Control of Transfer Of  Requirement  creation Screen   T code OVZG

Hi All,
I am trying to create a new Requirement Class in T code OVZG but in the details screen i am not able to change some fields like,Special Stock,w/o val start,strategy seq,costing.........etc, All in display mode how to make it in change mode.....
Regards,
Balarengan

Hi Balarengan
There will be a loft of fields in REQUIREMENT CLASS which will be greyed out
That means the values for these fields are flowing from somewhere else
Say for example Special stock (this will be greyed out)
This flows from item category in VOV7
If you take the REQUIREMENT CLASS delivery requirement 011 then the special stock indicator will be blank in greyed out
If you take the REQUIREMENT CLASS make to order cons stock type 042 then the special stock indicator will be E in greyed out
Like that some controls cant be directly given flows from somewhere else
Check in PP forum for more inputs
It is certainly not related to authorizations
Special stock comes from SD side and like that from other modules as well said by Mr.Sadanandam
Regards
Raja

Similar Messages

  • Transfer of requirement

    Pl explain me the transfer of requirement???

    Dear Shridhar Jannu,
    Transfer of Requirements
    By means of the transfer of requirements, the MRP department is informed about the quantities and deadlines by which incoming orders should be delivered. The system checks the availability of the goods based on the requested delivery date of the customer and creates MRP records which contain all necessary information for passing on to materials planning. The transfer of requirements ensures that the goods are available in time for the delivery. Materials planning transfers the reported requirements and creates production orders or purchase requisitions from them, for example.
    The following sections on the transfer of requirements describe how to control the transfer of requirements.
    The transfer of requirements is basically dependent upon the following factors:
    requirements type
    requirement class
    check group
    schedule line category
    Note
    The transfer of requirements is controlled globally using the requirements class which is derived from the requirements type for all sales document types. For the sales document types, fine tuning is also possible at schedule line level. This fine tuning is described in the section "Defining the procedure for each schedule line category".
    Note that the requirements classes are also used in production so you should coordinate  any changes to the requirements classes with production. The requirements type and, eventually, requirements class are determined in the strategy group so all changes made there should also be coordinated with production.
    Requirements transferred to planning are further processed in the module MM. You must, therefore, coordinate the transfer of requirements with the module MM.
    Requirements
    For controlling transfer of requirements, you have to carry out the following steps:
    1. Each requirement type has to be allocated to one requirement class only.
    2. The transfer of requirements must be switched on at requirements class level, the sales documents at schedule line level.
    3. You must define a check group. It is possible to have this check group proposed for the initial creation of a material master record.
    4. Note that a plant must exist for transfer of requirements to be carried out at document item level.
    Note
    Requirements transferred to planning are further processed in the module MM. You must, therefore, coordinate the transfer of requirements with the module MM.
    Reward if usefull
    Regards,
    Srikanthraj

  • Screen error while adding  table control to existing tab in BP screen

    Hi experts,
    Requirement: Add new section with table control in existing tab in BP screen. Purpose of creating table control is to add or delete multiple entries etc.
    To fill this requirement, we have created custom transaction with table control facility. When we run this transaction from SAP easy screen, we are able to add, delete and create multiple records to database.
    We have configured this custom program and screen in BDT (views) and saved.
    When we call BP transaction we are getting following error message.
    "Screen ZMOD_TEST1 0100 must be an Include screen (screen error)".
    We are not sure, the approach we have chosen is correct. Incase, any one of you come across this type of problem, please guide us to rectify.
    Thanks in advance.
    Venky

    Venky,
    If you are on CRM 4.0 or even 5.0, my approach to adding a table to business partner attributes would have been the following:
    - Use EEWB to generate the table extension
    - Modify the generated code/screens if what was generated did not meet you complete requirements
    However going back to your original question, if you add new screens for the BDT, then they must be "subscreens".  The screens you create for the BDT tool are always subscreens placed in a container by the BDT program.
    So your options are one:
    1.  Convert your screen to a subscreen and if you have coded all the BDT event function modules correctly it should work
    2.  Use EEWB to generate a new extension and make adjustments as necessary.
    Good luck,
    Stephen

  • Transfer of Requirements for Return Orders

    Hi,
    Please I need  help on TOR management with Return Orders in SD.
    I've already red  all the threads realted to TOR and ATP but I couldn't find a solution. As we know TOR is dependent on the following data: reqts type, reqts class, checking group and schedule line category.
    The reqts type and class are determined in the strategy group (material master - MRP3).
    Now if I switch on Transfer of Requirements for Returns, at Schedule Line level and Reqts Class level, the result is that I can see requirements related to Returns in the availability check overview of Sales Orders (ATP count) but if I check in the requirements list (i.e. transaction MD04) these requirements related to Returns are not recorded. Why?
    And also another point please: requirements generated from Return Orders, into ATP count are considered as normal Sales Orders (negative sign, reducing ATP quantity, when it should be the contrary because a goods receipt is expected).
    Can you help me please on these 2 points (perhaps something related with Sales Document Category)?
    Thank you very much
    Kind Regards
    AP

    I practically did a sample order / returns order to see your requirements and these are my observations
    a)
    If you create a standard sales order, then the availability check registers a minus sign with stock required in Rec./reqd qty field.
    Once you save the sales order, this is not seen again as the total quantity is reduced by sales order quantity.
    It was indicating a minus sign when you created a returns order because you checked the Transfer of requirements and availability check indicators in schedule line category.
    It was simulating a requirement as you checked the indicators in schedule line category.
    If you create returns order with standard DN (i.e. Transfer of requirements and availability check indicators are not checked), then you would not see any requirement for stock i.e. you don't see any new entry in availability overview screen.
    b)
    You are not seeing returned quantities in MD04 because of Movement types. This has nothing to do with Transfer of requirements.
    Schedule line DN uses movement type 651.
    Using movement type 651, you post returns from a customer with returns delivery to blocked stock returns.
    The blocked stock returns are are neither valuated nor part of "unrestricted-use" stock.
    Hence you are not seeing the returned stock in your available stock.
    If you click the magnifying glass on total stock i.e. top line of your stock/requirements list (transaction MD04), you could see the returned quantity in 'Returns field'.
    If you want to post returns from a customer with returns delivery directly to the valuated stock, you could use the following movement types in schedule line category.
    653 Returns from customer to unrestricted-use stock
    655 Returns from customer to stock in quality inspection
    With these movement types, you could see returned quantities in stock/requirements list.

  • How to add new fields in message creation screen

    Hi All,
        My requirement is to add another 2 fields in the message creation screen.
        Also I found this link is bit useful.
    Add custom fields to Support Message
    Can anyone share the detailed procedure to add a field in the message screen.
    Thanks in Advance.
    Regards
    Narasingam. B

    Hello,
    I think of something like:
    First, you create extension, with transaction WE30.
    Then, reduce your idoc, your extension should also be proposed.
    Do not forget to add this extension in outbound we82, and/or we57 in inbound, and WE20, and find BTE or exit to populate extension.
    regards.
    F.S.

  • Transfer of requirements

    dear gurus,
                   can any body explain the transfer of requirements from salesorder to production..ie integration of sd and pp.
    in sales orders what are all the pp parameters ?
                      -guna

    Hi Guna,
                       It is through the strategy group that is defined in the MRP 3 view that controls the integration b/w the two:
    If for eg we take the strategy 20 that is classical make to order than  product is produced specifically for an individual sales order.This planning strategy is used when planning of the (parent) product is not required or not possible.Each product is specifically produced for an individual customer so that the finished product is rarely placed in stock.Similarly other strategy can be there for example strategy 82 when a sales order is created for the material, a production order is created automatically in the background. And as follows the other given by Mr.Bala.
    With Regards
    Tarun

  • Vendor creation screen ends in withholding data

    My Vendor creation screen ends in withholding data,and the screen having no control.Only way to exit.Now we are unable to create vendor codes,please suggest.

    Hi,
    When you create vendor has 3 section .1) General 2) company code and 3) Purchasing Org .
    IF you want to create all three segment then you need to use Xk01 and you need to enter 3 Mandatory information .
    Vendor number if external , comapny code and purchasing oorg .
    Please see below screen Each of heading under each segment has tab and screen like General segment has tabs address and control etc
    if you are unable to creat then please let us know the error.

  • Transfer of Requirement & Availability Check

    Dear All,
    In simple words can anybody tell me the concept of Transfer of Requirement & Availability Check..
    I am not looking for Configuration details but want to know the basic things like......
    What is Transfer of Requirement & Availability Check?
    Where we are using ?
    How it help us ?
    etc...........
    Points will definately awarded.
    Regards
    SAGAR

    Dear Sagar
    1)  Transfer of Requirements
    Transfer of Requirements determine whether and how requirements should be transferred and if they should be checked against planned requirements. The transfer of requirements in sales can be switched on or off by transaction as required. For example, you can switch off the transfer of requirements for inquiries and quotations, whereas you can switch it on for sales orders and deliveries.
    2)  Availability Check
    There are three types of availability check:
       --> Check on the basis of the ATP quantities
       --> Check against product allocation
       --> Check against planning
    In Customizing, you determine whether an availability check is to be carried out against the ATP quanitity or against planning. The check against product allocations is controlled in the material master and elsewhere in the system.
    a) Check on the Basis of the ATP Quantities
    The ATP quantity (ATP = Available To Promise) is calculated from the warehouse stock, the planned inward movements of stock (production orders, purchase orders, planned orders) and the planned outward movements of stock (sales orders, deliveries, reservations). This type of check is performed dynamically for each transaction, taking into account the relevant stock and planned goods movements with or without replenishment lead time. Planned independent requirements are not taken into account here.
    b) Check against Product Allocation
    Product allocation facilitates period-based distribution of products for certain customers or regions. As of Release 3.0F, you can carry out an availability check against product allocation. This ensures, for example, that when production is low, the first customer does not get the full amount, resulting in following sales orders not being confirmed or being confirmed far too late.
    c) Check against planning
    The check against planning is performed against independent requirements which are usually created for an ‘anonymous’ market rather than being customer-specific (for example, in the strategy ‘Planning without assembly’, when production occurs only up to the stocking level). The planned independent requirements result from demand program planning and are used for planning expected sales quantities independent of orders
    thanks
    G. Lakshmipathi

  • How can I control an iPad from a touch screen which is mirroring the iPad screen

    How can I control an iPad from a touch screen which is mirroring the iPad screen.
    This is a very important application for disability students who wish to use iPad apps but do not have sufficient fine motor skills to use the small screen of an iPad but could use a large format display touch screen.
    There must be a way.?????????? Help!!
    Peter Niass
    [email protected]

    Have a look here
    http://www.macstories.net/iphone/the-external-touchscreen-that-can-control-an-ip hone/

  • Document is in transfer for PO, creation not possible

    Hi
    We are using SRM 4.0 EC scenario. Recently we have been facing the subjected error 'Document is in transfer for PO, creation not possible' while making the confirmation in SRM. It is observed that this is happening mostly in case once we make GR and cancel and repost. Thru some other thread posted in forum, came to know taht we need to delete the entries in table "BBP_DOCUMENT_TAB"  via FM ''BBP_DELETE_FROM_DOCUMENT_TAB''. I ran thei FM but found NO poitive results. Hope somebody can help me out. This error became very common in our production system
    Thanks
    Kiran

    Hi Kiran,
    Please, use the report CLEAN_REQREQ_UP to clear the entry made for the GR in BBP_DOCUMENT_TAB. The problem comes because there is an entry for the GR in the table probably from the previous creation.
    Regards
    Saravanan.
    Please award if useful

  • GR Error: Document is in transfer for PO, Creation not possible

    Hi Experts,
    While posting a GR for PO, following error is being encountered,
    'Document is in transfer for PO, Creation not possible'.
    I checked the PR - PO. There are multiple GRs for the PO and all earlier GRs are posted successfully.
    For posting a new GR this error is coming.
    Any pointers?
    Thanks in advance.
    -Dhananjay

    Hi Kiran,
    Please, use the report CLEAN_REQREQ_UP to clear the entry made for the GR in BBP_DOCUMENT_TAB. The problem comes because there is an entry for the GR in the table probably from the previous creation.
    Regards
    Saravanan.
    Please award if useful

  • Period shift in Transfer of Requirements

    Dear SAP experts,
    I'm looking at the following challenge. I have a situation where there a number of Materials linked to the same Planning Material. I'm using Planning Strategy 60 (on both the Planning Material and the real Material).
    The production process has for most Finished Goods only one main production step. For a numer of Finished Goods there are also one or two post processing steps required.
    With only Main production step> When the customer orders for wk X the main production has to take place in wk X-1
    With post processing               > When the customer orders for wk X the main production has to take place in wk X-2
    I have created Planned Independent Requirements (PIRs) for the planning material (requirements type VSEV) representing the (sort of repetitive) production cycle of the planning material. So for example production in week X, X4, X8 etc.
    The first challenge I had was the ATP check (not via ATP logic, but against planning). For materials that require post processing I should not do an ATP check on wk X-1 but on wk X-2.  With help of this forum I found the user exits where I could change the Material Availabilty Date for the Materials with post processing before the ATP check etc. etc. So the ATP challenge is solved.
    However, when the ATP check is succesful the quantity gets confirmed, but the actual Material Availabilty Date is wk X-1. Based on this the transfer of requirements takes place. Now it could happen that the wrong PIR get's consumed or even worse I cannot save the order, because of availability issues.
    I realize I can solve this problem by splitting the Planning Material in two. However this would seriously increase the number of Planning Materials which would make the solution not practical anymore.
    Is there anyone out there who can give me a hint on how to proceed?
    Kind regards,
    Mark

    Dear Kumar,
    In my understanding Planning table is used for capacity check and capacity levelling and to modify the existing requirements.
    Planning Table and Capacity Planning
    You can also use the planning table with capacity planning. Here, planning is based on lead time scheduling. The basis for lead
    time scheduling is the routing. You can access the capacity planning table directly from the REM planning table. The capacity
    planning table provides you with support in dispatching and reallocating production quantities.
    Check this link,
    http://help.sap.com/saphelperp60_sp/helpdata/en/5f/1faba54aee11d189740000e8322d00/frameset.htm_
    Check and revert back.
    Regards
    Mangalraj.S

  • Challan creation screen(J1if01)

    Hi,
    if the user click the material document in the report it should take user to challan creation screen(J1if01)
    i am capturing the values of Material Document & Material Document year but not capturing the Exercise Group.
    below i am attaching the code.
           SELECT SINGLE *
           from J_1IEXGRPS
           into J_1IEXGRPS WHERE J_1IWERKS = wa_final-werks.
           exgroup = J_1IEXGRPS-J_1IEXCGRP.
           SET PARAMETER ID 'J2I' FIELD exgroup.
           SET PARAMETER ID 'MBN' FIELD WA_FINAL-MBLNR .
           SET PARAMETER ID 'MJA' FIELD WA_FINAL-MJAHR .
           CALL TRANSACTION 'J1IF01' AND SKIP FIRST SCREEN.

    Hi,
    What i understood with your question!!
    Is it giving you error in that transaction of challan.
    If it is a mandatory field without which you cannot move ahead than pass other group field
    and check again.
    Please specify the exact problem you are dealing with..
    Regards,
    Mayank

  • Relationship b/w the PO number field in the SO creation screen(va01) and th

    Hi All,
    What is the relationship b/w the PO number field in the SO creation screen(va01) and the sales order .
    Can we maintain a specific number range for the PO Number??
    If yes where do we maintain the setting?
    Cheerzz..
    Subbz..

    Hello,
    This is nothing to do with a SAP purchase order, and you can't maintain any number range for the same as it is not a system proposed one.
    Imagine, the customer is sending a purchase order to you, and you are creating a sales order. We can give a reference to the customers PO number in this filed. It doesn't have any effect.
    It is widely used in reporting.
    Prase

  • How to remove the "table control" icon in ITS based ESS screen

    Hi All,
    I have upgraded my external ITS 620 to patch level 28. Earlier we were on patch 04.
    Since then I am seeing the table control in my ESS screens (ITS Based),
    In some thread i got to know that the table control is totally redefined / modified from patch 22 of ITS.
    Is it possible that we can remove / hide the table control from the screens.
    I dont want to let the users access the "Table Settings" screen at all....can u plz tell me how to do it
    regards,
    PK

    we could not remove the table control...it seems like we can not remove it as the table control also appears in the r3 screens also..

Maybe you are looking for

  • Time Machine issue on a new iMac - "Cleaning old backups..."

    Just got a new iMac. Migrated my system over from a TM backup from my old iMac. I then let TM inherit the backups on that drive. Now, I am attempting to do a TM backup, and it stays on "Cleaning up old backups..." forever. What's the deal?

  • Run Time error - Description of Exception

    I was loading data from Source to PSA, and it failed because of: Runtime Errors         DBIF_RTAB_SQL_ERROR Date and Time          05/22/2007 17:33:52 Short text      SQL error occurred in the database when accessing a table. Trigger Location of Runt

  • Connect Coldusion to Oracle when encryption connection is enabled

    We have had ColdFusion 8.0.1 connected to Oracle (11g r2) with no problem until we encrypted the Oracle connections. All our software tools had no problem still connecting except Coldfusion. Supposedly encryption changes should only have been server

  • Query consuming more time

    Hi, Db: Oracle 9.2.0 OS: AIX. We are running the below report. and it takes around 6 hours. I want to know exactly where the issue is. else, please refer me any gud doc id for query tuning. SELECT FLT . MEANING "Bank Name" , PPV . EMPLOYEE_NUMBER "Em

  • Spry insert master/detail layout Can't get more than two columns?

    Ive been trying to get more than two columns just experimenting with spry data sets and can't with the layout option "insert master/detail layout" What am I doing wrong? <!DOCTYPE html PUBLIC "-//W3C//DTD XHTML 1.0 Transitional//EN" "http://www.w3.or