Control receipe creation in process order

Hi,
Can you please tell me how to create control receipe.
After releasing the process order when I select the button for creating  control receipe. System shows error as " No control receipe generated"
Please tell me the basic steps required to create control receipe and PI sheet.
Regards
Karthikeyan

Hi,
Check In master Recipe ,in the PI Tab,There must be some PI category is assigned and in that PI Category,this PI Charactiristic has been assigned.
First goto that Phase of the Master Recipe and then goto PI tab and then find the PI category.
In Process order
Goto->List->Control Recipe List--->
As per above link first find out Control Recipe is generated or not and also find out its status.
If Status is Created then you can find it in CO53,
if status is Sent then you can find it in CO55 or CO60
Please rfer this thread also,
https://forums.sdn.sap.com/click.jspa?searchID=16154042&messageID=5839678
Regards,
R.Brahmankar

Similar Messages

  • Change Production version during creation of Process Order COR1

    Hi,
    Scenario:
    Based on the entered Material, Plant and Order type system need to trigger a popup asking the user to select the Production Version. This should happen before clicking on SAVE button, so that all the values will be populated correctly based on the changed VERID.
    I did not find a user exit that enables to change the Production Version (VERID) value. So I thought of displaying the popup in the user exit EXIT_SAPLCOZF_003 which will be triggered before initial screen appears, export the selected value and pass it to a User Exit or BADI where VERID can be changed. But cannot find a user exit to do it.
    Please help me find a User Exit or BADI to change the Production Version during creation of Process Order using COR1 transaction before clicking on SAVE button.
    Thanks,
    Manoj.

    Hi Manoj,
    So - almost four years later - I saw your post and I saw myself in the very same situation as you did...
    I found a solution for those who wants to change the production version of the production order from the sales order creation: create an enhancement in the function module 'MD_VERSION_SELECTION' and you are good to go.

  • HOW TO CONTROL ON CREATION OF SALES ORDER WITH REFERENCE TO EARLIER SO?

    Dear All,
    I want to contol on creation of Sales order with reference to earlier SO?  While creation of sales order our enduser are creating sales order with reference to earlier month SO which I want to restrict. Recently I made changes in sales order like payment terms is grayed, system will atomatically pick pay terms from customer master.Now I am getting correct data also but enduser is using old SO no while creating new SO and old payment data is reflecting in fbl5n.
    I want to restrict enduser while creating new SO with ref. to old SO. Only for returns they should be able to use Billing refrence. Pl. suggest how to control the with reference to ealier SO.
    Nikhil

    Nikhil Deshpande,
          If you dont want allow create a sales order in referent to other one, just delete the copy control between these sales order type, so when the user tries to create a SO in reference to other one a message is displayed that is not possible.
    Thanks,
    Mariano.

  • Manufacturing date entry control in MIGO for process order GR

    hi
    when i make process order GRN output entry ,i enter the manufacturing date for the batch.But it is now allowing me to enter,future date as well as any past date even before the RM issue date.please let me know wheter any control can be given so that while enterin manufacturing date , system should not allow a dae earlier than , RMissue date or Operation start date and any date future than the material recipt GR date for the output.The best practice is the manufacturing date is the date on which the first operation of the batch starts.
    unnikrishnan

    please write the user exit for the same

  • Apportionment Structure -In Control Data Tab of Process Order

    Dear Gurus
    How we can enable Apportionment Structure in Control Tab of Process order. In the drop down menu list i can see the Material / Plant / Appont str in the field of Apportionment Struct ( But it is disabled ) .
    Thanks & Regards
    Anupama

    Hi
    If you have co product then it will get enabled.
    Thanks
    S.Murali

  • Batch creation during process order

    Dear all,
               Can any body tell me for some materials Automatic batch is not creating after releasing the process order.
    Regards
    Ravi

    Dear,
    Go to MM02 of these materials click on work scheduling view and check which scheduling profile is maintained there.
    Then go to CORY and check same scheduling profile for Auto Batch Creation. If scheduling profile is missing then assign same in work scheduling view of material master.

  • Error in creation of Process order

    Dear Expert
    while creating a process order i am getting 2 errors no valid task list for key date and lot size
    No task list with in validity period of production version , how to resolve these error
    Regards

    Dear Usmfarhan,
           Check your validity in your routing and BOM , and also check the lot sizes are matched or not in these two master data, in C223 check the production version you will get the error if it does not matches, check and revert back.
    Regards,
    Karad D D

  • Error with Creation of process order

    HI,
        I am trying to create a Process order, system throw the error message "No valid task list for material XXXXX plant XXXX  for sel.criteria". MAster data has not been transferd. I have checked in Recipie and BOM Nothing is missing, evry thing is fine. But as for my best of knowledge, it has been mantained correctly.
    Kindly tell me what could be the problem & how to resolve it.
    Regards.
    NSR

    NSR,
    The problem could be the validity dates or Lotsizes or status.
    Most often faced problem could be that you would have created the recipe valid from todays date, but you may trying to create a Process order back dated. You can go to the master data tab in the process order display transcation(COR3) and check the Explosion dates, and check in C203 your master recipe header valid from date.
    Regards,
    Prasobh

  • Creation of Process Order without assigning master recipe

    Hi,
    I want to create a process order without having default master recipe for the given material or default operation for the given order type. I want the user to select the master recipe manually in process order. We do not want to use production version also.
    We can define the default operation for the order type (OPJG) so that we can create a process order. I do not want a default operation in the process order but the user should select a valid master recipe. If we have default operation in the process order, it serves no purpose as it is never used anywhere.
    Is there any way we can achieve this?
    Regards,

    Hi,
    Please find the required details and conditions for creating process orders without master recipe.
    http://help.sap.com/saphelp_47x200/helpdata/en/89/a42cb3461e11d182b50000e829fbfe/frameset.htm
    Regards
    Kannan

  • Creation of process order

    Hello,
    I would like to know how to create a process order, the T-code for it and i would like to know the steps involved in lnking the process order and replenishment based on the process order.
    Expecting an earliest response.
    Thanks,
    Maxx

    Hi,
    Can i use the process order as a reference doucment while posting a MIGO transaction. I tried using the process order as a refernce document for Goods receipt with inbound delivery. but while posting, a statement indicated that the process order doesnot contain any selectable items.
    i want to know whether it is a right process or do i need to make any chnages whil creating the process order.
    Thanks,
    Maxx

  • Table for transaction code for creation of process order

    Hi Gurus,
    Please tell me, in which table i can see the transaction code used to create process order.
    regards
    Kaisar

    Hi,
    Table for transactions is TSTC.
    If your looking for t-code for process order - COR1.
    Regards,
    Vivek

  • Control recipe generation from process order

    Hi,
    Iam using XSteps to generate control recipes for external destination ie destination type 02. But I find no control on the number of control recipes that can be generated.Whenever I click on the generate control recipe botton,  a new control recipe is getting generated,
    I need to have a control on this similiar to the case of destination type 04. ie system will not generate a control recipe if already a control recipe is there for a destination.
    Can anybody know how to bring this control?
    Thnaks in advance
    Regards
    Prathib

    Hi
    If you want to restrict quality inspection based on production order type, Its possible. Use exit QAAT0001. Take help from ABAPer, dont forget to set E_NO_INSPECTION based on the order type field there. VERY IMPORTANT: Put  E_TQ32 = I_TQ32 in the program, otherwise you will get error "Post stock in QM only"
    SDG

  • Automatic Creation of Batch in Process Order Confirmation

    Hi Guru,
    What are settings required to set the batch creation automatic during the confirmation of the process order? The header material is semifinished and batch management is ticked in the material master. BOM has been created. In the present scenario, few
    Regards,
    Raja

    Hi,
    You can do that in T Code CORW.
    For the required production scheduler select the batch creation for process order.
    Also in the Assignment tab of the process order, there is a field for batch, next to it there is a Create button. Click that, you will get the batch number in that field.
    Hope that helps.
    Regards,
    Rohit.
    Added: I apologise, its not the Assignment tab in process order. It is Goods Receipt tab.
    Edited by: Rohit Chauhan on Aug 3, 2009 9:42 AM

  • Stop Creation of reservation while creating process orders....

    Hi All,
    THe requirement is to stop creation of reservations on creation of process order.
    have done the configuration in order type dependent parameters to stop creation of reservations on creation of process order.
    After this configuration the reservations have stopped appearing in the MMBE for components although there are reservation created.
    The above case appears only when i am creating process orders manually through transaction COR1....But when process orders are created by converting Plann order then in this case although the order type is same there are reservations visible in the MMBE transaction for the components.
    Request you to please guide through the reason for creation of reservations when a process order is created by converting a plan order.
    Thanks in advance for your help.
    Vinit

    Hi All,
    We are using the planning strategy 40 where in we produce only when the sales order is received.
    For a material we are using SPK as stock transfer from other plant.
    The requirement for this material is triggered due to 1)dependent reservation(as this component is used as a component to manufacture other material 2)Sales requirement for this material.
    On MRP the requirement is transferred to the supplying plant and we receive the stock in our plant.
    Now this stock is the total of requirement generated to fulfill the sales requirement and the consumption requirement.We cannot differentiate which stock was called in for sales order and which for fulfilling the production requirement of the superior material.
    Whenever a production order for the superior material is created reservation for this material are created because of which the stock will not be available for creation of deliveries for sales orders.(This is because of the av checking rule)
    Is there a way to differentiate these stocks.
    We thought about creating MRP areas to manage the requirements differently but this will lead to creation storage locations and thus affect our global template.
    Thus we thought of blocking of creation of reservations......this we thought as all the materials are already available by the time the process order is created so there is no point in creating reservations for the same.
    Let m know if you need any further information .......Help me providing a proper solution to the issue.
    Thanks in advance

  • Text in PI Sheet and Process Order did not match

    Dear Sir,
    We are going to upgrade to our system from 4.7 to ECC6.
    We have a problem with PI Sheets with the Long text. The text instruction shown in the PI sheet is not matching with the long text put in the Process Order and Master Receipe.
    We are using the Process Instruction Category  "INST" and we are puting long text for instruction for this in the Master Receipe. At the time for creation of Process Order this Process instruction Category fatch correct value of long text from the Master Receipe after released the Process Order, Control Recipe generated for the same Process Order. But when we are going to process these Control Receipe from the T-Code CO60, We find the some different text for the "INST".
    This problem is not for one Material and Plant Specific.
    Thanks and Regards,
    Gaurav Kumar
    Application Consultant SAP PP
    Mobile +91 9971003631

    Hello Gaurav,
      There might be another possibility, make sure if you make any changes in the Control Recipe Destination program or user exit to populate the long text while sending the CR to the destination to reflect with the PO/Master Recipe.
    with best regards
    K. Mohan Reddy

Maybe you are looking for

  • I want the projected image on the wall to just be the full screen of the slide

    when I plug my mac air into my projector, Keynote display on the wall has Current slide: 1 of 85.  How do i make this go away on the projected image?  This also decreases the size of the image on the wall.  It's not full screen on the wall.

  • Service Product Cost & Profitability

    Dear Experts, I am having the following situation. 1) My Service product is relevant for cost but not for CATS entry. 2) Can I maintain a standard cost related to a service product? I evaluated the option of replicating the service product to R/3 and

  • ANN: Half-hour webinars (free) -- Web-based videos in PDFs (Apr 18) / Metadata in PDFs (Apr 25)

    (free; no fluff, no hype, no nonsense; starting 9am PT) Integrating web-based videos in your PDFs (with FrameMaker-to-Acrobat TimeSavers + Multimedia Asst) Thursday, April 18 https://www3.gotomeeting.com/register/954869454 Metadata in PDFs authored w

  • Help Customizing File Manager

    Hello, I am not sure if it is possible to do this. I really like mac and dreamweaver but the only thing I do not like is the way it mixes directory folders with and other files in alphabetical order. I am used to have directories above all the other

  • Auditing oracle applications

    Dear all, We have r12.0.4 installed on solaris.. Now the management is asking to audit all the financial users, basically they want to know the user login ,log0ut, transactions he/she did, daily activities. Told them that this will be heavy on the sy