Please note this can be done.
Go to Edit Cost Center
Goto Edit, Analysis Period.
Create a new validity period say today until 3112999
Change the data you want and save.
When you go into the CC again it will show two validity periods.

Similar Messages

  • Blocking of Cost centre and activity type

    Dear all,
    Please tell me how to block cost centres and activity types which will no longer be used
    best rgds,
    Manoj

    Hi,
    There are two ways .
    If you wish to use the cost center number for any other cost center , then you need to delete the cost center by KS04 & you need to mention the future period for which the same should deleted, normally, starting would be 1st day of next year to 31.12.9999
    Keep in mind, cost center can only be deleted , if no data (Actual/Plan/reversal) is posted in it. You may do it , before starting next year's budget processing.
    If you wish to just block the same , lock Actual primary/Secondary & Plan primary/Secondary in the control tab.
    Regards,
    Deepak Kolwankar

  • IW41 using HR data (cost centre and activity type)

    Hi all,
    Does anyone know the steps required to make IW41 determine the Cost Centre and Activity Type from the HR master?
    We can change the Activity Type by user-exit CONFPM04, but not the Cost Centre.
    Also posted [here|http://www.sapfans.com/forums/viewtopic.php?f=7&t=329923].
    PeteA

    Hi Pete,
    Which cost center field are you using? SKOSTL (sender cost center) should be changeable in export structure AFRUD_EXP. It is this field that is written to the AFRU table (not KOSTL). I did a quick check through debug and it looks possible to set a value in the exit that gets written to AFRU-SKOSTL.
    -Paul

  • Change Validity Period of Cost centers ??

    Hi,
    Is it possible to change the validity period of cost centers ??, like in my case we are having validity period until 12/31/9999, so because of this even when some one blocks the cost centers they still appear in the F4 list of cost centers!!! used at many places to search for cost centers.
    My requirement is to restrict the blocked cost centers from appearing in the search help list for cost centers.
    Thanks.

    Hello Rahul,
    Validity of cost centers can be changed in transaction OKEON : Standard hierarchy of cost center change.
    Select your cost center, In basic data tab you can change the validity dates.
    This should help.
    Thanks
    Ashutosh

  • Change validity period of cost center from 2009 to 2008

    Hi All
    I have created a cost center with validity period 01.04.2009 to 31.12.9999 which was supposed to be created from 01.04.2008 to 31.12.9999. when trying to change the validity period in Tcode KS02 I am getting the following message -
    "New analysis period must not exceed maximum period limit". In TCode -  OKEON the validity period button for that particular cost center is deactive. 
    In TCode KS13 when I generate report for that cost center with Parameters - Valid from 01.04.2008 to 31.12.999 I can see that the cost center is valid from 01.04.2008 to 31.12.9999.
    In TCode KS03 Display Cost Center the cost center is valid from 2009 which has to be valid from 2008. Please advise on how to change the validity period from 2009 to 2008.
    Regards

    Hi Eli
    Thanks for the reply and I have successfully created the cost center to be valid for the previous year as per the requirement.
    Thanks & Regards
    KIMKhan

  • Validility period of cost centre

    hi,
    can anybody tell me how can i change the validity period of cost centre and cost element ???
    ankur

    cost centre and cost element validity can be changed In KS02 AND KA02 we can click on Edit Tab - analysis period - other analysis period at the bottom.
    or for the cost centre we can also change in -  spro - controlling- cost centre accounting- master data- cost centres- define standard hierarchy-   u will find the cost centre basic screen at the bottom
    Beside the analysis time frame u will find small icon set analysis time frame where we can change.
    thanks

  • How to change validity from.. to dates in cost centre(production) ?

    Dear All,
    We have created cost centre(production) on current dates ? Due to this,
    We were unable to maintain activity price for work centre.
    Message is telling us to maintain activity price for current fiscal year.
    How to change validity from date in production cost centre(KS02) ?
    Appreciate valuable inputs.
    Jeyakanthan

    Dear ,
    1.Go to Transaction Code KS02 - change cost center and in the next screen go to Menu bar > Edit > Analysis Period.This will pop up another window - in this you can change the analyis period and save it.
    2.Or Use the tcode OKEON from the hierrachy choose the cost center in the basic data tab u will see one button named Validity period.Change the validity there.
    3.You can do it using 'KSH2' transaction.Open the hirarchy and select your cost center. now select the business area and new hirarchy node where you want to move it. and click on 'INSERT AT LOWER LEVEL' to move the cost center from one business area to another.
    Try and check
    regards
    JH

  • Urgent:How do i change the validity period of cost element !!!!!!!!

    How do i change the validity period of cost element like:
    From 03/01/2008 to 01/01/9999
    To 01/01/2000 to 01/01/9999
    Please help me.I will assign you points.Thanks in advance.

    hi,
    pls go to t.code ka02 and select that particular cost element and go to menu bar and select edit -analysis period and select other analysis period there we can change
    if it is useful to you pls assign the points
    Thanks & Regards
    phaneendra

  • How to find out Plant wise Cost centre/ Profit Centre

    Hi Guru
    My problem is How to find out plant wise cost centre. To be more clear------ I want to know what cost centre is valid for a particular plant
    My mail Id. [email protected]

    Hi,
    Then this explains the problem.
    The message number starts with a Z and so it is not a standard SAP message because SAP does not link cost centres or GLs to Plants
    But also, the message doesn't indicate a problem with the link? it is stating that you should check that the GL account and the PROFIT CENTRE are valid for the posting for the period???.
    It looks like someone has written a custom modification  in your system and so we are , unfortunately, unable to help because the data would be in custom tables and not standard SAP tables.
    You can only solve this problem by speaking to someone within your own company who knows the mdofication that has been done.
    Sorry
    Steve B

  • How to change company code in cost center master

    Hi,
    Can anyone throw me the light about how to change company code in cost center master? User make some mistake. They maintained wrong company code in cost center master and there are some transactions already posted to this cost center. I would appreciate all attention and point will be reqard. Thanks much
    Best Regards,
    Bird

    Hi,
    The cost center master data fields have time dependancy.  Following are the details of time dependancy.
    You can maintain master data for cost centers, cost elements, activity types, and business processes as time-based. Changes to any other time interval are possible at any given time. Data storage is also time-based. In this way, you can store multiple database records for a master data record, each holding different information.
    The time-based dependencies are determined by SAP and cannot be changed. The following dependencies are possible:
    Not time-based
    Day-based
    Period-based
    Fiscal Year-based
    Cost Center's company code field's time based dependancy is Fisal Year Based and hence, the company code can be changed on cost center only on new fiscal year.  And hence, system will not allow changing company code on cost center master data until new fiscal year if transactions are posted to the cost center.
    You may have to think of work around :
    1) Create new cost center with correct co code
    2) Repost the cost posted to old cost center (with wrong co code) to the new cost center.
    Explore the possibility of this work around on your system with the key user and then see whether this option works out.
    Hope this helps.  Pls. assign points if this is helpful.
    Regards,
    Chirag

  • How to change purchase order's cost center in batch

    Dear all :
    how to change purchase order's cost center in batch?

    Dear Manish :
    thanks so much for you reply.
    the filed which i wanted to change it's content is cost center (KOSTL) in table EKKN.
    i couldn't find it in this t-code when i select fields.

  • How to change validity in info record

    dear experts ,
    how to change validity in info record
    Srithar K

    HI,
    Tocode - ME12
    Enter Vendor code and Material and press enter button.
    After you can change the Validy on Date.
    Regards,
    PK.

  • Send cost centre and attendence type not filled automatically

    Hello,
    I am configuring the time recording in ESS. I configured the recording profile and in cats2 it looks good. The send cost centre and attendence type get filled automatically. But when I do the same thing in ESS the values are not populated. Is there something I have to take into account in order to get this done?
    Thanks a lot, Vanessa

    Dear Venessa,
    Please note that in contrast to personal templates, which enable you to prefill the data entry area when you start time recording, the system first displays default values when you create a new account assignment row with one receiver object and at least one working time.The system only proposes default values when you create a new account assignment row. In ESS, this is correct, because it does not make sense to provide default values for the sender cost center and activity type if you are only entering an attendance or absence type.
    Hope this helps,
    Regards,
    Roy

  • CAT2 - How can I see the rate assigned to an activity type?

    In transaction CAT2, there is a column named ActTyp (Activity type). How can I see the rate assigned to this activity type (example: 50$/hour pour activity type Project management) ?
    Thanks,
    Julien

    Hi Julien,
    plz goto KP26 and enter the acitvity type and cost center of the work center and check the price ..
    regrds
    pushpa

  • PM Order Confirmation using Personnel's Cost Center and Activity Type

    Hi All,
    Is it possible to have PM Order confirmation (IW41) using Cost Center and Activity type from Personnel instead of default from Work Center?  If it is, can it be done with some configuration or user exit?  Please advise.  Thank you.
    Dai

    Hi friend,
    Order confirmation will be done for order operations.While doing confirmation we post the actual work done by the repective work center and respective activity type assigned to the same workcenter.
    But these activity types are assigned to cost center for cost calculation.confirming the respective operation in maintenance order through workcenters gives the report of planned work and actual work done by the respective workcenter.
    We cannot confirm the operation using costcenter and activity type directly through transaction IW41.
    If you want to develop new confirmation screen and making confirmation of the respective order operation with only costcenter and activity type fields, you can do it .
    Regards,
    Pardhreddyc
    Edited by: Pardhreddyc on May 17, 2011 12:45 PM

Maybe you are looking for