Cost Centers for Work Orders

HI Guru's,
I have an issue with work orders for our maintenance team. The orders are being settled to the incorrect cost center.  I believe this is happening because they have not been set up correctly.  Please can you tell me if there a way to transfer these into the correct cost center?  and how can I change the set up on these work orders?
Please can you help.
Best Regards,
Yasmeen

It sounds like you need to change the settlement rule on the work orders so they settle to the correct cost center.  Go to IW32 -> Goto->Settlement rule
To move previous postings, you can do an CO only reposting using transaction KB11 to move CO postings to the correct cost object.
Good luck!
Tammy

Similar Messages

  • Cost Centers for Work Centers

    Dear All,
    In our senario we have defined 30 Work Centers required.   here the Activity are only for 2 (labour, Mechaine Hr).  In KP26 we have to maintain the Standard Price.   How can we build a logic in this.  Can we create 30 Cost Centers.  Y becoz each end eavery work center have the different price for Labour.  for EX;
    WC1 - 150 Labour Cost
    WC2 - 180 Labour Cost
    WC3 - 190 Labour Cost
    Like this we have to calculate.  I hope it is required to create 30 Cost Center to assaign wot Wrok Centers.  Here we are going to KP06.  We have a standrd pirce to calculate.
    Regards

    Dear Raj,
    IF the business is interested in capturing using different cost centers means then you can create individual cost center and
    assign it to the work center and define the rates in KP26.So only one activity type will be there but different cost center.
    The otherway is creating multiple activity types say LABH1,LABH2....and creating different rates for the activity type ans same
    cost center combination in KP26.But here the challenge is you have to assign the activity types properly under costing tab
    against the formulas.
    Check and revert back with your queries.
    Regards
    Mangalraj.S

  • Actual costs posted to work order without maintaining costing variant

    hi,
    i havent maintained costing variant for work order(maintenance order) type i used to create the work order. so when i posted goods issue, how does the actual costs get posted with out maintaining the costing variant for work order type. what is the role of costing variant configuration in work order type settings.
    thanks,
    monica

    Hi monica,
    Costing variant forms the link between the application and Customizing, since all cost estimates are carried out and saved with reference to a costing variant. The costing variant contains all the control parameters for costing.
    The configuration parameters are maintained for costing type, valuation variants, date control, and quantity structure control.In costing type we specify which field in the material master must the price be updated,
    In valuation variant we specify in what order the system should go about accessing prices for the material master planned price, standard price, moving average price etc. Further which is the price which should be considered for activity price. How the system should select BOM and routing.
    assign points if useful
    Regards
    Genie

  • Is there a process for moving costs from maintenance work orders to capital

    Is there a process for moving costs from maintenance work orders to capital projects?
    We have reversed the settlements on the work orders, and then trying to put the relevant NWA in , then receive error message :
    Rule for allocation of PM order to PS network is not maintained.

    hi
    check the allocation structure and the settlement related customization settings.

  • Error reading material cost estimate for sales order (KE292)

    Dear All,
    I have an issue with billing. we are posting july month transactions, the material cost is maintained through MR21. When releasing billing document for accounting we are getting error message like"Error reading the material cost estimate for sales order "11"
    Message no. KE292
    Diagnosis
    In Profitability Analysis (CO-PA), the system tried to valuate item 000010 of sales order 11 by reading the corresponding product cost estimate.
    However, no product cost estimate could be found for this sales order item.
    The system accessed product costing for product AMLFP011011XX00P using costing key YB3 as defined in the
    CO-PA Customizing settings.
    System Response
    The system cannot process the document any further.
    Procedure
    Check your Customizing settings."
    We cross checked with other client as a current date and we ran cost estimate through CK40N with same material. and we posted entries. Here it is working fine. but in above process it is not working. Can you pls guide me where i missed.
    Regards,
    Nagaraju,

    Hi,
    When the Costing Key is assigned to the material types in the COPA customizing, then system expects Cost estimation when billing is released to Accounts.
    If you dont run cost estimation but update the material master through MR21, system will not accept as in the Costing key configuration you must have selected the Current Standard price field for the valuation.
    Hence, try to run cost estimation and then do releasing.
    Thanks & Regards
    Ravi Kumar

  • Cost centers for reveneue

    Hi,
    can we use cost centers for revenues and cost both?
    Thanks!

    Hello,
    In general, Cost Centers are not meant for revenue posting. They are meant for expenses. However, you can allow them by your cost center category. But, this is not industry best practice.
    Cost center, WBS element and Internal Orders are real CO objects, where the real postings will flow.
    Profit Center is always statistical only (statistical means just for information postings) - These postings are like shadow postings.
    When you give two real CO object for posting like Cost Center and Internal Order (Real), then real postings will go to Internal Order (Real) and statistical postings will flow to Cost Center and the profit center assigned to Internal Order. Cost center will modify itself to a real or statistical based on the other CO object given.
    Hope this is clear.
    Regards,
    Ravi

  • How to Mass change cost centers for assets

    Dear All,
    I have change the cost centers for about 1500 assets. I am not sure if there is an easy way to do it. Is there any way to get this list in excel and upload?
    I am using ECC 6.0 (I think CATS could not be used.. but I might be wrong). Thanks in adv for your help.
    SD

    Hi
    I hope the above given suggestions will not fullfill your requirement,
    Do follow the below steps for carrying out mass change of cost centers in asset master data.
    Enter t.code-AR01 - Generate
    Enter your Co.code and the assets numbers for which the cost centers have to be changed and execute.
    In the next screen select Create worklist (CntrlShiftF8)
    Give the worlist a Name and select-Change asset w/o dialog (bulk change) and press enter,from the next pop up select create Substitution,where you will be taken to creation of Substitution rule.
    Write a Substitution as per requirement and assisn the same to your company code.
    Where  you will be prompted with a message "Work queue XXXXXXXX added".
    Now enter into AR31 - Edit and release the woklist and see that your mass change of cost centers is carried out.
    hope this might help you in doing mass change of cost centers in asset master record.
    Good Luck
    Hari

  • Automatic settlement for work orders.....Plant Maintenance....

    Hello everyone,
    In plant maintenance, does anyone know how to setup automatic settlement rule assignment for work orders?  We know how to do it for internal orders already but the concept doesn't work for work orders.  We are on release 4.6C
    Thanks,
    Chris

    hi
    while maintaining the settlement profile you can define the default oject categors as CTR and in the equipment master you have to specify the cost center, and if you create maintenance order then settlement rule will be automatically created
    if you want some specific cost center as default irrespectiv of equipment then you have to use the customer exit
    IWO10027 User exit: Generate user-defined settlement rule
    regards
    thyagarajan

  • Sales Commission poting to Cost Centers Through Sales Order

    Dear All
    I have a situation. My Client want to post commission on different Cost Centers for different materials on the processing of Sales Order.
    I mean when a sale order is processed the Commission will be expended in One GL but it should be posted to different Cost Centers for Different Materials
    Can any one please help me how i can configure this
    Regards
    Bilal Athar

    Hi,
    You can try to create a substitution in CO (OKC9) and to substitute cost centre based on material number - COBL-MATNR (grouped in sets).
    Regards,
    Eli

  • Different Cost Centers for Different Line Items in a single Reservation

    Hello Gurus,
    When we create a Material Reservation, we give the cost center at the header level and that cost center is accounted for each of the line items in the reservation. But when the reservation has many line items which depend on different cost centers,  there is a need to enter different cost centers for different line items in the same Material Reservation. How can this be done? Please suggest.

    Hi,
    It's a standard restriction in SAP functionality  where one reservation document can only accommodate one cost center.
    You can not maintain multiple cost centres for individual line items.
    You have to create seperate Reservations for each cost centre.
    check below thread:
    ONE RESERVATION FOR DIFF COST CENTERS
    Umakanth R
    Edited by: Umakanth R on Dec 8, 2011 7:53 AM

  • Function Module for data retrival for work order clearence (WCA)

    Hi All ,
      Function Module for data retrival for work order clearence (WCA) for a particular Planning plant and (WCD's).
    Thanks.

    Hi Anne,
    BAPI_PRODORD_GET_DETAIL
    BAPI_PRODORD_GET_LIST
    You can find further FM in Function Group COPRINT and CODR or take F4 on CO* in Function Group
    These will serve your purpose.
    Cheerz.
    Ram

  • Table for Work Order

    Can you please tell me what is the TABLE for 'Work Order'?
    Regards,
    Subhasish

    hi Subhasish Ganguly,
      these are the tables of worked order which used in work order make and udates
        AFIH, AUFM, PMCOQT, PMFLAGS, AFFL, AFKO, AFPO, AFVC .............
    Hope i will help u.
      with regard
    chetan vishnoi

  • No delivery costs exist for purchase order

    Dear Friends,
    While doing MIRO, i am getting an error message as mentioned below----
    "No delivery costs exist for purchase order xxxxxxxxx"
    Message no. M8014.
    Kindly guide me in resolving the error.
    Thanks & Regards,

    hi
    >"No delivery costs exist for purchase order xxxxxxxxx"
    itself says that there is no delivery cost,
    firstly check ur PO ,Did u entere the delivery cost conditions like for freight or octoi in the PO
    or if u have entered the condition then check if it is not already invoiced
    if u dont have delivery cost in po and wanna do IV for material then in miro
    change the option of delivery cost to goods/service
    (at right side of the po no field)
    regards
    kunal

  • HR table for cost centers for positions

    Greetings to you all
    I need to get cost centers for positions, both vacant and occupied positions. I've tried PA0001 but this one only caters for positions which have already been occupied.
    thank you

    Try with RH_GET_COSTCENTER_OF_OBJECT
    Regards
    Marcin

  • How to obtain profit centers and cost centers for a particular GL account

    Hi Gurus
    Can you please suggest me a table or a function module to obtain profit centers and cost centers for a particular GL account.
    Thanks in advance for help!
    Regards
    Ankit

    Hi There, I have a simillar problem as above, however I would like a list of all G/L Accounts with profit centres and cost centres as well. Is this possible? Reason being that I have many unassigned cost centres and need to link them to profit centres.
    Is there also a mass processing list to see which G/L accounts dont have primary elements assigned?
    Regards,
    Edited by: Luke Saloojee on Jul 29, 2008 8:12 AM

Maybe you are looking for

  • Row Not Found from executeQuery

    Statement sql = con.createStatement(); ResultSet rs = sql.executeQuery("select * from emp); How do you know if the executeQuery has returned any rows ? How do you test for row not found. thanks

  • My photos did not download

    My photos did not download to photo album

  • ACNS nsc link issue

    My windows player is returned with a link something like this http://server_ip/stream.nsc?item=12345&enviro=67890&type=.wmv However when I try http://server_ip/stream.nsc it works fine. My question is, why does the ACNS system fail when the link has

  • Missing App category under Library section

    So I had upgraded to the newest iTunes a week ago or so but havent restarted my computer in a while which I did today. So when I opened iTunes it said welcome this is your first time using itunes etc.. My library was all there and its the usual welco

  • Ipod Touch January Update

    I bought the January Update about a month ago, and I haven"t gotten it on my touch yet. Is there anyway I can resell it back to Apple for the 19.99 store credits?