Contract - MRP Issue

Hi
Contract exist for a Raw Material,Enenthough for the demand MRP generates Purchase Requisition for that Material.
If i assign Source of supply it will automatically pick the
contract. If i create PO with ref to PR it will not affect to
Contact.
Basically I want to know the Procurment and MRP Procedure
if there is a contract exist for the material.
Thanx in advance,
RRS.

what u are doing is correct
please check have mentioned the contract no. in the sourcce list in front of your vendor and also give the mrp indicator for that vendor

Similar Messages

  • Sub-Contracting material Issued to Vendor and balance to be Issud

    Hi,
    Sub-Contracting material Issued to Vendor and balance to be issued against the Sub-contracting Purchase Order.
    Please suggest T.Code for the same.  (Same Like ME2O, but PO number should be an input parameter)
    For example I have Created PO with header Material for 1 quantity which having one child item and qty say 20 numbers, and issued child material to vendor 10 numbers (541) and balance is to be issued to vendor is 10 numbers, now I want a report which gives PO number, Header item with qty, total requirement of qty for the child item with line item number, issued child item with qty and balance to be issued child item with qty.
    Thanks
    Ramesh.G

    Report MB51 is there. Here you have to input your Purchase order number and execute but, it will show only material issued to subcontractor through 541. It will not show the balance quantities.
    And there is no such standard report which will show information how much issued to subcontractor and how much is balance based on Purchase order.
    You can develop a z report with the help of abaper.

  • Are Procurement Contracts MRP relevant ???

    Hi All,
    This may seem like a very novice question but I could not find any detail pertaining to this on the net.
    1. Are Procurement Contracts MRP relevant ? If so what are the settings required.
    2. Whats the use of creating a procurement contract with reference to a Purchase Requisition ??
    Regards,
    Imran

    Hi
    I hope you are referring to contract & not scheduling agreement.
    If you have contract assigned in source list with fixed source checked & MRP indicator as MRP relevant, MRP would generate the PR with contract as source of supply.
    Then you should have job running to conver the PR to PO for transaction ME59N with variant having "Contract" checkbox ticked.
    This would ensure that PO is released against contract for the generated PR.
    I hope this helps.
    Thanx
    Prasad

  • MRP issue for future delivery PO/STO date

    We have a sceanrio where the available material quantity in MRP list is considering future delivery date STO quantity.  The PO delivery date is 08.11.2008 and MRP run date is 07.11.2008.
    Step 1, material master details:
    Material = 16814, MRP Type = PD, Lot size = EX, Special Procurement = D0 (Stock Transfer), Consumption mode = 2 Backward\forward consumption, Fwd Consumption per = 0.
    Step 2, MRP list details , before PO creation:
    MRP list before having any purchase order = 191-
    i.e, Available qty on 07.11.2008 with a DepReq = 191-
    Step 3, Creating Purchase oder (In our case it is STO):
    We created one Stock Transport Order on 7th Nov 2008 giving Delivery date as 08 Nov 2008 which is in future. Our plant is receiving plant = y100.
    PO quantity = 2
    Step 4, Running MRP in MD02:
    Processing key       =   NETCH               Net Change in Total Horizon       
    Create purchase req.   = 1                   Purchase requisitions             
    Delivery schedules   =   3                   Schedule lines                    
    Create MRP list   =      1                   MRP list                          
    Planning mode     =      3                   Delete and recreate planning data                                                                   
    Scheduling         =     1                   Determination of Basic Dates for Pl
    Result = PR is getting created for Qty = 189, but our actual required  qty = 191 - meaning it is considering the future delivery date(8th Nov 2008) PO qty while creating PR and removing that qty while creating PR's on 7th Nov 2008.
    Here we are running the MRP on today (7th Nov 2008). STO delivery date is 8th Nov 2008
    Step 5, MRP List details, after STO creation:
    Now the PO is coming in MRP list and the available qty is 189-
    Earlier stock before purchase order is 191 - after creating purchase order (STO) for future delivery date available qty is coming as 189-
    DepReq is still 191- but the total available qty is changing to 189-
    We want PR to be created for DepReq of 191 and not 189.

    In step 2
    What is the stock?
    If it is PO then the qty cannot be in  minus 189
    step3
    Where are u running MRP? In receiving plant or sending plant and all the steps you are showing for which plant?
    It is confusing...
    What i can say is in general if it is MTS scenario, then system will always consideres stock + receipt - issues = 0 after running MRP.
    If it is MTO, then for each sales order/project segment stock + receipt - issues = 0...
    Hence apply your situation in the plant and see the data.

  • MRP Issue for subcontracting

    Hi Gurus
    When a requisition is used to build a Sub-Contracting Repair Purchase Order, then subsequently a delivery u2013 a new requisition is raised, usually once the delivery has been post goods issued this new requisitions is automatically canceled on SAP, but recently this is not the case the requisition is still active.
    Please suggest me what was the reason for this one.
    Thanks & Regards
    Sada

    Hi,
    I am not quite sure if I have understood the problem, but sometimes inconsistencies occur for dependent requirements for subcontracting purchase orders. Refer to SAP note 115899. Note explains types of such errors and  there exists a program to correct these inconsistencies.
    Edited by: Özgen Canan on Jul 21, 2011 11:47 AM

  • MRP issue after MRP run

    Hello Everyone,
    We have a issue in the MRP process. When we run MRP it creates PR for additional quantity then needed not considering the Purhcase Order that exisits already. Below example will explain you in detail.
    Product A Plant ABC
    Stock 4
    Product A safety stock = 8
    Purchase Order creatred = 3
    So when MRP run it should create another Purchase requistion for Quantity 1 (4-8+3 =1). But it is creating a Purhcase Requistion for Qty 4 which means it is not looking into the Purhcase Order Qty 3 that is coming in. There is no minimum lot size or any rounding rule.
    Please can you tell me if there is a settings/config where we allow/not allow the Purchase Order to be considered during MRP run. I think it should be a plant specific config as for our other plant I dont see this happening.
    Any help will be appreciated.
    Thanks
    SAP Fan

    hi,
    Few checks:
    1. Check rescheduling horizon...
    2. check the plannning key set while running the MRP....is it NETCH...try with NETPL or NEUPL if doing for first time...
    Regards
    Priyanka.P

  • Sub contract MRP Settings

    Hello
    Can any one guide me , how to do MRP settings for subcontract Proces.We want the system to generate MRP for the subcontract Process, We need B & C Material to Make A.  A is a finished goods , B is going to Produce and ship to subcontract Vendor  and C will be Procured and directly shipped to Subcontract Vendor . We are going to get back A as a finished Goods. Can any one please tell me what will be the MRP Settings required to create a Sub contract Purchase Requisition ?
    Thanks
    JJ

    Hi,
    For material B, it is a inhouse production. Set E - inhouse production in MRP2 view.
    For material C, it is a External procurement - F, assign in MRP2 view. For material C, maintain delivery place at Subcontract place in MIGO screen, so that material directly dispatch to subcontract place.
    For material A, external procurement - F, maintain in MRP2 view. Maintain BOM for material A.
    When BOM explodes, P.R will create for material A.
    Send material B by ME2O 541 mvt.
    And receive material A by MIGO 101 mvt.
    Regards,
    Dharma

  • MRP issues

    Dear Experts,
    We have a requirement to implement MRP in our client and we've agreed to generate Planned order as the output of MRP run.
    After then, the user will select the planned orders and convert them to PR.
    My questions are:
    1. Is it possible to generate 1 PR from many planned orders?
    2. If there's a contract exist for that material, is it possible to convert directly from planned order into Release Order?
    please advise,
    Thanks much,
    nasikhin

    MRP will support the generation of 1 PR for each material/date combination. You may later on combine many of them into one purchase order (per vendor for example).
    If a contract exists, then you can use it to process (also automatically) the vendor assignment.
    Alternatively, if you want a leaner process, you can use scheduling agreement with delivery schedules created directly by MRP.
    Regards,
    Mario

  • Production and MRP issues

    Issue-1
    i have sales BOM for my main item in which components are production item where they have production BOM, i want to create a multiple production orders for my components based on my sales item is it possible to get it with SDK

    Hai
    Thanks for your kind reply, i am also aware we can make many production orders with the help of MRP, but if i am not using MRP can i do some cahnges with the help of SDK and create multilevel production orders
    Thanks and Regards
    Boopathi

  • MRP Issue

    Dear Experts,
    I have some confusion about MRP wizard.
    In MRP running wizard step 3 of 4 i checked Existing Inventory, Purchase Orders, Sales Orders and Production Orders.
    But in  the order recommendation report status is not considering the Open Purchase orders Qty., its only consider existing inventory for child items.
    Waiting for you kind reply.
    Thns & Regards ,
    Ravi Jha

    Hi Ravi.........
    If you ticked those check boxes then it means Recommendation report will come for qty minus Ordered Qty and minus Committed Qty if something existing is there in system.
    It wont add up such Qty......
    Regards,
    Rahul

  • Sub contracting Process issue for A/c entry

    Hi All,
    While doing the GRN for subcontracting process ,cost object error is appearing for stock change SFG account ( BSV).
    Business would like to do not assign the Default cost object for change in stock account. Kinldy confirm whether it is possible to determine Internal order number ,whcih same assigned to GRN for stock in change account SFG.
    Any alternative method would be apprecaite
    Rgds
    SumaMani

    Thanks to all of us for answers !!
    We solved problem as mentioned !
    1. Created separate SFG Stock change over subcontracting GL account and assigned same in OBYC - BSV & profit centre wise internal order defaulted in OKB9 settings.Also created sub contracting expenses GL and assigned OKB9 profit centre wise. ( Problem has been solved with separate GL account of stock change over)
    It can be possible to solve with using of substituion GGB0 with module pool RGGB0*
    Rgds
    SumaMani

  • MRP Issue: Planned orders Vs Pur Requisition

    HI All.
    I have a query on MRP.
    We run Total planning for a plant in a night batch job  The parameters for variant are as below
    Planning Run Type: NETCH
    Creation Indicator for Pur Req  2.
    Planning Mode 3 Delete & recreate order proposals
    Scheduling type Lead time scheduling
    For example MRP runs on 19th Jan & for a given material, a planned order is created as the lead time 10 day & the requirement date is 15 Feb.
    Now as normal proedure, when the opening date in the planned is reached, MRP should delete this planned order & create a Pur Requisition. But this is not happening even though we have used the planning mode 3 (delete & recreate order Proposals)
    There is no planning file entry for the material after the initial MRP run. Is this the reason that the target material is not picked up in the planning.
    Any suggestions on this.
    Regards
    Vineet

    Hi
    If Requirement is 15 Feb System Calculates and Gives the proposal for 05 Feb. As you may know there is one more Schedule Margin Key  and itu2019s a buffer time before and after Procurement prosal. May be its affecting your Openeing period. Please Check the Paramaters in Material Master 1. Schedule Margin Key,2. GR Processing time, Lead Time  and planning time Fence(During this Period System Doesnt Allow Automatic changes,,
    rewd if usefull !!
    BV

  • CO11n Operation and MRP issue

    Dear All
    1. I have a query when i am doing confirmation production order CO11N at that time i am doing manually but at the time of goods movement i am unable to see my materials please help for this
    2. When i am converting planned order to production order at that time i am unable to get the default Order type its throwing an error enter order type
    pavan

    Hi,
    1. I have a query when i am doing confirmation production order CO11N at that time i am doing manually but at the time of goods movement i am unable to see my materials please help for this
    Goods Movement
    Maintain in OPK4 as ALL COMPONENTS-this is for automatic goods receipt and automatic goos issue.
    now create new production order and while doing confirmation go to goods movement tab-now you will see that raw material and finished material.
    2.When i am converting planned order to production order at that time i am unable to get the default Order type its throwing an error enter order type .
    Create Production scheduling Profile(OPKP) in spro-Maintain in order type in make to order or make to stock enter respective order type and save.
    Assign this Production scheduling Profile in respective material master in work scheduling view.
    now it will works.
    Regards,
    S.Ananth

  • Master Scheduling/MRP  Issue

    My EBS version is 11.5.10.2
    In Master Scheduling/MRP Module,under MDS and MRP Submenu,
    there is a functions named 'opertions', shows the opertions of MDS and MRP, can anybody be so kind to tell me how does the checkbox 'net reservations' work in that screen?
    suppose i have two sales orders
    SO1 ordered for ITEM A for 100,
    SO2 ordered for ITEM A for 20(reserved)
    ITEM A has 100 onhand
    import SO1 into MDS and run mrp, should i have only 80 avliable for ITEM A if i checked the 'net reservations' checkbox?
    any reply is highly appreciated!

    Hi,
    MRP is by default licensed along with e-business suite.
    You do not need explicit licensing for using MRP.
    For further queries, please contact your nearest sales office or your sales representative.
    Hope that answers your query!!
    Regards,
    Mohan Balaji
    NOTE: Please mark the post as Helpful or Answered if the update has really helped you. This would also bring the thread to logical conclusion and will be helpful for the viewers.

  • Production MRP Issue

    Hello,
    In our facility, we have production finish goods, raw materials stored at the warehouse and the other warehouse goods that we purchase. I am trying to run MRP for production finish good and their raw ingredients. However, whenever I try to run it, I always have some other warehouse items not used as ingredients that ae processed.
    How can I segregate my production MRP run?
    Thank you!!
    Chaka

    Hi Chaka,
    Another good option to include only selected materials in MRP run is to use MRP area.
    Try exploring option of 'MRP area for storage location'. System will consider only those materials which are in specific storage location (defined as MRP area). You can exclude the materials which you don't want to plan in MRP by assigning these materials to some other storage location.
    For more details on MRP area refer following link.
    http://help.sap.com/saphelp_46c/helpdata/en/c4/106956ae8a11d1a6720000e83235d4/frameset.htm
    Regards,
    Himanshu