Cost Model

Hi Experts  ,
i am using ECP for one of my requirements and it is a construction project .I have created  characters (Lenght , Bradth and depth) for one of the cost models and for one line item (First line item )in the cost model let us say for an example , For  concreting a column i enter the respective values for character (Length , Breadth and depth) and the quantity in the form of values are picked from these three characters as defined in the derivation rule.
When i am trying to  enter the values for the second line item for the beam, the system i is picking the first values which were entered for Characters for first line item .
Please let mw know  whether am i missing some thing in this process as my requirement is i want to use the same characters but the Values  that are being entered for each line item shall vary .
Please help...
Reg
Judy

Hi Judy,
May be you can try to automate the process of calling the sub divide function by modifying the derivation rules. You can create a characteristic called " No. of items" ( Numeric ) and use it in the planning form.  In the derivation rule, use Type as "Costing model"  and enter the same Costing model in the "Object". In activation  you can define the value with respect to this characteristic.( say XYZ = 3 ). you will have to configure in such a way that if user enters 3, then three Planning forms will appear..if entry is 4 , then four costing models will get populated.
With this arrangement, the costing models will populate automatically , thereby reducing the user workload.
Hope this helps.
Warm regards,
Srinivas Potluri

Similar Messages

  • Easy Cost Planning-prob Costing model

    Hello ,
    I am creating costing model
    i want at time of Easy cost planning  court fee(Characteristics)   to be selected from drop down list
    i have made characteristic court fee ,in currency format
    (CKCM) while defining derivation rule(template), if i am mentioning quantity as court fee
    Facing error that Syntax error in quantity
    Pls help
    Thanks

    After Double click on Qty , you have to define the formula there,
    correct your Formula which may be wrong leading to Syntax Error.
    Regards,
    Nitin

  • Easy Cost Planning: Calculation Row (Business Process) in Cost Model Derivation Rule

    Hi All,
    The Requirement:
    Using the Cost Model I am able to do up to Sub-Total Value.  I tried with Calculation Row (Business Process) in the Cost Model Derivation Rule, but could not succeed. 
    I tried with Base Planning Object, but the formulas are different for other scenarios.  Which require 5 to 6 Base Planning Objects are required to be created to get the total amount for a single line item, in the construction project there will be more than 10,000 line items and it is very difficult to maintain the data and also it is time consuming.
    Can you suggest me, how to map the requirement?
    Best Regards,
    K. Rajendra Prasad Rao

    You need to check the following for the material cost to appear in network costing:
    1. Check whether costing variant is assigned to the network or not.
    2. Check whether costing relevancy indicator is checked in material component assigned to the network.
    3.  If costing variant exists, check the valuation variant and strategy sequence for material valuation.
    4. Go to the material master and see whether price is mentioned  or not.
    I would suggest you to use Network costing, Also note network costing are recorded in Co version '0' so if you have maintained your ECP for '0' version, there is a chance of both the costing getting added up.
    Edited by: Ahmed Rifaee on Mar 28, 2010 10:10 PM

  • Is Costing Model (ECP) Transportable

    Team,
    I need to create near to 100 forms in CKCM for using in Easy Cost planning. Is the costing models created in CKCM is transportable to production server? While creating I didnt get any transport request and as per BASIS people its a transaction data and cannt be moved to production.
    what is the best practice following while using costing model; how the testing and quality check is performed for such forms if we are directly creating it in production.
    Thanks in advance
    Reg/ Tony

    Thanks
    Summarizing for future reference
    Step 1
    Transfer the Characteristics to Target system- Use CT10 to download the Characteristic list and LSMW with object 0150 to upload
    Step 2
    Use SE38 and CKECP_EXPORT_MODEL in original system and SE38 and CKECP_IMPORT_MODEL in target system
    Points to remember
    Ensure that all the values are available in target system like Unit of Measurement etc
    Ensure the cost element is defined
    Ensure the material numbers are same in both systems

  • ECP Costing Model Load

    Hi Experts,
    I am currently tryin to develop a solution to create a large number of ECP costing models from inputs provided in a spreadsheet. Is there any way to do this without having to manually key the data?
    Any help would be greatly appreciated.
    Cheers,
    Glenn

    Hi
    Your ABAPer can throw some light on the possibility with BDC.
    This cannot be done with LSMW.
    regards

  • Cost model derivation rules error

    Hey PS upgraders,
    We are upgrading 4.6c to 6.0. When I m uploading the cost model from 4.6c to 6.0 thru CKCM , derivation rules are missing in 6.0.
    Does any one come across this kind of issue in 6.0.
    Thanks,
    Krishna Reddy
    Edited by: krishna.gujju on Jun 17, 2010 11:59 PM

    Hi guys,
    any idea!

  • Sample data for Revenue model and sales cost model

    Can someone provide some sample data for the following model
    Sales Revenue
    sales Cost
    Thanks

    Hi,
    you can generate your own sample data, Take a look at this document:
    http://www.sdn.sap.com/irj/scn/index?rid=/library/uuid/804b8088-1853-2e10-c78d-f60e7af3d633
    hope it helps,

  • DOubt in CJ20N Transaction with Costing Model

    Hello experts,
    I have a Requirement which is as Follows:
    After Entering to Transaction CJ20N, i am choosing the Project definitions, and after that choosing the
    Project Structure and then the Easy Cost Planning.
    My Requirement is I should modify the Form by Placing an approving Button in that.
    The Details will be filled in that Form. After filling that, The manager can View that Details by entering in the same  Transaction.
    Once he Click the Approve Button, the details which ever entered by the users should be Reset to all   other than the Manager.
    so Experts Pls help me to Complete my Requirement.
    Thanks,
    Raja.

    Via workfolw you can send any type of  approval to project mgr / project team member  etc.
    If I say in general via workflow you can send workitem in the user's sap inbox in the form of email. user can approve /reject /modify that work item and give back to the reqester. If user has modified/approved/rejected  that changes will get reflected SAP.
    your technical can chekc that is that standard Business object is available for your Form. if not than they can customised the same.
    Perticularly i have not used form as workitem. The situation i have narrated on that scenario i have worked.
    I request you to ask the same in PP forum. because thae also use the txn CKCM.
    Regards
    Nitin

  • Develop cost model to integrate process

    I'm looking for help to calculate the cost benefits of moving from a 3rd party engineering interface to full SAP integration.
    We are ultimately upgrading from R3 4.6c to eec 6.0.
    I envision full CAD integration with PLM/DMS Replication, Collaboration.
    I need a contact within SAP to help me rationalize my thoughts and goals.

    Hi Larry,
    There is a lot of cost/efforts advantage in store for you, when you integrate the PLM to ECC 6.0 environment.
    Some of the PLM concepts like Receipe Management, EH&S come ready and will be just a plug and play affair.
    CAD integration has been greatly improved with improvements to Engineer's workbench.
    Please share on any specific information around mySAP PLM, that you are looking for.
    Regards
    Vikas Gupta
    [email protected]

  • Calculated field in model of easy cost planning

    Hi,
    I would like to introduce the cost model easy planing a calculated field (characteristic), which was the multiplication of two fields (Characteristics).
    I have entered into the transaction CKCM "Easy Cost Planning: Model", I created 3 Characteristics (A,B,C)through the option
    "Assign Characteristics to the model."
    I entered the "Define the derivation rules (template)" and created a calculation with the two characteristics( C = A * B). The problem I have is that I did not enter the calculation in characteristic 3, which is what I want to pick up the value.
    Many Thanks.
    Regards.

    Hi Vivek,
    Thanks for answering.
    My question is, how I can assign a  calculation in a characteristic?
    Characteristic A
    Characteristic B
    Characteristic C = A * B
    I want the easy cost planning screen, enter a value in the characteristic A and B, it will automatically calculate the C and view the calculation in the screen in characteristic C. As I can do?
    Thank you very much.

  • How can Oracle ERP system reduce the total cost of ownership

    i have read a report that describe the advantages of using Oracle ERP system in different organizations ; it is mentioned that
    "+Oracle’s ERP solution suite helps customers achieve 30-80% lower total cost of ownership, benefit from a predictable cost model, and reduce risk+".
    So does this means that Oracle ERP system reduce the total cost of ownership because it provides cheaper price comparing to other ERP providers, or it is meant that using Oracle ERP system will reduce the total cost of ownership for other assets in the organization by 30-70% ?
    Thanks

    My thoughts:
    1) Oracle ERP (or any ERP) typically replaces numerous applications. Each of those applications needed separate licensing fees, separate support mechanism, and separate employees in your organization to support them. By consolidating into one, it is easier to support it.
    2) Normally, Oracle ERP is cheaper than SAP but it certainly not the cheapest ERP in the market. There are some smaller ERPs which are cheaper but may not offer the breadth that Oracle offers. In fact, Oracle offers a small business ERP that is quite cheaper than EBS.
    Sandeep Gandhi

  • Easy Cost Planning & Project Stock

    Dear Experts,
    I am using Easy cost planning for WBS cost planning and Project definition control data tab page has Valuated Project stock selected.My costing model had an external procurement material for which I generated PR & PO thru Execution services.But the account assignment in my PR & PO was P with the corresponding WBS as account assignment and not Q.
    I have two question regarding this,
    1) Does it mean that while using ECP, Project stock concept will not work?
    2)How can we get the pop up of procurement type options(like Res + PR for WBS element) while generating PR through execution services?

    Hi,
    I am replying again because in my last answer there was some typing mistake.
    Hi,
    I tried your scenario is my system.
    whenever i am changing P to Q in Config in SPRO,It is giving an error that "The selected account assignment category is not supported" that means it is not meant for Q but i double click for object type PR WBS Element and changed Acct Assgmt Cat to Q then system allowed me to save.
    The i create a PR and WBSE is coming in the Account Assignement ,then i converted PR to PO and then i recived goods as project stock.when i issued the material in ECP it is not issuing from Project stock because 221 Q is not present in Config for SPRO so it is issuing from Normal stock so special stock from ECP is not supported.
    But you can manually issue the material to the WBSE in MIGO/MB1A by 221 Q.
    Hope it is clear.
    Muzamil

  • Easy Cost Planning -Costing has already been completed. No changes possible

    Hi,
    I am in Easy Cost Planning tool and i would like to remove some items or add in some items.
    The system is giving a message that "Costing has already been completed. No changes possible"
    May i know where did we complete the costing(Transaction code?) such that no changes are possible on East Cost Planning tool anymore?
    Thank you.

    Hi,
    Check the Costing Model in CKCM and do changes as per your requirement.
    Now Use this costing Model in CJ20N while cost planning for wbse. you can change cost plan here also as per wbse specific requirement.
    regards,
    Hari

  • Easy Cost Planning (SAP) in Tender Process

    Hi All,
    I am using SAP ECC 6.0 EHP 4. I wanted to know if Easy Cost Planning in SAP PS can be used to cost a project initially while Tendering process.Or is there any other tcodes in SAP for tender process? I created Costing Models for most of the possible processes in a civil project and included the labour cost,equipment cost and material cost in it.By this way can we proceed implementing SAP in our tendering department.Looking forward for your valuable replies.

    Hi ,
    SAP has easycost planning objects available to cater to it. Process starts with inquiry.
    1) Create inquiry for customer request. Define service material in material field in VA11
    2) Create Project copying closest executed in part ( you have said 70% is engineered fresh, then project is 30 % correct at the time of copying)
    3) Amend project to add/chnage/delete components & network activities. Add miilestone payment you wish to propose in quotation.
    5) Add project no in inquiry (Accoutn assignment in Line item )
    4) Use DP81 traxn to create quotation.Easy-cost planning need to be configured to calculate price( Cost+ mark up scenario possible) There are possibilites to pull as many deatils as you wish in quotation ( As line items) from project structure. It is possible to list major assemblies that will be delivered to customer( Make- To - Order variations). It is also possible to replace Service item used in inquiry with 'Material masters' of FERT & itemization in Quotation. Milestone dates from project will be copied you can propose % billing arrangement at each date to customer.
    5) Able to revise quotation seamlessly & resond to customer changes/addtioal request. Revised quotation reflects your ability understand customer request & changes are seamlessly reflected in qty,  total price & dates.
    6) Upon confirmation of Sale, Sales order can be created copying quotation. All hard work/ iteration of commnucation with customer , need not be defined in system again. Order Acknowledgement will reflect agreements with customer.
    SAP E C & O best practice has few more addtion for Civil project ... how to measure % completion based on Mortar used & daily output of cement mixing. That will help,
    Regards,
    Jatin

  • Easy Cost Planning in a currency other than Cont Area and comp code curren

    Hi,
        I want to do the easy cost planning in a currency which is other than controlling area and company code currency.
      But I am getting the option of only these two currencies only.
    Any idea how to do it?
    Example:
      Controlling Area currency :INR
    Company Code Currency : AED
    Planning Currency to be used for Easy Cost Planning :USD
    Regards,
    B P Singh

    Hello,
    You may try to go to transaction CT04 - Characteristics. There in tab BASIC DATA you choose Data Type - Currency Format. In field Currency enter the required currency. Save the characteristic.
    Next step is to go to CKCM - Models for Easy Cost Planning. Open the Costing model and add line with the created characteristic.
    Good luck, Aleksandra

Maybe you are looking for

  • How to delete to-do list items in 5800 XM

    I transfered the data from my old PDA to Nokia 5800 XM. Now there are hundreds of to-do list items with showing up every day at the top of to-do list. I would like to delete lots of them. So, i can delete only one at a time. How do I select and delet

  • Turning sql  string (with dynamic columns) into a pipelined function

    Hi guys, I was working on an apex report the other day, and wrote the sql below (for those who don't know apex well, in an apex report you can define the columns at runtime.) When I was finished, I said to myself: "It would be great to have a pipelin

  • Flash image viewer works in preview but not online

    Hi I followed an online demo on how to get an image slideshow on my webpage using flash. It was using insert media image viewer. It all worked fine, looked great in the preview but when I put everything online I can't see it. Just an empty space were

  • Cannot connect to we when using facetime

    Cannot log into facetime with my IPAD mini. 

  • J1IEX-Excose part 2 posting

    Dear guru's, User is trying to post the Excise Part-2 by using the T.code : J1IEX , but he is getting the error message " Balance in transaction currency". Detailed Error message is "A balance has occurred in transaction currency 'INR' with the follo