Cost Centre Error

Hi All,
Can anyone help me the possibilities for the error given below:
"Error: Cost Centre is blocked against revenue postings on 30.04.2007"
Pls reply asap.
Vinay

Hi
Normally cost centers are used for capturing and analysing costs incurred on a particular cost center or group of cost centers
So generally only the costs are posted on costs centers and revenues are not allowed to be posted
This control is there on the cost center master data in Control Tab
If you want to post the revenues also to cost center remove tick on Actual Revenues and post entry.
But even in that case you can only post revenues on cost center as a statistical posting. So u need to give a real CO object for capturing revenues for eg. COPA Segment etc.
Hope this clears your error
Regards
Ram

Similar Messages

  • Field cost centre is a required field for GL account Error

    The error that I get during a sales transaction is: Field cost centre is a required field for GL account Error. Where or which transaction in FI do I use to maintain this setting.
    Thank you.

    Hi,
    Goto Tcode - OKB9. Search for that G/L account number under your co. code. There select the row, you can maintain the cost center directly. Else for Account assignment detail column, keep it as 1(Valuation area mandatory). Then under new entries maintain the valuation area, which is nothing but the plant, and against that maintain the cost center.
    Hope this resolves your query.
    Please let me know if you need any additional information.
    Thanks,
    Prithwiraj.

  • MIRO Error-Can not post to mat.account & using overhead cost centre &.

    Dear Colleagues,
    On MIRO,users have come across this error where they can not post to a particular G/L account using 2 different cost centres(219 & 220).
    We have some validations on OB28 but although one particular step menitons this message as I stated above,the prerequisite of that step seem to be referring to G/L IN VAL_Plant No_16 AND Cost Center IN VAL_Plant No_17.
    Whereabouts I need to maintain this G/L account/Cost Centre Combination?II had a look at OME9/OKB9 but couldn't get any resolution looking over there...
    All Help appreciated.
    PAPJ1.

    I had to tweak the types  of error messages on OB28 temporarily,to allow for these postings to go through and it worked!.
    PAPJ1

  • GL account posting error with cost centre

    Hi experts
    I am trying to post Goods issue with the combination of GL account and cost centre...
    The system throwing an error message saying " GL account XXXXX not valid for cost centre XXXXX or order entered"
    what could be the mistake i have done... kindly reply
    Thanks
    Alex

    Hi
    Z message means you have a custom validation in Place
    Go to OB28 and check which validation is causing this issue..
    you need to either change it so that this posting goes through or use a proper GL account in accordance with the validation
    Regards
    SAPFICO

  • RAPOST2000 error as Cost Centre blocked

    Hi
    Would like to check with you on the monthly depreciation posting as if one of the cost centre of assets was blocked:
    1) 4.6C RABUCH00 run in background and failed as certain cost centre was blocked. The job re-run and the system will prompt user to enter the correct cost centre WITHOUT changing the cost centre in the respective asset master.
    2) ECC5/6 RAPOST2000/AFAB run in background but flag out error as the cost centre was blocked.
    For that scenario, does that mean we need to change the cost centre in the respective asset master IF we do not want to unblock the primary posting of the cost centre?
    Pls advise and thank you so much.

    Hi Claudia,
    this issue arises very often with the new depreciation run. But the main question should not be "how can I change the cost center within the posting so that the depreciaiton run does not fail". Because if you changed the cost center in the past processing the Batch Session, you definitely created an inconsistency. The cost center stored in FI-AA tables has not been the cost center being used in the FI and CO documents.
    If you do not need that consistency, it is in the users responsibility. But personally I doubt this procedure.
    So personally I agree on Pauls statement, it is - from my personal opinion - more reasonable to spend some time assuring data consistency, then to skip system checks accepting side effects and inconsistencies.
    Regards,
    Markus

  • F-92 posting error- Cost centre locked for revenue posting

    Hello,
    While I am trying to post F-92 (Asset Retirment), I get the following error:
    "Cost center AR011001 in controlling area 1000 is locked for revenue postings on 25.11.2009."
    How do I go ahead?
    Thanks,

    Hi Eli,
    Thanks for the quick response.
    I am aware I can remove the lock indicator in the cost centre master data.  We had earlier uploaded cost centre master data through LSMW .
    My question is  once the lock is removed , we will be able to go ahead and post to the cost centre .The Gl account used here is CLEARING REVENUE ACCOUNT FIXED ASSET and when we assign the cost centre with lock indicator we get the message
    "Cost center AR011001 in controlling area 1000 is locked for revenue postings on 25.11.2009"
    Would like to know the impact (apart from effect on reporting) once the lock indicator is removed.
    Thanks,

  • Error while asssignment of Org unit  to cost centre.

    HI  Frdz,
    When I am traying to assign org unit to cost centre I got this error CALL_METHOD_NOT_IMPLEMENTED.
    Experts pls let me know  how to solve this error.
    I maintained A\001 relation for cited above.
    Thanks in advance.
    Best regards,
    Narayana Kaja

    Check the table T77S0
    When you create relationships between cost centers and positions or
    organizational units in Organizational Management, the system requires
    that the cost center is assigned to a controlling area, as a cost center
    must always be assigned to a particular controlling area. In this case,
    the value of this entry will be used as the default for the controlling
    area.
    Let me know if you need more information.
    Thanks,
    Kiran.
    Reward points are appreciated.

  • Error while uploading cost centre

    Hi Experts,
    I am trying to upload the cost centres against org unit in pre-production client in PP01
    After giving relationship A011 and selecting the cost centre if I am clicking on save it is throwing this error "Personnel number 123456 does not exist"
    Pls let me know your what would be the cause
    Thanks

    Hi,
    error "Indicators are not their for controlling area" but I hav given the controlling area as well
    please check you have now controlling area for fiscal year 2011, or desired year.
    i think you do not have for the fiscal year that you are trying the same.
    go to OKKP for your controlling area for fiscal year 2011 & select in as CoCd->CO Area ( controlling area same as company code) and active components/control indicators for { Cost Centers : Component Active ,Order Mgmt: Component Active } and then save.
    or it might be in T.Code: OKE5
    Check whether control indicators is checked in OKE5 or not.
    this is done by FI consultant. if you have authorization then do it, if not consult your FI consultant.
    regards,
    mohammed
    Edited by: 0mohammed1 on Nov 9, 2011 5:23 PM

  • Cost centre posting error

    Hi
    There is an error while intergration postings from PM module to cost centre as follows.
    "Indirect postings are blocked for this cost centre"
    Can some one suggest what is this error?Cost centre master record is not locked for any postings.
    regards

    Hello
    Because of the following reasons u were getting that error message:
    1) while creating the cost center categories, activated the secondary costs, then it will not allow u to post the indirect postings.
    2) while creating the cost center, you have activate lock for secondary costs, then it will not allow u to post the indirect postings.
    3) Check the okp1 settings, where concerned peiod is opened for indirect postings or not.
    I hope it will fulfil your requiremets.
    Regards
    Madhav

  • Goods Receipt of BOM material- cost centre required for components

    I have created a subcontracting PO with a BOM material.
    When trying to post a Goods Receipt the components of the BOM material are required to have a cost centre assigned to them.
    The profit centre for the BOM material and components are the same. The BOM material does not require a cost centre to be entered in the Goods Receipt as the Profit Centre is allocated to account assignment tab.
    Why does the profit centre assigned to the components not default in the account assignment, why is the system asking for a cost centre?

    I receive this error when trying to post the material document:Field Cost Ctr is a required field for G/L account 1000 7023000200
    Message no. F5808
    Diagnosis
    The value for field "Cost Ctr" in the interface to Financial Accounting is an initial value but you are required to make an entry in the field selection for G/L account "7023000200" in company code "1000" linked to the field selection for posting key "81".
    System Response
    Error
    Procedure
    It might be an error in the configuration of the G/L account field selection. The initial application, used to call up the interface must otherwise define a value for field "Cost Ctr". If this is the case, contact the consultant responsible for the application used to call up the interface or get in contact with SAP directly.

  • Cost Centre Derivation Issue at the time of PGI

    Dear Experts,
    At the time of Posting Post Goods Issue, SD Consultant is facing error that GL Account 6* requires assignment to a CO Object.
    According to my understanding, system should derive Cost Centre at the time of P.G.I through following logic :
    I have assigned Profit Centre : 999999 to the Cost Centre : ABCD and the said profit centre is being used at the time of Sales Order Posting. While doing PGI, system should derive cost centre data from Profit Centre Data which is used in Sales Order but currently system is not behaving like this.
    Another way is to assign respective cost centres against COGS Gls through T-Code : OKB9 which is not right I think. Because how can we map Cost Centre Data with Profit Centre Data in order to get Profit Centre Wise Profitability Reports?
    Please guide me any solution.
    Regards,
    Sapna

    Hi Sapna,
    For most cases, your COGS account should not be a cost element.
    Secondly, if you want to make it a cost element, you will have to maintain OKB9 for it, either on the basis of profit center or plant.
    System cannot pick cost center based on the cost center master data because there may be many cose centers assigned under the same profit center. There is no one-to-one mapping of cost center to profit center.
    I would suggest you do not make COGS as cost element unless the sale order is an MTO sales order or business insists on it.
    If business insists on it, then add the cost element to OKB9.
    BR
    Abhi

  • Cost centre without business area

    Hi All,
    I have document splitting with business area and profit centre mandatory, along with this i have configured business area wise FSV in OBY6.
    We have  configured 10 business areas and 5 profit centres, but i have  created cost centres without business area and i dontwant to create cost centres with business area becoz junk master data in system and no control to users. also i have done configuration in OKB9 for automatic posting expences account with the combination of valuation area-business area- & cost centre, but when we are posting any financial document though MM or SD transactions like PGI or MIGO for service, system is not allowing to post financial document without business area cost centres. Error "Business Area XXXX / Cost centre XXXX is not assigned".
    After all analysis i came to know that, if we have cost centre with business area then only we can move with this set of configuration. Is it right?
    In No. what need to be done. basically we dont want to create cost centres for all Business Area
    Thanks in Advance,
    Sahil

    Hi,
    If you are not ready to maintain BA in CC master you should write Substitution / you should maintain derivation rule for deriving business area.
    Regards,
    Viswa

  • Balance in 1 currencies at  the time of settlement of WBS to cost Centre

    Hi,
    while settling the WBS to cost  centre I am getting this error in IDES for CO Code1000.
    Balances have been found in 1 currencies with the following details:
    Currency type Amount Currency
    40            0.04  USD
    (A maximum of three differences are listed)
    Pl suggest what to check
    Thank You.
    Regards
    Man

    None

  • Profit centre error while vendor rebate settlement

    Hi
    this is regarding vendor rebate settlement TC- MEB4.
    while settlement of agreement, system is not able to determine the profit centre, hence unable to post the entries. in this regards, i have checked following:-
    1. material used in rebate agreement - profit centre maintained
    2. field status of all GL used in settlement process is optional for profit centre and cost centre
    3. in document splitting, categories of the GL's are Balance Sheet Item and Revenue
    4. field status of the posting key also open for profit centre
    5. document type is defined as Unspecified posting in splitting
    do i need to look some other place for possible cause of error? please revert
    Regards
    DD

    If you have mainatained the Rebate as accrual based on agreement adn Sales conditions then you should use Item Category as "01300-Cash Discount Clearing".
    Change and try in atest system and while changing the category read the warning message carefully that the system issues and understand the implications.

  • Dimension 1 Cost centre field is not able to edit in Incoming payment for Down payment Request

    Hi Exports,
    I am facing an issue on selecting Cost centres in Incoming payment screen.
    Issue: While I am booking the payment entry for Down payment request, I am not able to select first Dimension cost centre in Incoming payment rows for down payment request document, the Second dimension is able to select and update. the field is in non-editable mode (only on specific document row)
    Setup:
    1. Two Dimension are enabled
    2. In Separate Columns - Both Cost Centres are in separate column
    The above issue is only for Down payment request, for other documents (Invoice) I am able to select and update cost centre
    Please find below snap shot for reference
    Kindly check and let me know the solution
    Regards,
    Kiran

    Hi Gordon,
    Thanks for your reply.
    Yes agree, The Down Payment request is not a financial document but the Cost centres are able to select in Down payment request rows, no issue at all in this case.
    In Incoming payment screen it is necessary to select Cost centres because it has financial implication using down payment request with related to currency difference or Bank charges (both are Expense accounts) and DR assignment is mandatory in this case.
    And you have to notice one thing in above issue, I am able to select second dimension cost centre and it is allowing to edit and update the cost centre on respective row. Only issue is specific cell (dimension 1 cost centre) is not able to edit.
    Even I am not able to process payment entry without selection of Cost Centre on first dimension, the system is blocking and displaying the error message "DR Assignment is mandatory on Dimension 1 for specific account"
    Looks like bug, please clarify
    SBO version: 9.0 PL 11
    Regards,
    Kiran