Creation indicator in MRP

Hai PP Gurus,
              Whenever we run the transaction MDO1,MD02 & MDO3 it shows some default values for creation indicators like 1/2/1.But i want to set default values like 2/2/2 that means whenever i call this T-code it shows 2/2/2. This default values are maintained by PP or ABAPER through program.
             So please throw some light on this....
             Thanks in advance
Regards,
S.ganeshraja

Dear Mr.Ganeshraja,
Check this,
Maintenance
You can only create transaction variants for dialog transactions and reporting transactions.
Only "normal" screens, dialog boxes, and subscreens can be included in the variant.
Screen Variants are automatically created anytime you create a transaction variant.
Initial Screen
Enter the name of the transaction and the transaction variant on the initial screen. The system creates a cross-client transaction variant. If you want to create a client-specific transaction variant, choose Goto -> Client-specific transaction variants tp branch to the client-specific transaction variant maintenance transaction.
Client-specific transaction variants only exist in the client in which they are created. The field contents of the transaction variant must be available in this client. Cross-client transaction variants are available throughout the system, regardless of the client currently being used. The field contents of these transaction variants must be available in all clients.
Creating the Transaction Variant
Choose Create to create a variant.
The system calls the application transaction that you want to create a variant for. Enter the values you want to use in the in the input fields. Each time an action is completed, a Dialog Box, appears listing the fields of the current screen with their current values. The kind of dialog box called depends on the kind of screen currently being processed (see Requirements).
Here you can determine:
if you want to save the field values you have inserted on the current screen (the "Adopt field values" checkbox)
if you want to hide the entire screen (the "Do not display screen" checkbox). This is only possible if settings are copied to your variant ("Adopt field values")
if field contents are saved (the "With contents" checkbox)
if the ready for input status of specific fields should be revoked (the "Output only" checkbox)
if specific fields should be hidden (the "Invisible" checkbox)
if specific fields should be mandatory the "Mandatory" checkbox)
You may or may not be able to select each of these checkboxes for every field depending on the field's type (--> Requirements).
Screen variants are created automatically for each screen where values have been saved (adopted). Enter screen variant names in the "Name of screen variant" field. These names must be unique. If the system is able to find a unique name for a screen variant it is automatically inserted into this field. The convention reads like so: (< name_of_transaction_variant>_(<client>)_<screen_number>).
Choose the function Continue to proceed. The following pushbuttons are available:
The Cancel function displays the current application transaction screen again. Here you can make changes to your settings.
The Menu functions function displays an additional dialog box wher you can deactivate menu functions.
The GuiXT function allows the user to edit a GuiXT script for the current screen (--> GuiXT).
The Exit and Save function exits and saves the application transaction. A list appears containing all of the screens in the application transaction that you want to save entries for (that is, all screens for which screen variants will be created).
Enter a short text for your transaction variant here.
Display settings can be changed as needed from this list in the future. Settings that require information at application transaction runtime (field values, table control columns) cannot be changed from this list.
Choose "Save". The system saves your transaction variant and the corresponding screen variants. The Workbench Organizer dialog box is displayed for the transaction variant and for each screen variant. Use it to assign each of these objects to a package.
You can also branch to this list using the Change values function during the function selection process.
Deleting Preassigned Values
You can delete all of the values you assigned to fields of a single screen in a transaction variant by resetting (deselecting) the Adopt field values checkbox. This deletes the screen from your variant, even those entries that were transferred to the variant during previous processing.
If a screen variant has already been created for this screen, then the system simply deletes the screen variant's transaction variant assignment; the screen variant itself is not actually deleted.
Individual fields can be deleted from transaction and screen variants by resetting (deselecting) their corresponding checkboxes.
Regards
Mangal

Similar Messages

  • MRP Creation Indicator

    Hi Experts,
    Just want to seek help regarding the MRP Creation Indicator. What would be the effect if the Opening Period set is "0" or zero for the MRP item in SMK of Material Master but when we run MRP in the Selection Parameters we uses the parameter "2"- Purchase requisitions in Opening Period in the Create Purchase Requisition field.
    We have MRP items wherein MRP still generates Planned Orders (STPO) even if the Opening Period is Zero or "0". The MRP Planned Orders contains Planned Opening Date which is the same date when MRP run and yet MRP did not created PR for the item. Hope you can help enlighten us.
    Thanks,
    SD

    Hello ,
      The Opening period define at SMK is used to  calculate the "Opening date" of either planned order or Pur req. Opening date is calculated as below.
    Open date = Opening period - Order start date of Planned order  or Release date of Pur req.
    According to cont ind 2 ,  If Opening date  falls  before the "MRP Run date" system will create  Pur req directly.In your  case the Opening date and MRP date are same it will create Planned order Only. You have to  convert ot manually.
    Opening period  is nothing but a buffer period for MRP controller  t o convert the Planned order to  Pur req
    To check the same, increase your Opening Period at SMK and check with MRP
    Regards
    Pradeep
    Edited by: Pradeep Kumar on Jun 16, 2009 1:33 PM

  • Creation indicator purchase requisition in md02

    Hello SAP Gurus,
         This is regarding creation indicator purchase requisition in md02.In this creation indicator purchase requisition if we keep setting as 2 than it will create purchase requisition if the dates of PR are in the opening period and will create planned order  if dates of PR falls out of opening period.And it takes the opening period from schedule margin key.
         My question is , as system calculate the opening date by subtracting the number of days which we have given in opening period in schedule margin key from the order start date.suppose if order start date is 10.03.2008 and we have given the opening period of 5 days,than the opening date will be 05.03.2008 if there are no holidays between it.So how it comes that PR date will fall in opening period?I am confused that when system will create planned order and when system will create PR if we keep creation indicator purchase requisition as 2.
          Plz help me with this query.If you could explain with one example than it would be great.
                         Thanking all in advance.And obviously for suitable answer i will definately give good points.

    Hi,
    System calculates the opening date  by subtracting the number days given as opening period at SMK from order start date.
    For creation ind =2 ,
    MRP run date decides the PR / Planned order creation even if u set procurement F.
    If MRP run date falls bettwen the opening date & order start date , it will create PR only,
    If run MRP run date falls outside the opening preriod ie earlier than the order opening date, system will create planned order and it has to converted to PR
    For  examble,  Order start date is  28.03.2008 and 2 day is defined as opening period SMK for ROH.
    If u run MRP on today it will create planned order.  
    Hope u understand , ifso reward and close.
    Regards
    Pradeep

  • Creation Indicator in PR: B Material Requirement planning

    Hi All,
    I am facing an unusal scenario.
    User is claming that PR is getting generated for a material after running the MRP, even there is enough stock.
    I checked material &  I found that MRP type is ND, there is no entry in the planning file for this material.MRP list & stock requirement list of this material is showing nothing. So there is no way that PR will be created automatically via MRP run for this material.
    When I checked one PR for this material, Plant & storage location, creation indicator is showing as B Material Requirement planning.
    Could you please help me that why creation indicator is showing as B>
    I further checked these PRs are created long back when MRP type was V1. Later they changed it to ND.
    How to delete MRP generated PR manually when PO has been created for these PR.
    Regards
    Shilpi
    Edited by: sapmm1234 on Dec 14, 2011 6:10 PM

    As you said; the PR was created long ago by MRP, when it was not ND.
    If it was already converted into a PO, there's no need to delete it, right? If not, just delete it manually.
    In the future, when you change MRP type from a valid type to ND, always remember to do 2 additional things, as the system will not do them automatically:
    1- delete the MRP list
    2- delete any planning elements if they exist, like planned orders and MRP generated PRs.

  • Authorization object for field, EBAN-ESTKZ (creation indicator)

    Dear All,
    Does anyone know if there is an authorization object for field, EBAN-ESTKZ?
    I need to control the PR's authorization at creation indicator level. i.e. we need to remove the ability for all users to change Purchase Requisitions created by MRP.
    Thanks,
    Arun.

    Hi Jay,
    Thanks for your response.
    I didnt find it there. You have any Z options?
    Thanks,
    Arun.

  • Defining planning time fence and creation indicator with out oppr settings

    Hi, we dont use mrp groups and accordingly i did not set oppr settings. i observed that planning time fence and the creation indicator (omdz & oppr) are defined thru mrp goups. please advise how to define those w/o oppr settings? is there any seperate settings or oppq settings for them? please advise.

    Hi,
    Maintain it directly in the Material Master.
    Best Regards,
    Siva

  • PO creation Indicator in SRM

    Hi Experts,
    I have a question for you?
    Where can i find the PO creation indicator in SRM?
    We are in Extended Classic scenario. POs are created from Shopping carts either manually by Purchaser from SOCO or autmatically by the system for catalog items & for items with Contract.
    I want to know whether there are any status indicators for a PO in SRM from which i could know whether the PO was created manually or automatically...similar to the field we have in EKKO for a R/3 PO.
    Thanks in advance!
    Cheers - Aakash

    Hello Aakash,
    You can determine whether PO hasbeen created automatically from a preceeding document or created manually at line item level only. If the PO is created from a preceeding documents like shopping cart then the fields SRC_GUID and SRC_OBJECT_TYPE of the table BBP_PDIGP will be filled. If the PO is created manually then these fields will be empty.
    Hope this will answer your question.
    Best Regards,
    Mani

  • Bapi_pr_change error Creation Indicator G invalid

    Has anybody come across this error?
    I tried searching in sdn forum and google, could nt find it.
    If i try to change the PR manually it allows, but using the above BAPI it gives this error.
    'Creation Indicator G invalid'.
    How do I solve this?

    Hi,
    Creation indicator G stands for store order .
    I think you should give F...
    else try from all the remaining possible combinations
    B, D, R, U, V, M, Y, A
    Regards

  • Individual and Collective Indicator in MRP 4 View and BOM Expl.No

    Hi
    Please get back to me on the below queries
    a) I am using Planning Strategy u2013 40, do we need to maintain Individual or collective Indicator in MRP 4 view?? If I maintain what will be the impact and if I do not what will happen to the dependent requirements.
    b) What is BOM Explosion No?? please let me know this functionality and the configuration steps if any..
    Thanks

    Hi,
    u2022Individual requirements
    Requirement quantities of the dependent material are stated individually.
    u2022Collective requirements
    Requirement quantities of the dependent material are grouped together.
    BOM Explosion Number:
    1) Starting from the MRP menu, choose Master data -> BOM explosion number -> Edit.
    The system displays the initial screen for maintaining the BOM explosion number.
    2) Choose Execute.
    The screen for maintaining the BOM explosion numbers now appears.
    3) Choose New entries.
    A screen now appears where you can enter new BOM explosion numbers.
    Enter data as required.
    BOM explosion number - The BOM explosion number is the object for which the following data is maintained. It can be entered alphanumerically.
    Fixed key date - The fixed key date determines which bill of material is exploded.
    Plant - You can also specify a BOM explosion number for a specific plant. Enter the appropriate plant in this case.
    Material - You can specify a BOM explosion number for a specific material. Enter the appropriate material in this case.
    Status - You can set the BOM explosion number to active or inactive using the status field. Only active BOM explosion numbers are used in the planning run.
    4) Save your entries.
    Regards,
    Sulabh

  • Significance and use of CVD indicator and MRP indicator in J1IEX

    Dear Frndz...
    Plz expln significance and use of CVD indicator and MRP indicator in J1IEX.
    Regards,
    Amit P Hiran
    njoy SAP..
    njoy Life...........

    hi
    >CVD TICk
    CVD indicator will be auto ticked when when u go for IMPORT PROCESS
    check folowing for import process
    import process customization
    >MRP TICk
    MRP tick is used for the first stage dealer scenario ,where at time of purchase u cant have excise values
    the bill will be including base price exciseothertax + delears commisiion
    E.g.:
    Material Price = 80/-
    Excise Duty = 14/- (BEDECessSECess)
    Margin = 6/-
    Total =100/-
    VAT @3% = 3/-
    Grand Total =103/-
    Step 1:
    Create PO with Base Price as 100/- by selecting tax code which is having VAT as 3% (Total PO value will be 103/-)
    Step 2:
    Post MIGO and Capture Excise Part - 1
    Click on More details icon in Excise tab (header), check MRP Indicator in miscellaneous tab, Enter Assessable value as 80 in Excise tab Item level and enter the excise values BED, ECess , SECess manually, check & save the document.
    Step 3;
    Post Excise Part 2 in J1IEX
    Step 4:
    Post MIRO by checking calculate tax, edit base value as 80/- enter the amount in header as proposed by the system (103/-), simulate & post the document.
    Note 1104456 - Use of MRP indicator for capturing excise duties from dealer

  • MTS  Scena. but after creation of SO & mrp run ,double requiremnt generated

    Dear Gurus and Sir,
    Good morning,
    Client Has Make to order scenario. Scenario is as stated below
    company  is into  making "Machines which manufactures bottles" which is a standard product for client.
    Hence as per experiance, Client manufactures the Machines in adavance for the Stock.
    As and when  sales requirement is observed, machine is assembled with the changes asked by customer.
    For Make to Stock Scenario.
    Standard Machine code (11digit) is avaialble with BOM. The same code is used for Long term planning.
    After receipt of order, customer wise MAterial code is generated. The above stadard code becomes child of This new material code.
    The changes are addressed to customerwise material code.
    This customer wise material code is nothing but dispatchable assembly as per customer requirements.
    The Stratergy used for Stad. M/c code in MRP3 view is 40 and in MRP4 collective indicatior  as 2.
    The stratergy used for customer material code in MRP3 is 50 and w/o collective indicator.
    Hence there is a std. bill of material for standard machine. MD61 plan will run  against the same std. code.
    MD61 is having Consumption indicator stated as 3.
    As soon as Sales order is received, The MRP run is taken with command MD50. 
    During this MRP run, system consideres the Sales order requirement as a seperate Demand apart from Planned demand through MD61.
    The system should not generate double requirement.
    Needless to quote that  raw materials and semi-finish items are planned in advance due to make to stock strategy.
    "I have got one solution presently
    that using MD02  take MRP run for common components
    after receipt of sales order take MRP run  MD50  for final assly.
    system will not generate double requirement .
    When MRP RUN taken through MD01,system generates double requirement. MRP run through MD01 run is required for VB marked items.
    The std user Exit M61X0001 is available in standard SAP.
    What should be the appropriate/correct solution for above stated problem.
    Advance Thanks & regards,
    Vidyasagar

    Hi Vidyasagar,
    In your case, MRP Creates sepearte dep requirements for customer demand.
    As per ur settings, yor are doing procurement for std material before the receipt of sale order of customer material code.
    u need not worry about dep requirements created against custome ordder. Bcz once u issue the std material to production order (while confirming production order created for custmer material from planned order) it will be reduced.
    Please comeback
    Regards
    pradeep

  • Firming indicator in MRP run!!!

    hello! everyone!
    can anyone tell me the importance or use of firming indicator  in relation to MRP run?
    when does it appear or what are the settings required?
    value answers will be rewarded!!!

    Hi,
    If MRP generates a Purchase requisition and if nobody changes (or allocates) that requisition then it can delete or change that requisition in the next MRP run.
    If the flag has been set then  MRP cannot change it.
    The flag is set automatically when you change the requsition or if you (fully or partially) allocate it to a PO.
    this means that the reaquisition wioll stay there forever unless it is manually deleted or converted into a PO.
    the most important use of this indicator is for it to be set automatically by the release strategy. The reason for this is that MRP can be run in a way that it is "told" to delete all requirements and start again. If it deletes a requisition and then decides that it still needs it, it creates the requisition again and (very cleverly) uses the same number. BUT if that requisition has been released by someone (due to the release strategy) this will be "lost" and the requisition will have to be released again. This can happen time and time again, with the same requisition authorised and then reset then authorised and then reset many times.
    On the release indicator (in the release strategies) there is a "fixed" indicator. If you set this, MRP treats it as Firmed (Fixed) and so does not delete it. This can save a LOT of effort and confusion (if the requisition is no longer required you still get warning messages telling you this and so it doesn't matter that MRP cannot delete it)
    So a VERY important flag.
    Steve B

  • Individual / collective indicator in MRP 4

    What is the use of this indicator and when to use individual and colloective option ?

    Hi,
    If you maintain Individual requirement seeting in MRP 4 view , always a PR or Planned order is generated aginst the WBS element based on Procurement type setting ( E or F). If a PR is genearated, and is converted to PO and when we do GR of the item , for a valuated stock , Stock and price will be in project stock not in actual cost. ( can see report in T-code GR55. Report Z6P2.)
    If you maintain collective requirement seeting. Always a reservation is created against the network activity. Once the item is issued against the reservation , cost is debited from the activity and item is consumed. No stock.  Cost will booked to actual cost.
    Can check the same by testing with same material ....
    first have seeting as a Individual requirement. Genrate PR , convert to PO , do GR and check MMBE (stock report) and GR55 cost reprot.
    next time same material , change setting to collective requirements, Reservation is created , DO GI against that resevation. Check MMBE ( No stock should be there ) , Check GR55 cost should be booked in actual cost.
    No change in costs. Only change in the flow of qnty and cost.
    Thanks
    Saikishore Ganga
    P.S : Kindly confirm as soon as you try this.

  • Creation of new MRP Areas.

    Hi All,
    While creating new MRP areas am facing problem like "ERROR IN CUSTOMIZING:MRP AREA 1002 IN PLANT 1002 DOES NOT EXIST.
    But I am creating MRP areas for another plant-1003.
    I didnt understand thatwhy this error is coming and unable to save.
    Can any body tell me how to slove this problem.
    Thanks
    Chindam

    dear 2009,
    frist create MRP area using SPRO->Prod>MRP>MRP areas-->Define MRP area(SM34)
    then come back and activate MRP for created MRP area
    sree

  • Not running MRP but has Purch Req with Sales Order as pegged reqmnt in AFS

    Hello Gurus!
    MRP run is activated in the Plant but we do not run MRP (no MRP batch job nor manual MRP). However, there are materials that have Purch Reqs with creation indicator as MRP showing pegged reqmnt from Sales Order even if Item category is the same.
    My initial check shows that those materials with issue has MRP Indicator as BLANK(Multi-level, transaction dependent MRP) and those that do not generate Purch Req from SOs has N(No transaction-dependent MRP). However, transaction dependent MRP is not activated.
    Can you provide areas where I should check/other probable cause of this?
    Your valuable insights is deeply appreciated. Thanks!

    Hello?
    I just want to update how this was resolved.
    I found out that MRP Indicator field in AFS MRP view for the materials with MRP generated Purch Reqs is maintained as BLANK(Multi-level, transaction dependent MRP) in AFS MRP view instead of N(No transaction-dependent MRP) but there is no transaction group maintained. So MRP run is triggered whenevert there is MRP relevant transactions performed.