I am trying to download a cprojects-project to ms project. One phase of my cprojects-project has a fixed start dart ("must start on"). But if exporting to ms project the fixed date is not mapped to ms project. Instead the second phase starts right after the first phase.
e.g.
cProjects:
project definition   start date 02.10.2007    end date 27.10.2007 (not constraint)
phase 1               start date 02.10.2007    end date 10.10.2007 (no constraint)
phase 2         must start on 20.10.2007     end date  27.10.2007 (start constraint)
download to ms project:
project definition   start date 02.10.2007    end date 27.10.2007
phase 1               start date 02.10.2007    end date 10.10.2007
phase 2               start date <b>11.10.2007   </b> end date  18.10.2007
In the IMG-Activity I maintained the following mapping:
CALENDAR_UID     PPCP     Phase (cProjects)     CALENDAR_ID
CONSTRAINT_TYPE     PPCP     Phase (cProjects)     CONSTR_TYPE_FIN
DURATION     PPCP     Phase (cProjects)     DURATION
DURATION_UNIT     PPCP     Phase (cProjects)     DURATION_UNIT
FINISH     PPCP     Phase (cProjects)     FINISH_DATE_FIX
LATE_FINISH     PPCP     Phase (cProjects)     SCHEDULED_FINISHED_LATE
LATE_START     PPCP     Phase (cProjects)     SCHEDULED_FINISHED_START
NAME     PPCP     Phase (cProjects)     DESCRIPTION
START     PPCP     Phase (cProjects)     START_DATE_FIX
TEXT10     PPCP     Phase (cProjects)     NUMBER
TEXT2     PPCP     Phase (cProjects)     CREATED_BY_NAME
TEXT20     PPCP     Phase (cProjects)     PHA_TYPE
TEXT5     PPCP     Phase (cProjects)     CONSTRAINT_TYPE
I maintained the mapping of the constrain type but that doesn't help.
System: cpro 4.0, support package 10 (netweaver2004s)
Thanks for your reply
Isabella

Hi,
I solved my problem.
The following mapping ist needed (to map the contraint type for the start date):
CONSTRAINT_TYPE     PTCP     Task (cProjects)CONSTRAINT_TYPE
The following mapping ist needed (to map the contraint type for the finish date):
CONSTRAINT_TYPE     PTCP     Task (cProjects)CONSTRAINT_TYPE_FIN
Maintain the same mapping all other project element (e.g. phase). If you are using summary tasks the fixed dates maintained for phase are not mapped to ms project (althought you defined the mapping for the phase). The fixed dates are then aggregated to the phase.
Now the contraint types are mapped to MS Project.
But there is still another problem. MS Project has only the possibilty to maintain a contraint type for start date OR finish date!!!!! Therefore you have to decide which ones you want to map to MS Project.

Similar Messages

  • Download of Blackberry Project Fails: err 907 -- 404

    New 8520. Restored contacts from 8220 I upgraded from.
    "About" V5.0.0.681 (Bundle 1168,Platform 5.2.0.67)
    I now want to add applications using Blackberry Project but the download "of" BB Project fails
    The BB shows a BB Project  icon
    I select it and I'm told to "Download Now"
    The download fails?  I select "Details"  and get 907 invalid COD HTTP Error 404: Not found
    When I back out it says "Thankyou for downloading"  ugh I didn't get anything
    quite frustrating, because I'm only trying to get the features back that I had on the old 8220 which I don't want to have to go back to

    to attach a close button you need to import
    mx.events.CloseEvent and then you need to
    _window.showCloseButton = true
    and lastly you need to setup a listener
    _window.addEventListener(CloseEvent.CLOSE, closeHandler)

  • Failed to download the example project from Oracle site.

    Hello,
    Every Time I am trying to run a sample or load an example I am getting the following error in workshop 10.3.
    Failed to download the example project from Oracle site.
    what do I do?
    Thanks,
    Indu.
    Edited by: user8828376 on Sep 27, 2009 5:12 PM

    Hi Indu,
    what kind of he samples your are trying to install in workshop 10.3.
    Do you have site address.
    if you need any further help on this put complete details so that we can able to help you more.
    Regards,
    Kal.
    (Thanks for you using OTN forums and sharing knowledge.)

  • Where are the downloaded files? Project is not showing up in the programs area of Windows 8.1

    I downloaded the Project files.  Now it doesn't show up in the programs area.  What happened to it?  The files did download completely - it took a while!  Assistance is greatly appreciated! 

    The default location for download in Windows 8.1 is the DOwnloads library, unless you changed it. from start screen, type downloads and see if you can find your files there. You will only see it in programs, after you have INSTALLED it.
    Prasanna Adavi,PMP,MCTS,MCITP,MCT TWitter: @prasannaadavi Blog: http://www.prasannaadavi.com

  • CProject integration with MS Project

    Hi,
    Bascially can we upload MPP file directly to cProjects, if so what are the settings that we need to do.Do you have any documents which provide this information.
    Normally i heard that MPP files gets converted into XML and this file is generally upload and direct upload from MPP file is not supported, is this correct.
    Regards,
    Srikanth ( [email protected])

    Hi Rehman,
    Thanks for your response, i will wait for your documents.
    I have following questions and here is the business scenario.
    customer download cProjects to MSProject.
    now if he uploads same MSProject to cProject , it will result in simulation version
    can we bypass this simulation version and update directly to operational version.
    is it possible to provide your contact number to discuss this requirement.
    Regards,
    srikanth.([email protected]).

  • Automatic assingment of Cprojects to SAP PS project

    Hi all,
    I am using Cprojects 4.0 and is installed as add on on ECC6.0. I have created a projects in Cproject and wnat to replicate it into SAP PS. I have done all necessary customizations required for account integration and in project type and in controlling scenario.
    When I am going to accounting tab in cproject , I can see the tab for assing PS project and Assing WBS element. But when I click on Assign PS project, the projects is not getting assing automatically. I cannot see any project in below space.
    The scenario is for automatic assignment. Please help
    Thanks and regards,
    Hemant Patil

    Hi Hemant,
    I am a little unclear about your questin.
    As far as I understood, you use the automactic assignment, that mean, the PS project & wbs elementen are created automatically. After it runs successfully, you shoud see the assignment between cProject object & PS objects. But why do you carry out action 'click of assign PS project', this action is only relevant for manuall assignment.
    Kind regards,
    Zhenbo

  • Error downloading Trial version Project Professional IT x86

    When I try to download the italian trial version from here  http://technet.microsoft.com/it-it/evalcenter/hh973401.aspx the download doesn't start. No problem when I try to download another language version (ex. US version) but there is an error when
    the applet on the right of the page should show the status downloading bar.
    It's the same for different workstation (Win xp, 7, smartphone) and different browsers.
    How can I download the Project Professional Italian Trial version?
    Thanks!

    Sounds like you have a corrupt or partial download. I would
    try
    downloading again
    alex
    duckpuddle.net wrote:
    > Could someone tell me what i need to do to get fireworks
    8 to work.
    >
    > i downloaded the fireworks 8 from the adobe site and
    then i got an error
    > message stating that it couldnt read the packaging due
    to the file being
    > corrupted.
    >
    > is there a plug in or something that im missing that
    would make it work?
    >

  • CProjects - Unable to close project

    Hello,
    I encounter a problem in cProjects 4:
    I have a cancelled task which prevents me from closing the related project. In fact, when i try to close the project, i got a message telling me that this task as to be closed before...
    Does anyone have any idea of how i can solve this ?
    Any advice would be welcomed.
    Thanks in advance for your help.
    S. Talasi.

    Hi Matthias,
    First of all, thank you for your help.
    Yes i meant "completed" but the problem is i'm not able to complete anything at all at levels higher than my task.
    When i tried to complete the ITO above my TTO i got an error. As i thought i needed to complete all ITOs before beeing able to close my CTO , PPO, DPO, i thought i won't be able to close the project.
    But, i realized that i can complete the CTO without changing the task or the item status which solved my problem.
    Thanks again for your precious help,
    Sébastien
    Edited by: s.talasi on May 26, 2010 9:56 AM

  • Who uses cProjects for IT internal projects  ?

    Hi togehther,
    is there someone who uses the cProjects System to handle IT-Projects?
    Which templates do you use for IT-Projects?
    How to start such a project?
    best Regards,
    Carsten Schulz
    ebmpapst - Germany

    Greetings.
    We are  in the process of impmenting SAP Suite in our organization. I am trying to promote the use of xRPM and cProjects during the impmentation. The main reason is that we are looking for a sloution for our core activities which is related to development project fianiancing. The use of xRPM and cProjetcs will give a good chance whether this sloution is suitable for us. The other reason is to enforce good project managment discpline by utlizing cProjects stage-gate concept.
    I wish to hrear from others on thier expricne of using cProects in IT projects, speciaclly for SAP realted projects.
    Regards,
    Abdullah

  • CProjects-Bapi's for project and task details

    Hello,
    I am searching for bapis for cProjects to use in a report at back end which has all the project fields and task fields.
    For project i found a bapi BAPI_BUS2172_GET_DETAIL, but it does not have fields like project name,status, calculated start and finish date from teh basic data tab, division,design center from teh additional data tab.
    For task fields i found bapi BAPI_BUS2175_GET_DETAIL but it does not have task status, latest start and finish date of the basic data tab.
    any pointers to bapis which cover all the above fields would be really helpful.
    Also I want to know is there anyway i can get the URL of the document that is uploaded in teh documents tab of the task.
    Thanks,
    Simmi
    Edited by: Simmi Balakrishnan on May 2, 2008 9:13 PM

    Hi Simmi,
    Some information can not be retrieved via Bapi call. If you would like to read it, you can use simple select to get it from DB directly. The related DB are cgpl_project (dates), cgpl_text (descritption), and crm_jest (for status).
    Kind regards,
    Zhenbo

  • Roadmap download to MS Project after SP15

    Hi,
    After applying SP15 I can no longer download our customer defined roadmap to MS Project _ anyone know what could be the problem ? I am running SAPgui 6.20, could that be it ?
    BR
    Karin

    No one will know your problem, if you have not mentioned what error you are getting???!!!
    Why don't you provide atleast the error message??
    Please read rules of Engagement before posting.
    I would recommend to upgrade your FrontEnd to latest version and latest patch..
    Minimum requirement for NW04s is SAPLOGON 640.
    Feel free to revert back.
    --Ragu

  • Download for Microsoft Project 2010

    My employer purchased Project Standard 2010. My laptop does not have a disk drive. Is there anywhere that I can download Project Standard 2010? I have a product key and have tried entering it on the Get Office page, but it comes back as invalid.

    Hi,
    Please try this site:
    http://office.microsoft.com/en-us/products/download-back-up-restore-microsoft-office-products-FX103427465.aspx
    You will be asked for the 25-character Product Key that came with your qualifying office 2010 purchase.
    Hope this helps.
    Thanks,
    Ethan Hua CHN
    TechNet Community Support

  • I want to download my Idvd project to youtube, how is this donw

    H E L P !!!!!!    i have made a project I made using IDVD, how do I download it to youtube or anywhere else? 

    Follow the instructions in this Apple KB article to import the music from the CD: http://support.apple.com/kb/PH12486. when you have all the ID3 tags how you like them then follow the instructions in this article: http://support.apple.com/kb/HT4914.
    FYI, iTunes Match (not "iMatch") and iCloud are not the same thing. They are separate and distinct services and one does not require the other.

  • PPM 5.0: Assign cProjects New Status to Project Mngt business transaction?

    hello Experts,
    In SPRO -> Project Management -> Basic settings -> Create/Change Status Profile for User Status, I created my own status profile and assigned them to object types.
    Now, for status synchronisation, i need to map Project / Initiative Business Transaction to DFM Business Transaction
    ( SPRO -> Portfolio and Project Management -> Portfolio Management ->Base System Interfaces -> Decision Flow Management Settings -> Status Synchronization -> Map Project / Initiative Business Transaction to DFM Business Transaction)
    My question is : 
    How can I create my own Project Management business transactions?
    if is not possible, how can i assign the standard ones (DX01, DX02, etc) to my own status (ZST1, ZST2, etc) ?
    Thank you in advance,
    Amal

    Hello,
    Check the trasnaction BS32 for adding new business transactions.
    Cheers
    Amit

  • How to create a project in PS automatically wen it is created in cProjects.

    Hai experts,
        How to create a project in PS automatically wen it is created in cProjects.
        After creating project in cProjects wen i flagged to transfer it is not transferring to PS...
    How to achieve this...
    Thanx in advance...

    hi
    Try with following settings if you have not done:
    1) In define project type, for for accounting integration , select scenario as: Accounting integration in my SAPERP and type of transfer as : Always Automatic when saving
    2) For Define object link for object type , define proxy class for WBS element and Project definition(PS)
    Also define RFC for Single object Controlling on WBS element in Object types for object links.
    3) For Accounting integration in Make general settings, for your project type select frame09 for your object type single object controlling on Internal order
    4) Define CO scenario CPR2 with Strategy sequence as SAP040 in period end closing, costing sheet as standard and Costing variant as PC02(Internal Order)
    5) In CO scanrio maintenance view, for your project type select contolling method as Internal Order( Project Definition, Automatic)
    With these settings I am able to create a PS project from cProject when I save a cProject.
    Regards,
    Niraj

Maybe you are looking for

  • Need help with calculating interest

    Hey im trying to find out where my calculations are screwing up on the interest is coming up wrong but i am unable to find out where. After every month its suppose to be deposit - withdrawl * monthly interest rate and then add that total to the new m

  • Training and Event Management in XSS

    Hello Forum, I'm running ERP 2004, Portal 6.0, MSS/ESS Business Package 60.1. Where can I configure Training Management for ESS? There are no Worksets, iViews, Pages, ... for this application in my Portal Catalog. I have the same problem with Team Vi

  • Firewire Cable Needed For File transfer Between Old iMac & New iMac.

    I have an iMac G4 (Flat Panel) - just got the the iMac 21.5! Need to transfer files between old & new iMac. Is the 6 pin to 6 pin the correct cable I'm going to need to get my files transfered ???

  • Problem in displaying a datablock... Urgent!

    hello guys, i have a serious problem to solve. It's urgent for me . First of all i have a datablock which contains some data from the database table mis_efhmeries. Now, i want to display in the screen 3 columns , 1 from the database (so i make the ot

  • Reports for Sheduling Agreement

    Hi, SD Experts Any T-Code available to view the shedule line of the sheduling agreement for what are the quantities has been delivered and what are the quantitites to be delivered. Regards, Anand