Cost centre mass changing

Hi
I have arount 800 cost centres from 3 different co.codes A,B,C. which are to be changed to co.code D from the beginning of the new year.
i m trying to do through collective processing but what about profit centres attached to those cost centres.
there are some postings in it which do not allow me to change the co.code in profit centres . how do i do mass changing for them

Hi Milind,
Good evening and greetings,
Normally from the controlling aspect it is better to clear of the balances lying in the Profit Centres before you do the mass change so that in future there would be no need for reconciliation.  Considering that, you can do a mass change of Profit Centre using KE55 and if you want to change the company code assignment in Profit Center you can use KE56 for changing the same.
Anyhow if you are going to process this from the new year, then clear off the balances to a dummy profit centre and do the mass change.
If the answer found useful, please reward points.
Thanking you
With kindest regards
Ramesh Padmanabhan

Similar Messages

  • BAPI for cost centre create/change

    Hi,
    Is there a BAPI for Cost centre create and change?
    Thanks in advance.
    Regards,
    Arun Mohan

    Hi Ravi,
    My system is 4.6B.
    I found BAPI_COSTCENTER_CREATEMULTIPLE,
    but the BAPI for CC change is not present.
    Is there any other BAPI for CC change?
    Arun

  • Cost centre Name Change

    Hi Experts,
    i have few cost centres i want to change the name of these cost centres.
    For exp-
    Cost centre name       -  GSMPTA35
    Description                 - GSM FWP
    how can i do it. please advice

    You can use KS02 or OKEON to change the name.
    I hope it is really the name and not the technical name that you want to change, because the technical name can not be changed.

  • Custom Search Help for Functional Area of Cost Centre(KS01/KS02)

    Hi,
    I need to implement a custom search help and custom enhancement for the field Functional Area in Basic Data tab of Cost Centre Create/Change(KS01/KS02) transactions. Details of the requirement are as below:
    1. There will be a custom relation for the Cost Centre category and Functional Area which was maintained thru a SAP standard table TKA05 and a custom table.
    2.When the relation to Cost Centre category and Functional Area is a one to one it exist in the TKA05 and if its one to many it will be maintained in the custom table.
    3. The requirement is when the Cost Center to Functional area is maintained in table TKA05(One to One) in this case the corresponding Functional Area needs to be populated automatically after entering the cost centre and pressing a enter key by user.
    4.When the Cost Centre Category and Functional area does not exist in table TKA05 and existing in custom table(One to Many) in this case the F4 should be enabled for user selection with the list of Functional area values corresponding to the cost centre category entered that are maintained in the custom table.
    As per the functionality provided by SAP the input help(F4) of the field Functional area in Cost Center does not have any relation with Cost Centre Category. The existing F4 is from the Value Table(TFKB) attached to the domain of FKBER.
    Please provide your valuable inputs to implement the above requirement. Your input will be rewareded.
    Thanks in advance,
    Regards,
    Prasad.

    kalyani,
    i can see your requirement in below way..
    as it just reads: you need to assign the standard cost center help to a z cost center field in component /SAPSRM/WDC_UI_DO_ACC.. which actually is fetched though the component /SAPSRM/WDC_UI_BACKEND_SH
    so, if you see the component controller of SAPSRM/WDC_UI_DO_ACC you will see the component
    USAGE_SH_F4     /SAPSRM/WDC_UI_BACKEND_SH                        
    USAGE_SH_F4     /SAPSRM/WDC_UI_BACKEND_SH     INTERFACECONTROLLER
    so you can replicate the same functionality for your z field.
    but can you clarify one thing.. why are you going for this z field in place of standard field ?

  • RAPOST2000 error as Cost Centre blocked

    Hi
    Would like to check with you on the monthly depreciation posting as if one of the cost centre of assets was blocked:
    1) 4.6C RABUCH00 run in background and failed as certain cost centre was blocked. The job re-run and the system will prompt user to enter the correct cost centre WITHOUT changing the cost centre in the respective asset master.
    2) ECC5/6 RAPOST2000/AFAB run in background but flag out error as the cost centre was blocked.
    For that scenario, does that mean we need to change the cost centre in the respective asset master IF we do not want to unblock the primary posting of the cost centre?
    Pls advise and thank you so much.

    Hi Claudia,
    this issue arises very often with the new depreciation run. But the main question should not be "how can I change the cost center within the posting so that the depreciaiton run does not fail". Because if you changed the cost center in the past processing the Batch Session, you definitely created an inconsistency. The cost center stored in FI-AA tables has not been the cost center being used in the FI and CO documents.
    If you do not need that consistency, it is in the users responsibility. But personally I doubt this procedure.
    So personally I agree on Pauls statement, it is - from my personal opinion - more reasonable to spend some time assuring data consistency, then to skip system checks accepting side effects and inconsistencies.
    Regards,
    Markus

  • Way to mass change cost centre in positions

    Hi Experts
    We have a scenario, where the client i srequired to change the cost centre for multiple positions. Is there any report by which this can be done at one go.
    Regards
    Saurav

    First of all, u r talkin abt positions and cost centers....
    i would like to know ... how u mapped ur Costcenters to Positions ?
    did u maintain relationship thru Org Unit ? realtion ship A011 ?
    Then simple change Cost Center of Units accordingly, this would take hardly 10 min.
    Otherwise, use BDC to change the relationship for each position....from the date of effective.
    Option Move in PPOME is very useful for mass changes... like selecting n number of positions together and moving to required units
    Regards
    ...Sadhu

  • How to change validity period of cost centre or activity type

    Hi
    How to change validity period for an Activity type or Cost centre?
    Can we change the validity period once created?
    regards
    Prakash

    Please note this can be done.
    Go to Edit Cost Center
    Goto Edit, Analysis Period.
    Create a new validity period say today until 3112999
    Change the data you want and save.
    When you go into the CC again it will show two validity periods.

  • How to change cost center in asset master data through mass changes

    Hi sap gurus,
    Hi i have 20 assets i have to change the cost center through mass changes provide the solution.
    regards,
    ramanjaneyulu.

    Hi,
    For 20 assets it won't be useful to write a CATT or LSMW. So, either enter it manually or you could correct directly in the tables (ANLZ), though it's generally not recommended.
    Regards,
    Eli

  • Change the profit centre in the cost centre master after a year

    Hi All,
    Could you'll please let me know whether it was possible to change the profit centre in the cost centre master and if i did what will be the implications.
    Thanks and Regards,
    Vandana

    Refer transaction code OKEG.
    You can maintain master data for cost centers, cost elements, activity    
    types, and business processes with time dependencies. You can make        
    changes at any time for any given time interval. Data storage also takes  
    place with a time reference. In this way, a master data record can have   
    multiple database records storing different information.                                                                               
    The smallest interval is one day. To ensure data consistency, you cannot  
    change each field daily. The timeframes in which you can change a field   
    depend on the field functions, which are fixed by the system and cannot   
    be changed. Master data maintenance includes an automatic check for each  
    field's time-based consistency, resulting in individual time-based        
    maintenance for each field.                                                                               
    The following dependencies are supported:                                                                               
    o   Not time-based                                                                               
    o   Day-based                                                                               
    o   Period-based                                                                               
    o   (Fiscal) year-based                                                                               
    This function provides an overview of the time dependencies of           
    individual master data fields during master data maintenance, along with 
    checks and storage of consistency timeframes. You find this information  
    in the "Time dependency" column.                                                                               
    If you use fields requiring characteristics greater than one day and     
    which are changed for the system lifetime of the object, the system      
    automatically creates a new database record for this processing          
    interval, and changes the time-based validity of existing records. The   
    change is logged in the master data record with the time reference.      
    However, a great number of changes in multiple timeframes will result in 
    a correspondingly great number of data records.                                                                               
    Fields which you can change freely (indicated in the DAY column) can     
    possess different time dependencies only if you mark them additionally   
    as historically relevant. This activates the time-based updating for the 
    records.
    Object 1000 has one master data record created with a fiscal year of 12 
    periods and the cost center name AAAAAAAAAA. During master data         
    maintenance, you change the cost center name in period 5 to BBBBBBBBBB. 
    The system reacts with one of two options.                                                                               
    o   "Name" is marked as historically relevant. The existing master data 
         record for periods 1 - 12 must now become three records:            
         1000   01-04   AAAAAAAAAA                                           
         1000   05      BBBBBBBBBB                                           
         1000   06-12   AAAAAAAAAA                                                                               
    o   "Name" is not marked as historically relevant. The existing master  
         data record remains intact, with the name changed for the entire    
         existence of the record:                                            
         1000   01-12   BBBBBBBBBB
    Edited by: Ravi Sankar Venna on May 19, 2009 4:03 PM

  • Retro payroll processing for org unit cost centre changes

    Dear All,
    We have created some new cost centres and assigned  it to relevant org units . when we run payroll , retro run is happening from the period we changed the cost center and assigned the new cost centre to the org units . please suggest a solution
    regards
    Tressya

    Hi Tressya,
    changes in IT0003 won't affect retro calculation, since you have already created result periods for retro calculation. The payroll programm will detect this and allways will repeat the retro unless you delete those results first.
    Try TR PU01 during correction - then clear Earl.pers. RA date  by PU03 (PA30 won't work here)
    After that you hou'll have to repeat payroll run for effected employees to get new results for actual period only.
    regards
    J.

  • MM - Pricing Conditions - Mass Change for Planned delivery costs

    Dear gurus,
    Is there way to mass change the value of pricing conditions of Planned Delivery costs in the PO? Also the supplier?
    Any suggestion?
    Many Thanks for helping,
    Maria

    Hi,
    As far as I know, this can be done for condition type/vendor price maintained in info. record.
    Transaction code: MEKP
    Enter the condition type, enter the '+' sign if value is to be raised.
    If you tick the 'Test Run' you can also simulate the condition (old v/s New).
    Hope this helps!!
    Reetesh

  • How to Mass change cost centers for assets

    Dear All,
    I have change the cost centers for about 1500 assets. I am not sure if there is an easy way to do it. Is there any way to get this list in excel and upload?
    I am using ECC 6.0 (I think CATS could not be used.. but I might be wrong). Thanks in adv for your help.
    SD

    Hi
    I hope the above given suggestions will not fullfill your requirement,
    Do follow the below steps for carrying out mass change of cost centers in asset master data.
    Enter t.code-AR01 - Generate
    Enter your Co.code and the assets numbers for which the cost centers have to be changed and execute.
    In the next screen select Create worklist (CntrlShiftF8)
    Give the worlist a Name and select-Change asset w/o dialog (bulk change) and press enter,from the next pop up select create Substitution,where you will be taken to creation of Substitution rule.
    Write a Substitution as per requirement and assisn the same to your company code.
    Where  you will be prompted with a message "Work queue XXXXXXXX added".
    Now enter into AR31 - Edit and release the woklist and see that your mass change of cost centers is carried out.
    hope this might help you in doing mass change of cost centers in asset master record.
    Good Luck
    Hari

  • Mass change of profit centers in Product Cost Collectors

    Gurus,
    My client has a requirement of mass change of Profit Centers in Product Cost Collector (Transaction Code KKF6N). Is there any way of doing this using LSMW or anything else?
    I had tried with LSMW Recording, but there is a particular production version associated to profit centers in KKF6N tranasction, because of this I couldnt go to particular production version and update the profit center.
    So, Is there any easy way doing this?
    <REMOVED BY MODERATOR>
    Thanks,
    Kalikonda.
    Edited by: Alvaro Tejada Galindo on Jun 9, 2008 6:29 PM

    Kiran,
    I have tried with Recording and problem solved.
    Thanks,
    kalikonda.

  • Mass change of Profit center in Cost collector

    Hi
    On FERT materials profit center was and i have created cost collectors for all fert materials.
    How I can correct mass change of profit center on Cost collector.
    ty

    Hi,
    You can use the MASS transaction code for changing of Profit Center for your FERT Materials.
    Sateesh

  • Change Profit Centre in Cost centre

    Hello Experts,
    I have to change profit centre in cost center (postings have been done on cost centre), how can I do ?
    Thanks in advance.
    Regards,
    Catherine

    Hi,
    Once you post transaction to the Cost Center, we can not change Business Area or Profit Center assignment for the same Fiscal Year.
    System will allow changes for the subsequent Fiscal Years though.
    You cannot really reduce the number of Cost Centers. However we can restrict the validity period though. You can delete the Cost Center validity for the dates that do not have transaction with in the same Fiscal year as well.
    Hope this helps
    Regards,
    Som