Csting RUn Of Material in CK40n

HI!!!
Friends!!
I am working on make to order scenario.I have worked on Bill of material (Finished -Raw Material)
When I run the ck40n.
How I enter the price of materials .And How the system show me the result of costing of materials.
Could you give me brief details of costing of material.
Regards,
Nitin

Hi Nitin,
For Doing the costing of the FG, you need to do the following activities,
1. Maintain price for the Raw material (V) in the Material master.
2. Hope you have maintained the BOM and Routing(if it is in-house production) for the FG material.
3. From the BOM the quantity structure of the material is identified so the material cost is calculated (BOM qty multiplied by the Material master price)
4. Next is your process cost. You need to identify, for how many activities you want to capture the cost. You define Secondary cost elements for that many activities.
5.Create Activity types and assign the cost elements there.
6. Maintain activity price in combination with cost center in KP26 transaction.
7. The Overhead cost will come thro' costing sheet, your controlling consultant will do that.
8. If any External processing / Sub-contracting is there, you have to maintain purchase info record for that.
9. In CK11n /CK40n you can do the cost estimation.
10. In CK24, you have to do the Marking and release.
Hope this will give clear picture to you.
Regards
Bala

Similar Messages

  • Cost Estimates taking raw material in CK40N

    Dear Experts,
                 We are running Costing run using CK40n by selecting site & article
    type:ZMTG. (Only Finished Product)
    But Standard cost is displaying for ROH/VERP in CK13n/MM43.
    We only want to carry out std cost run for only ZMTG article.
    In Costing varinat Priority is set for "Valuation Price according to price control" so the value give is correct. But the standard price field is getting updated in material master for Raw Material.
    I want to know usually whether it used to take like this, if not where i need to make changes so that it should not take while costing the finished product.
    Please reply asap.

    Dear Abhisek,
    It does not matter if the standard field updates with cost estimate, coz it does not effect financial results at all, reason behind the price control which is moving average  for RAW materials.
    Secodndly, it is helpful for you to find out the price of material when cost estimate was exucuted, coz it will not change until your further cost estimate run.
    Raw Materials are part of BOM, so system always calculate their prices to reach at price of finish product, but system does not post any price change document for raw materials.
    Further u can confirm using tcode CKMPCD
    Regards,
    M. Tayyab Aslam

  • On costing run, Raw material price in Std price  field is getting updated

    Hi All
    When i am executing costing run (CK40N) for a FG, the price field in Std price for a raw material is getting updated.
    We are maintining price control as "V" in case of raw material.
    Is this right? if not, how can this be avoided.
    Regards
    Rakesh Hase

    HI Ian,
    Given enough time and money, anything is possible....
    You do not say which industry you are operating in. In some SAP industry solutions the functionality you describe is available - if I remember correctly IS Mill Product has something like that. It is available for use by companies that for example make copper cable. They get a regular copper price from an exchange.
    But it would be relatively simple to get a feed from an exchange with the daily closing price, and then write a little program that will read that file and post an MR21 transaction to update the price.

  • Run CKMLCP (material ledger cockpit) for closed period in MMPV

    Hi,
    I would like to run CKMLCP for period 12.2008, however MMPV was run in 02.2009, and only january and fabruary 2009 are allowed for material postings.
    How can I settle material ledger in 12.2008? I know about note 361236 (CKMLCP: No period-end closing operations after period shift), but don't know if this will do all the proper postings or only close 12.2008 technically.
    Regards,
    Karol

    Hi Carol ,
    Please remeber costing Run i.e CKLMCP is a closing activity so it should be done only at the time of closing a particular period .A syou said two periods are open for MM but costing also post some Accounting enteries if FI period is closed the its not possible.
    And its not recommended to run costing any time in middle of the period.
    Thanks
    Deepa

  • CO/PP - Costing run - raw material cost component

    Hi
    In the costing run how raw material cost is taken?
    is it the material moving price/
    or calculated separately?
    Please help

    i think this depends on the costing variant defined in the order type
    in the costing variant, this come from the valuation variant
    for process orders you may check the following txns COR4, OPL1, OPN2

  • Higher activity price in cumulative run in Material Ledger

    Hello,
    Scenario:
    The company is using material ledger and doing periodic run. After the periodic run, company post financial transaction and run cumulative run to take impact of financial transactions.
    During cumulative run, system is using actual price of the last month and revaluation the cumulative qty with this price. Due to no catual activity, the prices are very high. Due to this, system is revaluating cumulative quantities of all months with very high price (of last month).
    Please suggest to resolve this issue?
    Neeraj Rawat

    Hi Srinu,
    Do you mean that, just after changing the KP26 values, u are expecting the same to reflect in your cost component structure of materials? KP26 is only to plan the price of an activity type in a cost center. This will be applicable for the future period. ie when operations are confirmed in production orders in future, this costs will be absorbed to the production order.
    Use  S_ALR_87013611 or similar reports for actual activity prices(debits) and actual activity quantities. Former divided by later will give you the actual per unit activity price for the last period.( in case of 1 to 1 relationship between cost center and activity).
    Best Regards
    Vimal

  • MRP run for Material type

    Hi Gurus,
    I want to run MRP for particular material type say for all my raw materials or semi-finished.
    How it can be done?
    I have used to user exit in MD01, for running MRP for a particular MRP controller and also for MRP type like PD or VV etc.
    Srini

    Srini,
    in this same exit you can include the parameter for material type  "M61X0001" to able to select the materials based on a field like MRP type.
    In transaction SMOD you can check the documentation on this development.
    take help from your ABAP person.
    come back for further discussion.
    regards
    Ritesh

  • Costing run for material - std. cost estimate

    Hi all,
    The scenario is as below:
    I have a material (halb). I have maintained a BOM. Now, i donot have a routing, but i just use a reference operation set.
    In this case, when i run the standard cost estimate (t code CK11N), the master data is read. But, since no routing exists, so the activity costs wont be read. So what should be done in this case, so that the costs as per the activity in ref. operation set is also captured?
    Shrenik

    Shrenik,
    If the Referance Operation Set is standard and same is going to be used always, please <b>enter that details of the Ref. Opn Set</b> in the <b>costing 1 view of the material master under Quantity structure data.</b>
    Regards,
    Prasobh

  • Difference between normal Costing run and Costing run in Material Ledger

    Hi everybody,
    I have a question i wanted to know why we implement Material Ledger .
    If material ledger is for settling variances on material then that is also possible without material ledger
    Please clear the doubt what is different in ML as compared to normal costing run
    thanks in advance
    Regards
    Deepa

    Costing run is to calculate the std cost estimate of materials and Material Ledger costing run is to calculate Actual cost of production of materials.

  • Can mrp run consider material availability for more then one plant?

    H&#305; PP Gurus,
    My Case:
    Material "A" is maintained for plant "X" and "Y" for example. When i execute mrp for material A i have to specify a plant. And the system creates planned orders just considering the quantity in that plant. But i want mrp to see the quantities of both plant.
    I mean when i execute mrp the system must consider the quantities for both plant and create planned order or not.
    Is there a way to fix it?
    Thank you indeed.
    Evren Temiz

    You can use Scope of Planning for this.
    Total planning covers the planning of all the materials that are relevant for requirements planning and includes the BOM explosion for materials with a bill of material.
    You can use total planning for a single plant or you can use the scope of planning to control whether the total planning run is executed on a multi-plant level
    If you have activated MRP with MRP areas, you can also combine MRP areas in the scope of planning as an alternative to plants.
    With the help of the scope of planning, you can control whether the total planning run is to be carried out:
    1. For one plant (as previously without scope of planning)
    2. For several plants
    3. For an MRP area
    4. For several MRP areas
    You define the scope of planning for the total planning run in Customizing for MRP, in the IMG activity Scope of planning for total planning run .
    You can carry out total planning for a scope of planning online or as a background job. The planning run must always be started with parallel processing.
    You can use the scope of planning for total planning in Material Requirements Planning, Master Production Scheduling and Long-Term Planning.
    Please refer to the below links -
    http://help.sap.com/saphelp_46c/helpdata/en/35/b0e95c87a62488e10000009b38f9b7/frameset.htm
    http://help.sap.com/saphelp_46c/helpdata/en/d7/5c9366f47811d1a6ba0000e83235d4/frameset.htm
    Hope this helps you.

  • Standra cost run (material cannot be costed)

    Dear Guru's,
    Can any one help me,  I have one material which is created under Non - Stock (material type :NLAG) item,
    user raised sales order and billing document on that material,  while releasing billing document to finance it is searching for current planned price.  CO-PA is activated.  while running standrard cost estimate run in ck11n and  ck40n one error message showing  that is Material PSERVICE cannot be costed.  pserivce means material name,  for this material master there is no costing tabs. 
    This error message showing
    Material PSERVICE cannot be costed
    Message no. CK113
    Diagnosis
    In accordance with material type NLAG for material PSERVICE, the material is not relevant for costing.
    System Response
    Material PSERVICE is not costed.
    Procedure
    1. Check the master data for material PSERVICE.
    Display material master record
    2. If you have authorization for Customizing, check whether the material type is correctly set for this material. A material can only be costed if the Costing indicator in the material type is set.
    1. can any body tell me non stock materials can we able run standard cost.
    2. without costing tabs can we run standard cost
    3. which material type can we run standard cost
    This will appricated
    Thanks & Regards
    Chandra Sekhar Reddy
    99868773663

    Hi,
    Most of the materrial types like FERT, HALB, ROH can be costed. Exception is like this non-stock material type.
    With out costing view, it is not possible to perform standard cost estimate.
    Hope, this helps!

  • No Error Log generated in 'Costing' step in Costing Run (CK40N)

    In the Costing Run, when the 'Costing' step is run (after 'Material selection'  and 'BOM Explosion' steps), it gives a hard stop when it encounters the 1st error, instead of completing the 'Costing ' step and giving an Error Log with material information and nature of errors. This makes it very cumbersome to resolve all the errors.
    In the Costing Variant setting in config, the u2018Save Error Log' indicator has been checked.
    Please let me know if I am missing something.
    Venkat

    Hi Vimal,
    Your proposal does not resolve the issue. I found OSS Note 375901, which addresses this issue - see below
    :In Customizing for the costing variant (Transaction OKKN) in the tab "Misc.", you chose "Messages online" for the Error Management option.
    Solution
    Change the error management for the costing variant to
    "Log and Save Messages..."
    Many thanks for your inputs.
    Venkat

  • Consideration of stock of discontinued FG or trading material during MRP Run

    There is an functionality of follow up material for component. I would like to know if there is any similar option available for finished goods or trading materials.
    I am doing procurement planning for externally procured Trading materials. Now my previous material A is being replaced by material B. Therefore all the planned independent requirement is available in system only for B. But still there is some stock available for material A. How can it be considered during MRP run for material B.
    Example,
    Material A:
    On Hand Stock = 100
    Planned Independent Req. = 0
    Material B:
    On Hand Stock = 300
    Planned Independent Req. = 1000
    In this case if we run MRP for material B, how we ask system to plan Purchase Requisitions for 600 instead of 700 for material B, considering stock of material A.

    Hello
    Please refer to the following SAP note:
    43636 - Discontinued parts
    This note provides a detailed explanation of the system standard design of the usage of discontinued parts with material requiremenst planning and the most common questions about this issue.
    The following information is provided on this note regarding the PIRs:
    2. Planned independent requirements and forecast requirements are not redirected.
                  Explanation: Planned independent requirements after the effective-out date are not redirected but are provided with an exception message in the MRP list stating that they cannot be included in the availability check. Planned independent requirements and forecast requirements are therefore displayed in the MRP list and in the stock/requirements list. However, they do not influence planning
    BR
    Caetano

  • Secondary packing material procurement through MRP Run

    Hi
    Is it possible to procure Secondary packing material through MRP Run. Material type of Secondary packing material is VERP. In MRP view we defined MRP type as VB and reorder point also set.

    Hi
    the MRP run would create a procurement proposal if the stock has fallen below the re-order point. The procurement proposal needs to be a purchase requisition if procurement should start immediately (see Creation indicators for the MRP group). Further, you need to set the "automatic purchase order" indicator both on the material (purchasing view) and on the vendor. In the MRP run, the system also needs to be able to assign a vendor (i.e. through a source list). Then a purchase requisition is automatically converted into a purchase order on creation.
    Good luck
    Eivind

  • Post closing entry in Material Ledger

    During running og Material ledger last night, in CKMLCP, we ran post closing entry before we release the cost through CKME. When I tried to release tcode CKME and CK40N, the system gave error message as below:
    Price changes for material 200001  is not possible
    Message no. C+811
    Diagnosis
    You want to change the price or release planned prices for material 200001 with valuation type  in valuation area 2100. You have, however, already entered actual data or performed a single-level price determination in the period concerned. The status of the material in the period is Quantities and Values Entered.
    Price determination indicator 3 assumes that the standard price remains constant throughout the period, so that all movements can be valuated preliminarily with the same standard price.  Therefore, you can only change the standard price at the beginning of a period (i.e. as long as no actual data was entered).
    System Response
    The system does not allow the price changes or the release of planned prices for this material in this period.
    Procedure for System Administration
    In the future, to automatically release your planned prices upon creation of new actual data you can allow dynamic price release in Customizing for Actual Costing/Material Ledger.
    How I can release my standard cost for period 01.05.2010 to 31.05.2010. Please help
    Edited by: Ahmed EL Zain on May 1, 2010 10:49 AM

    Hey,
    What you described is the standard system behaviour.
    The price change or release of a cost estimate should always be the
    first transaction in a new period, when Material Ledger is active.
    Once period status = 30, the standard price cannot be release or
    changed. For more details please see note 190707.
    The only possible workarounds are as below:
    - postponing the costing release to next month
    - reversing transactions and usage of note 574930
    - using the option LTPC from note 555176
    Best Regards
    Young