CPr-PS integration - cProjects costs not showing up in PS

Hi,
We are on PPM5.0. Accounting integration results in successful replicaition of cPro structure as WBS in PS. However, the costs do not flow.
We have used PS06 (ECP) as the costing variant. All configurations seem to be done, and yet, we do not see the costs replicating.
Additinal Information:
We are not using "Org" structure. We understand that "Cost Element" and "Activity Type" aligned with the cost/revenue rate is all that we need to maintain for costing to take place.
Please advise on what we might be missing.
We are able to replicate all accounting charateristics including cost/rev rate, and project type to the ERP system.
The costing variant has been defined as PS06 (both under "Create and Change controling scenario", and "Settings for "Easy Cost Planning"). And yet, when we click on the "costing" button (under the "accounting" tab), we get the following warnings:
- Error occurred in controlling cockpit (and yet we see nothing in COCPCPR)
- Costing data may not be up to date
Please advise.

HI Deepak
Please advise how you got the planned costs to show up in PS.
I face the same issue now.
I have exactly the same settings as you have PS06 on both sides.
However, when i look at ECP in PS, it requests a planning form and no planned data is being pulled through, its just blank.
I am not sure what i could be missing, is a costing model mandatory ?
Please advise soonest.
thanks
Ihsaan Mayet

Similar Messages

  • CProjects to IO, IO to RPM - costs not showing up

    Hi,
    Having created an internal order from cProjects, I can see the costs in IO.
    To start with, costs from cProjects Role-Task assignment is all I am trying with (using role rates).
    Simultaneously, I have created the Finance Categories, Groups, and Views in RPM.
    I have tried a few juggleries to bring this cost under a finance view in RPM. Not through yet.
    I have run the programs that fetch this IO cost into RPM. But the link doesn't seem to have been estd. and therefore, though the program shows all green, it says there's no cost in the db to fetch.
    What all should I have completed before I get this through?
    Thanks...

    HI Deepak
    Please advise how you got the planned costs to show up in PS.
    I face the same issue now.
    I have exactly the same settings as you have PS06 on both sides.
    However, when i look at ECP in PS, it requests a planning form and no planned data is being pulled through, its just blank.
    I am not sure what i could be missing, is a costing model mandatory ?
    Please advise soonest.
    thanks
    Ihsaan Mayet

  • Landed Cost not showing in Inventory Audit

    I have a query that goes against the OIPF/IPF1 tables to locate all Landed Cost transactions for a particular item. To test/verify the query, I ran the Inventory Audit report for the item. There are transactions returned from the query that do not show in the Inventory Audit report. Is there any reason or circumstance under which a Landed Cost Transaction would not show in the Inventory Audit report. I checked against all warehouses. This does not seem to be a singular event in that I have found random occurences of this for different items yet the majority of the time the Audit Report returns all entries.

    Dear Cristian
    Please check the Following things.
    1)First check audit report for a Single Product.
    2)Select all warehouse in Audit report.
    3) Check you landed cost entry if your JV not pass in landed cost, so landed Cost not reflected in you audit report. (Auto JV not pass in SAP 2005 Version)
    Please check and Let me Know.
    Regards
    Mangesh Pagdhare.

  • Internal Activity Costs not showing

    Dear all,
    I'm creating a production order and all my work center activities are not being costed nor showing. I've made sure my activity types have "variable" rates from kp26 and I made sure they're assigned to the production operations and shown in the production order operations list.
    I'm also facing this when I run ck11n.
    What could possibly be wrong?

    Hi,
    A few quick checks
    1. Check if the operation is relevant for costing (control key)
    2. In KP26, click on the first icon at the left hand top corner & check if the rate is mentioned for the present month.
    I suspect that the 2nd point could be the issue. Check & revert.
    Regards,
    Vivek
    Added
    Rafiq, you've marked the thread as answered, but not bothered acknowledge the inputs provided nor assigned any points. Great way to appreciate the forum members....!!!!
    Edited by: Vivek on Jun 18, 2009 6:27 AM

  • Idoc to flat file using Integration process does not show up at all

    Hello All,
    I created a scenario IDOC to Flat File using Integration Process and one without IntegrationProcess. I am able to execute the one without Integration Process easily.
    However when I send the IDOC from SAP then the Integration Process scenario just does not work.
    I Checked SXMB_MONI  There is no entry for the Integration Process.I can see entry for other without Integration Process.
    SXI_CACHE : I can see my Integration Process active
    SWEQADM :  I have activated the Event Queue and Background job
    SWF_XI_ADM_BPE :  ALL BPE is showing green status.
    All syntax check on IP are fine.
    There is no Basis Help for me so  there could be some additional basis steps which need to be configured.  Has anyone faced such an issue with Integration Process?
    Regards
    Prashanta

    Hope this might help you. when u configure an IDoc as Sender with BPM this is how you proceed.
    <b>1<b>. let us split the scenario into two</b>.</b>
    a. <b>Sender to BPM</b> ( Integration Process).
    b. <b>BPM to Receiver</b>.
    <b>2. First let us configure the first Sender to BPM.</b>
    a. Sender Agreement( <b>Not required</b> ).
    b. Receiver Agreement( <b>NOT Required</b>).
    c. Receiver Determination( Sender Service, Outbound Interface, Receiver Service(<b>Integration Process</b>).
    d. Interface Determination( Inbound Interface(Sender Abstract Interface), Message Mapping(NOT Required if your using transformation stepin Integration Process)).
    <b>3. Now let us configure the Second BPM to Receiver.</b>
    a. Sender Agreement( <b>NOT Required</b>)
    b. Receiver Agreement( Sender Service(<b>Integration process</b>), Receiver Abstarct Interface,Receiver service, Inbound Interface).
    c. Receiver Determination( Sender Service(Integration Process), Receiver Abstarct Interface,Receiver Service).
    d. Interface Determination( Inbound Interface, Message Mapping(<b>NOT Required</b>)).
    So Finally we have <b>One Receiver Agreement</b>, <b>Two Receiver Determinations</b>, <b>Two Interface Determinations</b>.
    Please let me know if you have any more queries.
    Regards
    Gopi

  • Integrated web cam not showing any picture or video

    In my compaq 610 laptop i have integrated hp webcam.
    After double clicking the hp webcam icon, the software interface is coming on the desktop,
    and also the blue light near camera on monitor panel is getting switched on
    but there is no picture or video is coming in that software interface.
    Not even in skype or gmail chat plugin.
    Wghat could be the problem?
    help me.
    Thanks

    Have you tried upating the latest version of the Webcam driver from the support and driver download page on www.hp.com? Also try updating the BIOS on the unit.
    Although I am an HP Employee, I am speaking for myself and not for HP.
    Make it easier for other people to find solutions, by marking my answer “Accept as Solution” if it solves your problem.

  • SSIS 2012: Integration Services Catalog not showing data for most recent executions

    Techies--
    Under a previous deployment of an SSIS package, I was able to go to the Integration Services Catalog, look under the  folder-->project--> package  then right click and request a standard report for all executions. The report would display
    the execution details.
    Today a colleague recently deployed a newer version of the same package to a test server... which is failing from a job set up via sql agent.  I went to look at the root cause by going to the Integration Services Catalog to review the report. No execution
    data appears.  I looked at the filter--compared it to the filter I have set on the production copy of the stable version. The folder name, package name and project name match. Both have a status of 'All'. The date range is the same (2/19 - 2/25). 
    In fact, I went back to the test deployment and changed the date range to the date of the last failure (1/30).  Now I see data only from 1/30 but none for today's execution.
    Something must have happened in the deployment process--but what? How do I debug this issue with the reports--but even more importantly,  how do I get to the raw execution data to see what the story is on the failed execution itself?

    @Arthur, thanks for responding. In a nutshell, I searched through the ssisdb.catalog.event_messages table to determine roughly the same thing you determined--an execution for that package (or for that matter, any misnamed package) with today's timestamp
    simply never occurred--even though the job agent log appeared to indicate it had.
    I re-deployed the package ... forced an execution with an interactive run from the catalog... and viola! The execution info appeared through the standard reports as expected.
    Any idea where I could/should look for a wayward deployment? (BTW, the report for validations showed no data either on that first deployment).

  • Project Plan cost report - not showing any output.

    Dear Experts,
    I have created several projects and done the planning.  I have used work centers and activity types for manpower cost planning. Also created some PRs against the project.
    When I goto the network activities and select the line item in the menu path Edit - costs - Planned/Actual - cost planned /actual
    It shows me the planned cost of the activity correctly.
    But when I am running the report CJI4, it shows nothing. The report is not at all executing.
    I dont understand why it's \not showing.
    I have checked the control key PS01 for the cost field is enabled (tick available on the cost friled)
    Can any one please help me??
    Thanks and Regards,
    Praveen

    1) Please check that the WBS element is integrated in plan, and the plan integration is fully activated in the project.
    2) Plan line items are only written in certain cases.
    The following rules are valid:
    1. Plan line items can be written in
    a) structure-oriented cost planning CJ40 (total values, annual values),
    b) cost planning on orders KO12,
    c) unit costing independent of cost elements,
    d) structure-oriented revenue planning CJ42 (total values, annual values)
    e) structure-oriented financial budgeting CJ48 (total values, annual values, period values)
    f) primary cost planning,
    g) activity planning,
    h) revenue element planning.
    2. Plan line items are never written in
    a) Unit costing on cost element level
    b) Network costing
    3. Line items are only written if a user status permits the business transaction 'Write plan line items' explicitly.
    Exception:
    For plan-integrated WBS elements and orders, line items are written in cost-element oriented planning if integrated corporate planning is activated in the fiscal-year parameters of the respective plan version, regardless of the user status.
    4. Plan line items for structure-oriented planning can only be displayed in the respective planning transaction under menu option "Extras-->Line items".
    Let me know if this was useful
    Ritesh

  • CN41N and S_ALR_87013533 report not showing Production order planned cost

    Hi Experts,
    I am having issue to get total planned production order values in my CN41N or S_ALR_87013533 cost report. I am facing 2 issues :
    1. CN41N repoet does not show individual material cost planned in BOM.
    2. CN41N report and S_ALR87013533 report does not show total value but only picking fixed value.
    Example :
    1. CN41N report :
    Above screenshot shows no values in Project plan cost & Order cost column but it shows total cost as a lumpsum on top for project. I need to know how can i get material cost populated here for Project Valuated stock material?
    2. S_ALR_87013533
    This report shows Total Cost of BOM as 1 line under Material Procurement activity similar to CN41N report. Also Order value is picking from Fixed cost from planned order and total cost is added on top. How can i get Total cost picked from production order?
    Is there any Setting in PS config which allow me to pick the detail production order plan cost in both report under planned cost.
    Thanks in advance.
    Ashish

    Hi Ashish,
    I doubt whether Item level reporting  in S_ALR... (hierarchy report) is possible or not because I haven't seen item level cost in them only the lump-sum cost because they are summarized at cost object level itself. Navigation path are there which we use to go into details of cost.
    Please check the following links:
    https://scn.sap.com/thread/1743833
    (In the above thread,focus on  Mr. Mohamed Rafi comment.)
    http://scn.sap.com/thread/3530080
    http://scn.sap.com/thread/1311820
    Order cost plan in report CN41N
    Display of plan cost.,&amp;nbsp;CN41N&amp;nbsp;|&amp;nbsp;ABAP,&amp;nbsp;SAP,&amp;nbsp;benX AG,&amp;nbsp;benXBrain,&amp;…
    Just an additional pointer ,have a look on your costing variant and variation variant settings for material section.
    Regards
    Saurabh

  • Image not showing in Abobe integrated with Java WebDynPro

    Hi All,
    Image is not showing in Abobe integrated with Java WebDynPro.
    I did the following:
    Added the image field in adobe form. in URL value set the value of context node binding. Binding set to none and size set to Use Original Size.
    Then in script editor i wrote
    this.value.image.href = xfa.resolveNode(this.value.image.href).value;
    at innitialize , javascript and client.
    I can see the image from the same url context value if image field is created directly in WebDynPro View.
    Can anyone suggest what is missing?
    Thanks and Regards,
    Nuzhat

    Try changing your line of code for this one
    this.value.image.href = xfa.record.Images.URL;
    Check that the url passed by scripting is correct with a messageBox for example.
    You can also try assigning a hardcoded url at scripting level to check if its works.
    Best regards, Aldo.

  • Business systems not showing in I.D( Integration Directory)

    Hi Guys,
    I Completed the Configuration up to I.R( Integration Repository). in integration Directory i created a scenario. under Service without party when i am trying to assign Business systems. it is not showing any Business Systems. i already Created Business systems in S.L.D. any body have any idea why it is Happing. Thanks in advance.
    Thanks
    Kiran.B

    Go to Objects tab and find your Buss. System. Right click on this and select add to scenario. Buss. system should be imported into ID only once.
    If you cant find your Buss system in ID, then use the menu Environment --> Clear SLD data Cache.
    Regards,
    Jai Shankar

  • MIRO- Unplanned Delivery Costs info. not showing on FS10N line items

    HI,
    Can anyone explain why when posting an Invoice with unplanned delivery costs using T-code MIRO, the purchase order info. does not show in the GL line item display T-code FS10N for any of the unplanned delivery cost line items. If anyone have a solution to allow the purchase order info. to show on the uplanned delivery costs line item that would be great.
    Thanks.
    Rickey.

    Un-planned freight is entered on the header of the invoice and therefore relates to the entire invoice. Since, its possible to have mulitple PO's on one invoice it would only be possible to assign the PO when there is exactly one PO on the invoice.
    Alternative, you can use planned freight or post the unplanned freight using the G/L tab in transaction MIRO. By using the G/L tab you can enter any information required for accounting (including multiple lines in case it is required to split the un-planned freight by several PO's.

  • Cost analysis not showing up in production order

    Hi All
    Preliminary cost analysis is not showing up in the production order...can anyone suggest what could be the possible reason for this

    Hi,
    Once you issue goods(GI) to order then only you can see actaul cost in cost analysis in Production order.
    if you are looking for target cost in cost analysis,you have to post goods receipt(GR) from order to inventory.
    hope this helps you.
    Thanks,
    Rau

  • Why my Local Adapter Engine not showed in SLD and Integration Directory?

    Hi guru,
    I have installed one Local Adatper Engine on Host B, then an XI is installed on Host A, but After I installed the local adapter engine and follow the standard configration step mentioned in this document:https://www.sdn.sap.com/irj/sdn/go/portal/prtroot/docs/library/uuid/307deae3-604e-2a10-feae-f016fb9cadd4.
    After the configuration is done, I restart the local adatper engine, but this local adapter engine is not showed in integration directory.
    what is the problem?

    The post-installation configuration steps are not complex, I exactly followed.
    what other reason could it be? have any guru configured local adapter engine before?

  • Charts are not showing up in WEBI after the SAP Integration

    folks,
                  I have successfully iinstalled the following
                  BOBJ XI R3.1 Java version
                  Crystal Reports 2008 with SP1
                  Xcelsius 2008 enterprise
                  SAP GUI
                  Java Connector
                  SAP Integration tool kit.
    Now in WEBI when I want to draw some charts which are not showing up. Please give me some suggestions.
    Regards,
    preddy

    HI,
    I would suggest you open this in the WEb Intelligence forum unless this only happens with SAP based reports.
    Ingo

Maybe you are looking for

  • Questions on Oracle Management Packs

    1. What is the difference between MANAGEMENT PACK and CONFIGURATION MANAGEMENT PACK (Oracle versions 10g & 11g) 2. If one uses CONFIGURATION must one also use MANAGEMENT? 3. Is there a view that tells if either of these are actually being used? (No,

  • Problem moving files

    I'm pretty experienced using this product so yes I do know how to move files. Now I'm not sure if this is an OS (Windows 7 Home Premium) issue or a LR3.5 problem  (Or the one thing you never rule out, maybe I did something dumb). In any case I decide

  • IPhoto crashes when I try to Export

    I had a message pop up yesterday that wanted to update iPhoto. After the update iPhoto crashed when ever I tried to export a photo. I even tried to restart and it still crashed. What do I do next?

  • Can't launch photoshop cc,worked yesterday??

    cannot launch photoshop cc,worked yesterday

  • Tdms vs cluster where when speed doesn't matter

    hello, The question is in the title: in case speed doesn't matter wich could be advantage using one or other of methode. I 'm working on calibration bench at low speed ( T° of water , humidity, barometer) so hdd access is not a parameter. i have to s