
    Regards,
    Prasobh

Maybe you are looking for

  • Regular events in iCal

    Is there a way to create a list of items you regularly schedule in iCal?  For instance, I play tennis at different times on different days, but always for the same length of time.  I'd like to create an event "Tennis" which last for 1.5 hours which I

  • C6280 All-in-one driver for windows 8.1 - unalbe to select automatice 2 sided printing

    I downloaded and installed the driver and full photo print for my old all-in-one but now I don't have the option for automatice two-sided printing.  Is there a different driver specifically for the C6280 printer I can download? pennyph

  • Include the option to receive automatic notifications by email

    Great updates made to the new version of Acrobat.com! I would love to see the addition of automatic email notifications as an option when participating in a collaborative project on Acrobat.com. For example, if I am reviewing a design proof in CS Rev

  • Can't see how to access my iTunes wish list on my iPhone?

    Hi, Is there any way to access my iTunes wish list on my iPhone? The advice I've found so far is to look for a 'quick link' which is accessible from a home icon but I can't see any home icon in iTunes on my iPhone?

  • Using Sales Forecast packaged application

    Hi, i wish to use the sales forecast packaged application but, trying with different users all the users see the same data, i mean the Sales Rep A see the selling cycle of Sales rep B. Since the manager is right to be able to look to Rep's opportunit