Compute manufacturing lead time

Pls tell the detailed computing lead time in oracel.
Thandks

If you run MRP with "lead time scheduling" (instead of "basic dates"), it will schedule the order by the routing, and let you know the planned workload for each WC in advance.

Similar Messages

  • Manufacturing Lead time, milestone operation wise

    Good Evening to All !
    I have a scenario. I am explaining this scenario through 1 example.
    We have a material 'X'. Inhouse production time for this material is 6 days, which is maintained in MRP2 view.
    Now in Routing of this material 'X' there are total 10 operations starts from 1 to 10. Operation No. '4' & Operation No. '10' are milestone operation. The workcenter for both milestone operations are different. Now in house production time which I maintained in material master is total lead time for material 'X'.
    The requirement is:  Workcenter of Operation "4 "wants to know on daily basis that what quantity should be delivered from their workcenter.
    Now my question is that can I maintain this lead time(6 days) in 2 parts as:
    Till operation "4" my lead time is 5 days &
    From operation "5" to Operation 10 lead time is 1 day.
    Please suggest all possible solutions.
    Can APO help in this scenario.
    Thanks in Advance.

    If you run MRP with "lead time scheduling" (instead of "basic dates"), it will schedule the order by the routing, and let you know the planned workload for each WC in advance.

  • Difference between Compute lead time and Rool up lead time

    Hi All,
    Could you please clarify what is difference between Compute Lead time and Roll up lead time.
    I see in Routing > Tools.
    Thanks in Advance
    Regards
    Ravi

    Refer The Oracle document
    Manufacturing Lead Time Computations
    Manufacturing Lead Time Computations (Oracle Bills of Material Help)
    Rolling Up Cumulative Lead Times
    Rolling Up Cumulative Lead Times (Oracle Bills of Material Help)

  • WO scheduling based on lead times defined in item attribute

    I wanted WIP to consider the fixed & variable lead times specified for the item - where I am not rolling up mfg lead times using BOM.
    Has anyone been able to automatically schedule WO start date based on the lead times inputted in Item attribute.
    null

    Dear Bimal,
    The manufacturing lead times (setup and operation) are resource specific, and to declare them at item lead time attribute level is not practical (you need to define too many item levels in BOM to reflect every manufacturing step). The other work around is when routing is defined, you define two resource steps for each resource and make the first step lot basis and give setup time as usage rate and the second step item basis and operation time as usage rate. This gets reflected in manufacturing scheduling irrespective of quantity limitation (to define lead time at item level you need to define lot size also). I hope this takes care of your needs.

  • Lead Time for manufacturing and its corresponding Quantity in Material Mast

    Hi all ,
    Do we have any feilds in SAP Material Master
    which are useful for
    1) Lead Time for manufacturing
    2) Manfactured Lead Time Quantity
    if the mateials are produced inhouse.
    thanks
    ksr

    Dear,
    There are no such a fields in material master, But in MRP 3 view you will get theotal replenishment lead time field.
    Which use for the produced in-house if the replenishment lead time is included in the availability check:
    This is nothing but the  in-house production time and, if available, the goods receipt processing time.
    Also refer this link to calculate the in-house production time correctly,
    Total Manufacturing time for assembly
    Regards,
    R.Brahmankar

  • Lead Time for Purchasing Material & Manufacturing Material

    The query is related to the process of Material Requisition planning.
    I need to know from where exactly the system picks up the lead time for generating Purchase requistions?
    - For purchased material (lead time from placing order to actual recipt of material, time needed for QC checking till its release)
    - For own manufactured material (lead time at each work center in the recipe along with actual time required for a particular process)

    Hi
    for your information for  any material the data for the lead time comes from the material master
    http://help.sap.com/saphelp_46c/helpdata/en/fd/45b7ee9d6411d189b60000e829fbbd/frameset.htm
    if you click on the link you can get the entire process.
    as you can see SAP picks up the deatil from the MRP2 view of the material master.
    hope this  is helpful.
    regards
    Vignesh.

  • How to store lead-time and price per MPN for a single Item

    We are probably one of the only CEM's that use Oracle Applications in a one-to-one MPN-IPN (Oracle Item Part Number) relationship. We do not currently store multiple Manufacturers under a single Item. Rather, we use the Customer Item Cross Reference to rank the customer's AML, with each IPN tied to a single MPN.
    We are looking at moving into a one-to-many "world" in Oracle but are not sure how we can handle different pricing, lead-time, preference, status (prototype, production, obsolete, do not use), etc. for each Manufacturer's Part Number under a single Item. How are other CM's handling this???

    Hi Greg,
    Unfortunately, DIAdem Datafinder doesn't really support much in the way
    of Date/Time search outside of the File Level Creation Date property.
    In order to make the creation time of the Channels searchable you would
    want to create some custom properties (or use the existing RegisterInt1
    - RegisterInt6) to define your own searchable properties.
    For example, since you know that you have one TDM file per day, you can
    start your search by find the desired day on the File Property Level,
    searching the "Creation Date" property. When you store your TDM
    properties, you could store the hour creation as an integer (and
    thereby searchable) in one of the RegisterInt properties of the
    channel, or create your own custom "Hour" channel. You could similarly
    save the minute and second property in their own custom properties.
    Then, since you're saving integer values, you can then search those
    values to determine the time that the channel was created.
    I realize that this isn't ideal or elegant, as in total it requires 4
    searches (date, hour, minute, second). But that is the most
    straightforward way of searching your channels by creation date/time.
    Hope this helps Greg, let me know if you have any other questions.
    Dan Weiland

  • Lead time reffering to open SO- - -***** URGENT ***

    Hello
    When we create a brand new PO, the materials due date should be automatically
    calculated using the  materials standard Lead Time.  For example, if we are to create a PO on 10/1/07 for a part that has standard Lead Time 65 days, the materials due date shouldbe automatically calculated as 10/1/07 + 65 days = 12/5/07 and the PO shouldshow that the part's statistical due date and delivery date is 12/5/07.However, recently SAP has been checking a pending sales order's furthest duedate and stretch the PO's due date to match the sales order's due date.  Forexample, in the previous example the PO's due date should be 12/5/07 but if there is a sales order that is not due till 3/7/08, SAP calculates that the part
    on this PO is not due till 3/6/08.  This new function is affecting our PO
    creation and its due date.  Could you advice so that POs automatically use a
    part's standard LT to calculate the part's due date instead of using SO's due
    date?
    I checked planned delivery time in MMR ,INFO RECS,VENDOR Checked the availability check and checking rules what could be the reason...?????
    Will AWARD FULL POINTS URGENT

    If you used a remove personal settings option from Windows or Firefox,you may well have permanently lost those bookmarks.
    * Undelete<br>If you did that then timely use of a file undelete utility and a good helping of luck are likely to be required to attempt recovery (probably best to stop using
    the computer entirely, until you have such utility).
    *Your Own Backups<br>You could have a backup system in place that backs up such files or the firefox profile, and you may be able to use that.
    * Synced to another machine<br> you may have the bookmarks synced on another machine, or even on an external server
    **see [[what is firefox sync?]]
    See also [[lost bookmarks]] but I am not sure any of that applies in this case, it is worth reading it though
    Normally

  • Lead time for Purchase items

    I had read that Lead time for Purchased items is calculated per 7 working days / week, by default. However, when I checked this, I found that the MRP planned orders were always considering our mfg calendar that has 5 working days / week.
    Anyone tried this.

    Industries & Product which have stabilsed have the same measuring yard and standards. This is also applicable for calendar working days, otherwise we need to device the 'interface' because the results would be weird, specifically when we speak of 'supply chain'.
    <BLOCKQUOTE><font size="1" face="Verdana, Arial">quote:</font><HR>Originally posted by erik anthonsen ([email protected]):
    this is correct. it is up to individuals to change the amount of days that the company manufactures as their standard. if your facility is running 7 days a week-----use 7 days at setup<HR></BLOCKQUOTE>
    null

  • Lead time

    Dear friends,
    Is there any report in SAP LE which can give the total lead time for delivery of materials from the plants to the destinations(customer)
    Your valuable reply is highly appreciated.
    Regards,
    Sampath

    Sampath,
    I am not aware of such a report.
    The duration of time scheduled in a Sales order between the shipping point and the destination is carried in the Sales routes (configuration transaction OVTC).  The routes that your company uses can be determined in a number of ways.  Information (including duration) can be seen in Table TVRO.  Information concerning determination (which route is associated with a source-destination pair) are usually contained in table TROLZ.  This configuration is in IMG>SD>Basic Functions>Routes>Route Determination>Maintain Route Determination. 
    If you actually interested in the 'lead time', which also includes manufacturing/procurement time, Pick/Pack Processing time, etc, this is a bigger task.  More data needs to collected.
    In either case, I believe you will have to commission your ABAPers to create a Z report.
    Regards,
    DB49

  • How to influence lead time from vendors

    Hi All,
    I am trying to figure out how I can consider the impact of the Chinese New Year on the lead times of finished goods manufactured in China and sent to plants in the USA. I set up a special data range to account for this in the Calendar which was then assigned to the Time Stream ID.
    My initial thought was to assign the Time Stream ID to the Shipping Calendar at the Vendor location (location master) but this does not seem to have made an impact on the lead time. I also tried using the Production Calendar, but this was also without success.
    Does any have any recommendations that would assist me here.
    Kind Regards,
    Paul

    Hi Paul,
    If you are using APO PPDS means production planning heuristics from PPDS Scheduling will be done based on Planned delivery time in external procurement relationship. Planned deliver time will be considered based on production calender mentioned at vendor location.
    You may be facing problem because transfer to R/3/ ECC will consider planned delivery time in calender days. Check your setting in CIF that you are not retransfering planning results from ECC back to APO.
    For more information go through below link
    http://help.sap.com/saphelp_scm50/helpdata/en/cd/6dec39554c7f58e10000000a11402f/frameset.htm.
    Hope this helps.
    Regards,
    Santosh

  • Total replenish lead time

    Hi gurus,
    anyone can explain why this field (total replenish lead time) is designed to enter manually instead of system automatically calculate from BOM for a manufactured part? and how does it work according to the following scenario:
    product X is produced in plant=1000 from material A and B (both A and B are procured externally for plant 1000, to simplify the case)
    in plant 1000, PO processing time=1day
    A: planned del.time=3 days, GR. processing time=1 day.
    B: planned del.time=5 days, GR. processing time=1 day.
    to make X need 2 operation: 1st operation need 1 day to assemble A and B together, after assembling, 2nd operation need 1 day to paint, 1 day to dry
    what's the total replenish lead time we should enter for X?
    thanks,
    cookie

    Dear Cookie
    3.if it's only for availability check, does that mean the MRP would not be affected by this field, then what would be the lead time feed into MRP? what's the relationship between MRP and availability check? why they use 2 different sets of data?
    1) MRP will not take this field into Account for Calculating Dates
    2) MRP for in-house materials - in-house production time & GR Procesing time ( Lead time )
    3 ) For external Procured materials - PR processing time , Planned delevery time & GR Processing time
    4) MRP Net Req. Calculation Concept is different from Availbility check Concept
    Regards
    Madhu

  • View of lead time of product in APO

    In R/3 under transaction C203 we view the time required for different operations to manufacture a product.
    Where in APO does the inidividual operations time appear in APO. Specially the leadtime.
    Regards,
    Chetan

    Hi Siva,
    Thanks for your reply. but that data is maintained in R/3 Material master in MRP2 view.
    my question is related to production lead time maintained in transation C202 in R/3
    Regards,
    Chetan

  • Reg: lot size and replenishment lead time

    1. please explain about lot size and replenishment lead time.
    2. please also explain about consumption based planing and in steps explain how to perform manual and automatic reorder point(transc code please)

    You use the lot-sizing procedure to determine how the system is to calculate the reorder quantity in the planning run.                                                                               
    A lot size defining the lot-sizing procedure is assigned to every material master record applicable to materials planning.                                                                               
    The lot size is defined in Customizing by the combination of the lot-sizing procedure and the lot-sizing indicator.                                                                               
    Three procedures for lot sizing are available:                                           
    o  static lot-sizing procedures                                                          
    o  period lot-sizing procedures                                                          
    o  optimizing lot-sizing procedures                                                                               
    You use the lot-size indicator to define the procedure.                                                                               
    The following parameters are also available for controlling the lot-sizing procedure:                                                                    
    o  Short-term and long-term lot size                                                     
       You can split the lot-sizing procedure into a short-term and a long-term period. This means that you can select one lot-sizing procedure in the near future and a different one in the distant future.                                                                               
    You define the periods in the section of the screen entitled "End of the short-term period/start of the long-term period".                                 
       The valid from date of the long-term lot size area is defined via:                    
       -  a periodicity                                                                      
       -  a number of periods                                                                
       The beginning of the long-term period is calculated by taking today's date and adding the number of periods in the future; the long-term planning period then starts on the next complete period.                              
       Note                                                                               
    For materials that are planned using the short and long-term lot size,                
       it is recommended that you define a maximum MRP period. Defining the                  
       MRP period has the effect that materials after a certain period are                   
       included in planning even if no changes relevant to the planning run                  
       have occurred. This avoids a situation where order proposals created                  
       with the long-term lot size move into the short-term period because no                
       changes relevant to MRP have occurred for the material.                               
       You define the maximum MRP period in the step, "Define maximum MRP                    
       period". A material that is planned on a regular basis should also be                 
       provided with an MRP type that contains the indicator for regular MRP.                
    o  Scheduling indicator                                                                  
       For period lot sizes, you can use the indicator for scheduling to                     
       determine whether the availability date;                                              
    o  is to be set to the first requirements date in the period                             
    o  or is to be set to the beginning of the period                                        
    o  is to be set to the end of the period                                                 
    o  or whether the period start represents the beginning of the planned                   
       order and the period end represents the availability date (repetitive                                                                               
    manufacturing)                                                        
      Interpretation of the delivery times                                  
      For the lot-sizing procedure, you can also define whether the period  
      start is to be interpreted as the delivery date or as the availability
      date using the indicator, "interpretation of the calendar times".     
      NOTE                                                                  
      The indicators, Scheduling and Interpr.deliv.times are mutually       
      exclusive.                                                            
      Indicator for the splitting quota                                     
      For the quota arrangements, you can determine whether the requirements
      quantities are to be distributed to several items, that is, whether   
      they are to be split. With the splitting quota arrangement,           
      requirement quantities are not simply allocated to the smallest quota 
      rating. Instead, they are distributed among various sources using the 
      following formula:                                                    
      Quantity for source of supply X = Quota of source X * reqmts quantity                                                                               
    Sum of all quotas          
      Overlapping indicator                                                 
      The overlapping indicator along with the cycle time in the material   
      master record are used to split the planned orders into several       
      partial quantities whereby the in-house production time overlaps by   
      the cycle time.                                                       
      Lot-sizing procedure for make-to-order production                     
      In make-to-order production, you can use the indicator, Lot size for  
      make-to-order production to determine whether,                        
      the order quantity is to be calculated using the exact lot size       
      the order quantity is to be calculated using the exact lot size and   
      the system is also to take the rounding quantity or the minimum and   
      maximum lot size into account                                         
      the order quantity is to be calculated using the lot-sizing procedure 
      defined for the short-term area                                       
      Maximum stock level variant                                           
      The system only displays the Maximum stock level variant field in the 
      lot-sizing procedure, Replenishing to maximum stock level. The        
      indicator only has an effect in connection with reorder point planning
      taking external requirements into account and in connection with      
      material requirements planning and controls how the system calculates 
      lot sizes.

  • Lead time and Route time estimation used for deliveries

    Dear Friends,
    Can anybadyu let us know how to estimate lead time and route times for deliveries, and what is the exact meaning of the these two with differences
    if possible can you please give me the configuration steps, as i know at this movement route times are maintained in the route and lead times are maintained in the material master MRP view.
    what was these field impacts in the delivery..
    requesting your view as soon as possible
    Thanks
    raju.

    Hi there,
    Lead time is the time in which the material will be available. It is called Replenishment lead time RLT. It is maintained in MRP view of material master. RLT can either be inhouse processing time for inhouse manufactured goods or order time + goods receipt processing time for externally procured goods.
    Whereas time mentioned in route is used to calculate transit time during delivery scheduling. That is the time taken for the goods to reach customer from shipping point.
    Both the times are imp for delivery scheduling.
    When the customer places an order, if the material is not available, then the system will take end of RLT as material availability date. From that date, it will carry forward scheduling & propose a new confirmed delivery date.
    Regards,
    Sivanand

Maybe you are looking for