Configurable Material and Super BOM

Hi All !
Can anybody help me out to construct a Super BOM (starting from pre-requisites) to be done from Material master for the same.
Regards,
Srinivasan

Use Material Type KMAT only for the Configurable material and not for all the comps.
Following are the steps for creating varient configuration.
1 Create a material master
Material type: KMAT (or) check the indicator material is configurable in Basic Data 2
2 Create Characteristic (CT04)
3 Create Class (CL02) class type 300 (variant) & assign the characteristic to the class
4 Assign this class in the Classification view of the material master & save the material.
5 Create a configurable profile (CU41) for the material
6.Basic data 1: Gen Itm cat grp (0002) configuration
7Now while creating the super BOM, use the same Tcode CS01, in the item categary enter 200 and the item details assign it to the KMAT.
If you can send yr mail ID I can send you the file on CAMSHOW.
Regds,
Umesh

Similar Messages

  • Difference between varient configuration and super bom

    hi gurus
    i want to know the difference between varient configuration and super bom??
    i think as per my knowledge it is same.
    but my friend says  both are different.
    award points
    enjoy

    hi,
    Variant Configuration : You do not need to create a separate material for each variant of a product in your company. You can use one configurable material to cover all variants. You create a super BOM and a super routing for this material, containing all the components and operations for producing all variants of the product.
    Super BOM : The bill of material (BOM) of a configurable material contains all the components that are required to manufacture the material. The BOM contains components that are only used in specific variants (variant parts), as well as components that are used in all variants (non-variable parts).
    <b>This is why BOMs for configurable materials are known as super BOMs.</b>
    Thanks
    Sadhu Kishore

  • Product costing configuration material   and study material

    Hi all,
    Can any one pass me the Product costing configuration material and study material email id is [email protected]
    thanks in advance
    Regards
    vijay
    Edited by: vijay matlani on May 11, 2008 11:17 AM

    hi
    Product costing documentation
    http://www.sap-topjobs.com/SpecialPP/746.html
    nagesh

  • How to set up the inspection plan for the material in super BOM

    Hello,
    how to get the accurate inspection plan of the IQC for the material which was class item in a super BOM?
    I've gotten the characteristic value from the sales order, and get the PO after MPR. The problem is how to specify the target value and the range of inspection characteristic in inspection plan, because the value is temporary?
    Thanks!
    Lin

    Hello,
    I think you need to create MIC which linked with the configuration characteristic, and specify "inspection by configuration" for the inspection type.
    then the configuration value in the sales order can be transfered to the inspection lot when production released or goods receipts if you use inspection type 03 or 04. that means the value range for the MIC will be determined dynamically for each sales order.
    Regards, Winnie

  • Inventory maintenance for Configurable Material and their Variants.

    Hi Gurus,
    Can anybody help me as how to handle the following issues?
    1. inventory maintenance for configurable material
    2. variants stock position maintenance (should it be maintained seperately from configurable material?)
    3. what about single values and multiple values components stock position?
    Regards,
    Sada

    Hi,
    Thanks for your reply.
    my query is say for example there is a material called XXX.
    for this material the stock position is now 1000 units in warehouse. that is ok
    if the above "XXX" is a configurable material, it might be having chars (say as additional components upto 10, which may be required by customers some times and no some times).  If we maintain stock position for material XXX then what about components.  because it is not always fixed and asked by the customers.  customer may ask all components or some components. 
    Ex:  Car is material.
           A/C, Luggage carrier on the top, tool kit these are characteristcs.
    I hope you understand me.
    Regards,
    Aanand

  • Configurable material and project material cost

    Dear all,
    could you help me on the following question?
    we need to calculate the configurable material cost in the projcet.
    the costing varaint is to get the info record of the materials.
    but now the problem is when i use cn33 to assign the materials to the activity, the planned cost is only the material cost shown in the projcet. we cannot get cost of the bottom materials.
    how can i solve this problem, to get the planned cost,just as what we can get in the sales order (VA01)cost planning?
    thanks a lot.
    Judy

    can anyone help me or give me some hints on what to do?
    thanks a lot.

  • BOM explosion in sales order for configurable materials and variants

    Hi,
    I have these materials:
    A: configurable material (header)
    B: variant material (header)
    C: configurable material 1 (position)
    D: configurable material 2 (position)
    E:variant material 1 (position)
    F:variant material 2 (position)
    I can in the sales order explode in this way the BOM (using SD01 application in the position type of the header material):
    1) A --> C+D
    2) B --> E+F
    while I can't make the explosion in this way: A --> EF and A --> CE
    is this possibile? I want to make an explosion of a BOM for a configurable material  and having variants material as sons, or having mix sons (one configurable and one variant)
    Thank you
    Sandra

    Hi Sandara,
    Just check the BOM in cs03 u have maintained !!! If u have maintain the variant material there in the config mat BOM with object dependencies than u can explode !!!!
    Please let me knwo if u any query and also if u elabore more than will help u out

  • Super BOM in Variant configuration

    Hi SAP gurus,
    Can anyone tell me the difference between Variant configuration and Super BOM, if possible with an example.
    And also please forward any information on configuring the Super BOM.
    Thanks & regards,
    Praveen Kumar,
    [email protected]

    Hi,
      For super BOM u need to do do the following configurartion settings.
    1. For Min item pricing go to VOV7 and select TAQ , go to structure scope and keep B(Explode Multi BOM)
    2. then go to v0v4 do the settings
             OR ERLA TAQ
             OR NORM TAQ  TAE
             OR NORM  TAE   TAE
    3. Maintain the records in CS01.
    Regards,
    Sree

  • Super BOM for not KMAT materials

    Hi Gurus
    I have a client requirement to maintain the BOM for finished product as a Super BOM even though the material is not KMAT material. Super BOM has got KIT materials. Based on this customer requirement only certain materials which goes in to finished product are get selected and should check the availbility of those components and it should create a planned orders and purchase reqn After MRP run.
    My question is how the KIT materials are maintained in BOM?
    how the materials get selected while creating a Sales order w/o usinf Variant configuration?
    Does all the super BOM materials get consumed after the production confirmation?
    Quantum.

    Hi,
    What do you mean by KIT materials.
    By the way you can still maintain material as Configurable w/o selecting material type as KMAT.
    Just you need to do is select material type  FERT / HALB as applicable and then maintain material is configurable check box ticked in Basic Data 2 View in material master.
    Pls revert with more details.
    Regards,
    Tejas

  • Creation of Sale Order for configurable material with availability check.

    Hi,
    We have a scenario in which the material is configurable. The configurable material (X) has few variants (Ex: X1, X2, X3, X4, X5). While booking the sale order, we use the material number (X).
    Further, the material planning is done for the variants X1, X2, X3, X4, X5. The standard variants are planned for production in advance.
    1.     While booking the sale order, we want the availability check of the stock (type matching to happen). What needs to be done in configuration?
    2.     While booking the sale order, there is a possibility that the configuration selected will not match with any of the standard variants due to some additional requirements of the optional features, in such cases how to link the standard variants to the sale order & create requirement for additional requirements.
    Regards,
    Umesh

    Hi Umesh,
               1.Create material master for configurable material and variants in mm01.
               2.Maintain BOM for the configurable material in CS01
               3. Configur the variant configuration steps
                  a. Create charecteristics T.code CT04
                  b. Create values and assign classes
                  c. assign the values to charecteristics
                  d . Maitain dependence  T.code CU01
                  e.create configuration profile t.code CU41
                  f.stimulate the configuration profile.
    4. Do the availability check configuration through this path
    IMG --> Sales and distribution > Basic functions ,> Availabilty check and Transfer of requirements.
    5. Maintain the Availbility check field and MRP views in the material masters other wise you sit with PP people and do that
    I hope it will help you
    Regards,
    Murali.

  • Material variant replacement in sales order for Configurable Material

    HI
    I am using variant configuration. In this i have created material A as configurable material and have Preconfigured Material B as its variant by assigning configurable material in MRP 3 view.
    Now when i am creating Order for material A i.e. Configurable material and the characteristics values are same as that of Preconfigured material system is not replacing Configurable material with Preconfigured material.
    Please help me out.
    Regards,
    Anand.

    Even after maintaining the item category MTAC(Mills Make to order config at mat level), the configurable material is not getting replaced in the sales order (va02). It is just showing material variant exists for the configurable material.
    The setting in item category for configuration is.
    Config. Strategy     01(Sales Order Strategy (TAC, TAM))
    Mat. Variant Action  4 (Replace configurable material (Append and change))
    ATP material variant 2 (Do not substitute if not completely available)
    Structure scope      D (Configuration, poss. with BOM explosion)
    I have maintained the stock for material variant as well to take care of ATP material varinat setting shown above.
    Please suggest if missing something.

  • Configurable material  with make to stock

    Hi,
      My scenario is like  final products Distemper red 1kg, distemper  red 5kg and 10kg like this.But  Sales order will be Distemper red  1000kg.Based upon the availability of stock customer will get 5kg,10kg Depending upon the pack, price also differs depends upon the pack.
    In RG1 register they are updating only Distemper red total stock.
    If i go for variant configuration i should create distemper as variant and all finished material as normal and variant should be assigned(distemper red) in mrp 3 view.
    Moreover planning also done for only distemper red while packing they will go for different quantity.
    For Configurable material PIR can't be done.
    So how to proceed further, what about RG1 resister it should not update all pack wise only distemper red total quantity.
    Regards,
    S.Suresh.

    Hi,
    As BNR said you need to work with Material Variants for having Variant Configuration with Make to Stock.
    Pls. find the helpful details for maintaining Material Variants :
    Maintaining Material Master Records for Variants
    Prerequisites
    A configurable material exists, for which you create a material variant. The configurable material
    has all the necessary settings in the configuration profile, class assignment, dependencies, and
    so on.
    Procedure
    1. From the material master menu, choose Material   Create general   Immediately.
    Enter a material number, an industry sector, and a material type for materials kept in
    stock.
    You must process the following views:
    Basic Data*
    Sales Data*
    MRP Data*
    For material variants, you maintain the usual material master data, such as
    availability check, strategy groups, and so on. This documentation describes the data
    that you need to maintain specifically for material variants.
    2. Maintain the required basic data.
    Do not select Material is configurable for a material variant.
    In the basic data, you can link the material variant to a configurable material. This
    configuration applies to all plants. To manufacture the material variant in-house, you
    must maintain the variant at plant level, so that BOMs, routings, and so on can be
    determined. Cross-plant variants can be used in Purchasing, but are not supported in
    Sales.
    3. Maintain the sales data.
    You can only use the variant in sales orders if you maintain sales data for the variant.
    4. In the MRP data, enter a configurable material for configuring the variant at plant level.
    5. Choose Configure variant.
    You see the value assignment screen with the characteristics of the configurable
    material.
    Configure the variant.
    6. Once you have maintained all the data, save your material variant.
    Bill of Material (BOM)
    To do a requirements explosion for a configured material, you must maintain the data in the
    material master record and link a BOM to the configured material.
    If the material of the material variant is the same as the configurable material, the link
    is already there.
    You can either create a BOM especially for the configured material (perhaps using the copy from
    function) or allocate the configured material to the BOM for the configurable product. The second
    option is the more common solution.
    If you allocate the configured material to the BOM for the configurable product, the BOM for the
    configurable product is interpreted and exploded according to the characteristic values assigned.
    The interpretation includes the processing of selection conditions and the setting of field values in
    BOM items according to the relevant actions.
    Allocating a Configured Material to a BOM
    To allocate the configured material to the BOM of the configurable product, proceed as follows:
    1. From the bills of material menu, choose Bills of material   Material BOM   Alloc. config.
    mat.   Create.
    2. Enter the name of your configured material in the Material field.
    You see a screen on which your configured material is shown as the first allocation.
    Select the allocation and choose the All allocs for BOM function to see all the materials
    allocated to this BOM.
    3. Save your allocation.
    Task List
    To produce a configured material, you need to allocate a task list to the configurable material
    once you have created the material master.
    If the material of the material variant is the same as the configurable material, the link
    is already there.
    You can either create a task list especially for the configured material (perhaps using the copy
    from function) or allocate the configured material to the task list for the configurable product in the
    task list maintenance function. The second option is the more common solution. If you allocate
    the configured material to the task list for the configurable product, the task list for the
    configurable product is interpreted and exploded in the production order according to the
    characteristic values assigned. The interpretation includes the processing of selection conditions
    in the operations or activities, sub-operations, sequences of operations, and production
    resources/tools (PRTs).
    Allocating a Task List to a Configured Material
    To allocate the configured material to the task list of the configurable material, proceed as
    follows:
    1. From the routings menu, choose Routings   Routing   Change.
    2. Enter the number of the configurable material.
    3. Choose Goto   Overview.
    4. Choose Routing   Material allocation   New entries and enter the number of the
    configured material you want to allocate to the task list.
    5. Save your allocation.
    Creating Cross-Plant Material Variants
    Use
    For material variants that are procured externally, you can define the assignment to a
    configurable material in the basic data of the material master, because no plant-specific data
    needs to be determined for these variants.
    Procedure
    1. In the material master menu, choose Material   Create (General)   Immediately.
    Enter a material number, an industry sector, and a material type for materials kept in
    stock.
    Select the views that you want to process.
    2. Maintain the required basic data.
    Do not select Material is configurable for a material variant.
    3. Under Client-specific configuration, enter the configurable material of which you are
    creating a variant.
    4. Choose Configure variant.
    You see the value assignment screen with the characteristics of the configurable
    material.
    Configure the variant.
    5. Once you have maintained all the data, save your material variant.
    Result
    The variant can be entered in a purchase order. The configuration of the variant is copied from
    the material master.
    Cross-plant material variants can be used in Purchasing. However, they are not
    supported in Sales.
    Strategies for Variants
    Definition
    Low Variance
    This section describes how to plan products that have a practical limited number of possible
    combinations of characteristics and characteristic values. Technically speaking this section
    describes the use of variants to sell configurable materials.
    Variants can be used to facilitate the work with configurable materials. Variants of a configurable
    material are, for example, defined to prefabricate frequently required configurations and place
    them in stock, which is why variants were formerly called stockable types.
    For some configurable materials, it may be difficult to determine the variants of a configurable
    material. To use the strategies for variants effectively you must have an estimate of future
    consumption for each variant.
    If the configuration is not changed during the Sales Order stage, production can occur at the
    Production Before Sales Order stage. Then the customers must purchase the variants as they
    are or as they were planned. The benefit is that the products can be shipped immediately to the
    customers, if they are in stock.
    Make to Stock Production for Variants
    Variants can be planned on the finished product level using any make-to-stock strategy, such as
    Planning with Final Assembly (40)  or Net Requirements Planning (10)
    The planning of variants with make-to-stock strategies combines the advantages of make-tostock
    production (very short delivery time) with the advantages of variant configuration (one BOM
    and one routing for a whole product family).
    Make to Order Production for Variants
    Variants can be planned on the finished product level using any make-to-order strategy, such as
    Planning w/o Final Assembly (50) or Planning with a Planning Material (60)
    The planning of variants with make-to-order strategies combines the advantages of make-toorder
    production (planning without final assembly or cost tracking on the sales order level) with
    the advantages of variant configuration (one BOM and one routing for a whole product family).
    Integration
    Hope this helps.
    Regards,
    Tejas

  • Problem creating a sales order for configurable material in SAP ECC

    I have a Variant Configurable material named X.
    The structure of this VC material is
    Material X has charatcertics CHARCTERISTIC1 and CHARCTERISTIC2.
    CHARCTERISTIC1 has values VALUE1
    CHARCTERISTIC2 has values VALUE2
    I created a sales order manually from VA01 using configurable material and read the values of all configuration tables to be filled from BAPISDORDER_GETDETAILEDLIST. With the help of this data i got an idea how to fill the tables of BAPI BAPI_SALESORDER_CREATEFROMDAT2. But still i am able to create a sales order but the configuration data that i give is not getting populated in the sales order.
    Where am i missing. please some body suggest. I am unable to debug and searched the forums
    for this information but dint find solution for my problem. some body please tell me where am i missing?
    Any help would be highly appreciated
    Edited by: jessica sam on Jan 12, 2009 2:59 PM

    Even after maintaining the item category MTAC(Mills Make to order config at mat level), the configurable material is not getting replaced in the sales order (va02). It is just showing material variant exists for the configurable material.
    The setting in item category for configuration is.
    Config. Strategy     01(Sales Order Strategy (TAC, TAM))
    Mat. Variant Action  4 (Replace configurable material (Append and change))
    ATP material variant 2 (Do not substitute if not completely available)
    Structure scope      D (Configuration, poss. with BOM explosion)
    I have maintained the stock for material variant as well to take care of ATP material varinat setting shown above.
    Please suggest if missing something.

  • Problem while creating PO from SO for a Variant configurable material

    Hi
    i am facing a problem when i am creating a Purchse order from a Sales order.
    the material is a variant configurable material and we are creating a Sales order in Future date say in june.
    For one of the materials in the SO the configuration is different today and the configuration is different in June.
    Today the BOM contains different materials and in june there is a different bom for the material.
    and according to my understanding the BOM gets exploded on the basis on the delivery date in SO.
    here on the basis of the config which is valid in june materials are getting picked and that is correct.
    when i try to creat a PO out of that SO i could see that the BOM gets exploded and   correct materials are picked but i get the error message that inforecord for one of the componentes is not there.
    but that component is not getting selected in the config..and it is not there in BOM in june.
    It is there in the BOM today but not in JUNE.
    I dont understand why the system is refering to that componeent and throwing this error
    please help
    Thanks & Regards
    sarika

    You may try creating two BOMs  -- one speicfic to the date of order.
    Sanjeev

  • How to do the Partial delivery for configurable material ?

    Hi All,
    I am creating a sales order  for a configurable material and is trying to do the partial delivery for the same. But, after the outbound delivery the status of the sales order is shown as completed although I have done the partial delivery.
    Here are the steps I followed.
    1. material I used here is a configurable material.
        Main settings.
      a. In Basic Data tab, marked as configurable
      b. Procurement type='E' in MRP 2 tab
      c. Strategy group as 82 in MRP 3 view.
    2. I created a sales order for quantity 10
    3. Created a production order followed by goods Movement thereby increasing the stock.
    4. Did the outbound delivery for  quantity 5.
    Now if I checked for the status of the sales order using VA02, the status for the line item as well as for the sales order was "Completed" although I had done partial delivery.
    I have checked for setting in Customer master record, item category in VOV7. Everything seems to be fine.
    I checked for all the information in the FORUM without any help.
    Can you please help me?
    Kind Regards,
    Anupama

    Hi,
    For Info, I am creating a sales order for Item category TAC.
    1. In my case, after completing the partial delivery, in the document flow for Order, the status is shown as completed.
    2. In status overview for this item, delivery status indicator is set as  'Fully delivered'.
    I did check in the customer master record and the field
    Partial delivery per item  is set to Blank(  Partial delivery allowed)                
    3. I did run the report RIBELF20  and I am getting this error for all the sales order I created for partial delivery for configurable material.
    For Normal item, the status is showing properly.
    Is there any other settings I have to check?
    I needed this to be working. Please help