Defalut Document Type assignment for PR after MRP RUN
Hi,
I want to know we have 6 types of different document types , i want to know after MRP RUN i want to assign a document type how to do setting for this like for each plant i want to assign diffrent document type after MRP RUN, also if we have not made which will be the defalut doc. type after MRP RUN for PR
regards,
zafar
Dear Zafar,
Go to
Spro-Materials Management-Consumption-Based Planning-Planning-Procurement proposals-Define External Procurement-MRP Group-Under Doc Type SPO you can maintain your default doc types in front of your plant.
Now run MRP.
It will work.
Regards
Utsav
Similar Messages
-
Document type assigned for other goods receipts(MB1C)is WA why?
Hi,
Document type assigned for other goods receipts(MB1C)is WA why?
ThanksDocument type for Goods Receipt is WE but I found in standard(Default) system it is assigned WA?
Can anyone help me on this?
Thanks -
Schedule lines are not coming for HALB after MRP run
Dear All,
I am not getting schedule line after mrp run, inspite of all required setting only purchase requisitions are coming.
Material type is HALB and involve a subcontracting process (30). For raw material I am getting the schedule line but in the case of HALB, it is not coming.
Pls let me know if I am missing something and guide me further on this.
Thanks & Regards
Kundan KumarHi,
In transaction OMDT you have to enable the indicator create schedule lines
In MD02 MRP control Prameter here select the Delivery schedules -3- Schedule line. Processing Key as NETCH and Planning Mode - 3 delted and recreated.
Maintain source list ME01, in that put MRP indicator as '2' i.e. schedule lines via MRP.Put your agreement no in that.
If u run MRP properly u will get schedule lines automatically in ME38.
Make the schedule agreement, make it source relevent in the source list make is FIX and MRP indicator as 3. -
How system will generate schedule line for PO after MRP run.
Dear Experts,
i have updated MPS in MD61, the period indicator was M (monthly), after MRP run, system generating schedule lines on daily basis for Scheduling Agreement(ME38), i want schedule lines on mpnthly basis, how to achive this,
thanks in advance.
regards
rajakarthikHi
1. Are you maintaining any Planning time fence period for MPS- No
2. What is the PIR qty you maintained in MD61:
i.) FG01 is having BOM child part RM01.
To produce 1 nos of FG01 , I need 1 nos of RM01
ii.) i maintained FG01 in MD61 with PIR Qty 5000. in MD61,Planning period is M and planning hirizon1- jan10To 31-Jan10
ii.) i maintained lot size:Monthly lot size for RM01.
iii.) there is no stock available for both RM01 and FG01.
3. After MRP how much qty is get planned on what date-
i) planned order created for FG01 in co41 with qty-5000 nos.
ii) in ME38, schedule line created for RM01, on 01-01-2010, with 5000 nos, currently Category of Delivery Date
field is D and delivery date is 01-01-2010, but i want Category of Delivery Date should be M and delivery date should be 01.2010.
thanks
raja -
Purchase req type after MRP Run
Ca we control the type of Purchase req after MRP Run.
Now for every material it is creating "NB" type purchase req.
Can we control it material type or by mat number.
We have 2-3 purchase req types in system for Material.
Amit ShahDear ,
Goto -OPPR-Enter Plant Code and Maintain MRP Group -0000( as SAP Standrad for External Procurement ) -Select Scheduling /Doc Type tab -Here you can assing the PR type as per your requirement so the while MRP run , it will selct the PR documents types based on OPPR .At the same time , assing this MRP group in MRP1 view of the material .
Try and come back
Regards
JH -
Schedule lines are not coming after MRP run for HALB material
Dear All,
I am not getting schedule line after mrp run, inspite of all required setting only purchase requisitions are coming.
Material type is HALB and involve a subcontracting process (30). For raw material I am getting the schedule line but in the case of HALB, it is not coming.
Pls let me know if I am missing something and guide me further on this.
Thanks & Regards
Kundan KumarDear All,
I am closing this thread. As the vendor mentioned in scheduling agreement is not a subcontracting vendor. Its a individual vendor.
Thanks for all the reply.
Thanks & Regards'
Kundan Kumar -
Hi,
How can we change the docment type assignment to some of the transactions? For eg, vendor invoice, vendor payment and vendor clearing.
Thanks,
CWHi,
You can do the same in FB00, where you can make the document type ready for input.
Regards
Suresh -
Document type setting for Elimination
Quick question
Whats the impact to have only the GROUP CURRENCY turn on in the document type used for IU elimination ?
I have a CU in local currency USD and the group is CAD.
After elimination task i have elimination in CAD in the column GROUP ( Thhis result is OK )
In the column TRANSACTION Currency I have the original amount in USD and the elimination in CAD is it for this reason I see the amount in CAD ( GROUP ) in the column Transaction currency ? or if it's the normal result. Waht will be the posting if I turn on Trabnsaction currency in the document typeThe purpose of the Transaction currency in I/U elimination is to identify and record on a dedicated account the differences linked to currency translation.
to summarize the behaviour of the system :
If a I/U transaction is recorded in both LC and TC, and then translated in GC, the system will check, during the I/U elimination, if there is a difference in TC b/w the 2 partners, check the global difference in GC, and deduct what is linked to Currency translation diff and what is linked to other differences. It will then be possible to record these 2 kinds of difference on separate accounts.
If you do not use TC, then I agree with Eugene.
There are some example in the SAP BCS documentation.
Hope it helps
Regards,
Thibaud -
How to flip the FI document type assigned in sales billing type
Hi Expart,
We have a special requirement here,as per client requirement we need to flip the FI document type assigned in sales billing type screen (VOFA). The requirement has came because the billing type is used for one company code XXXX, and we need to use the same billing type with different FI document type for another company code YYYY. Since we can't assigned two FI document types in biling document, i belive this can be done only through user exit, pl help me to get the applicable user exit in SD.
Thanks
Garima.Hi,
The user exit (T.Code SMOD) u201CEXIT_SAPLV60B_001u201D, with include u2018ZXVVFU01u2019, will be implemented. In user exit code will be written, as if company code found as u2018YYYYu2019 and Sales Doc type found as 'AAA' the FI document determine as u2018Z2u2019 in place of default value coming from one-to-one mapping u2018Z1u2019 (FI Document).
IF VBRK-FKART EQ 'AAA' AND VBRK-BUKRS EQ 'YYYY' AND XACCIT-BLART EQ 'Z1'.
XACCIT-BLART = 'Z2'.
hope this will help.
regards
Vivek. -
Default Exchange rate type at document type level for parallel currencies
Hi,
I have a scenario wherein 2 parallel currencies have been maintained (Grp & index based) against a Co Code and have maintained a default exchange type (Z2) in the Document type settings (OBA7).
But when I want to post a foreign currency document, system picks Z2 rates for Co Code currency conversion and not for Grp & index based. In fact it picks M rate for these addtional currencies.
I know that for parallel currencies, the system will always use the exchange rate type defined in transaction OB22 ( "M" rate) which is at Co Code level but I want default exchange rate type Z2 to be picked at Document Type level for all the parallel currencies.
Please suggest how to archive this.
Thanks,
SamDear Sam,
The exchange rate type defined in the FI document type (-> field
exchange rate type in transaction OBA7) is only used for the currency
translation from transaction/document currency into first local
currency, not for the currency translation into second local (group)
currency or for the currency translation into third local currency.
The exchange rate types for the currency translation into second
local (group) currency and third local currency are defined in
transaction OB22.
Unfortunately there is no option to change the exchange rate of 2nd or
3rd local currency in our posting transactions. The design doesn't
regard that requirement. But you have the chance to adjust the parallel
currencies in OB22 or to change the amounts manually.
I hope this helps.
Mauri -
Document Types Setup for Expense Approval and Payable Invoice
Hi,
Can anyone please suggest Document Types Setup for 'Expense Approval' and 'Invoice Approval' and its tables related to the same. Table storing its document_type_code and wf_approval_itemtype as we have for PO_DOCUMENT_TYPES_ALL table for Purchase Order.
Thank You.
Regards,
MeghanaHi
It could be because of main memory problem... so Restrict your selections and do the statistical setup
by the way how many comp codes you have? restrict with comp codes or doc ranges
Thanks, -
Purchase requisition not generate for dependent requirement after MRP run
Hello PP expert,
In our MTO scenario after MRP run planned order generate for header material but no PR generate for BOM components, (BOM not explode) when we run MRP component level in MD02 PR generate, system showing message "40- No coverage not provided by master plan" in MD04 order tree. this problem coming after when we DIMP applied. I checked some OSS note also.
Can any one provide right solution.
thanks in advance.....its urgent as client requirement.
regards,
Amit Awasthi.Hi Amit
You must select the green star for the correct answer, in order to close the thread.
You may also select the yellow start for the helpful answers, in order to award points for those who helped you. See the blog below for more details:
How to close a discussion and why
I can see that most of your old threads are still open, therefore, I'd like to ask you to review and close them, by selecting the correct answer.
BR
Caetano -
Document type declaration for root element type "web-app" must end with ' '
I am attempting to deploy an application (.war file) using the Sun Access Manager Agent installed, (Reference http://docs.sun.com/app/docs/doc/819-3201/6n5eht3k4?a=view -near the bottom) and I get this error:
Error loading deployment descriptors for ajacs Line 3 Column 19 -- The document type declaration for root element type "web-app" must end with '>'.
Here is the relavent code:
<!DOCTYPE web-app version="2.4" xmlns="http://java.sun.com/xml/ns/j2ee"
xmlns:xsi="http://www.w3.org/2001/XMLSchema-instance"
xsi:schemaLocation="http://java.sun.com/xml/ns/j2ee
http://java.sun.com/xml/ns/j2ee/web-app_2_4.xsd">
<web-app>
<filter>
<filter-name>Agent</filter-name>
<filter-class> com.sun.identity.agents.filter.AmAgentFilter </filter-class>
</filter>
<filter-mapping>
<filter-name>Agent</filter-name>
<url-pattern>/*</url-pattern>
<dispatcher>REQUEST</dispatcher>
<dispatcher>INCLUDE</dispatcher>
<dispatcher>FORWARD</dispatcher>
<dispatcher>ERROR</dispatcher>
</filter-mapping>
<display-name>AJACS</display-name>
<welcome-file-list>
<welcome-file>frameSet.jsp</welcome-file>
</welcome-file-list>
etc...
Now, when I remove the parts that http://docs.sun.com/app/docs/doc/819-3201/6n5eht3k4?a=view said to add, it deploys just like it used to deploy- just fine with no errors. However, I add that code and it breaks.
Note: The code was a straight copy/paste, so if there is any error in the code, it is because it's written incorrectly on the Sun doc website.
Any help would be MUCH appreciated. Thanks!Well, if that was pasted on one line, it would be:
xsi:schemaLocation="http://java.sun.com/xml/ns/j2ee http://java.sun.com/xml/ns/j2ee/web-app_2_4.xsd"
So it's supposed to be that way. I just tried it with the extra quotes, and no dice... -
Invoice Reduction: No separate document type exists for invoice reduction
Hi,
I am posting a document for Invoice Reduction and getting the following error message. I have seen the document types in OBA7 T-code. What is the document for Invoice reduction, is it same as Credit memo or different one?
Can you Pls guide me to complete the transaction successfully.
Error Message:
No separate document type exists for invoice reduction
Message no. M8507
Diagnosis
You want to post an invoice that has been reduced. This results in two FI documents being created. You require different document types to process both FI documents correctly.
System response
The invoice cannot be posted.
Procedure
Your system administrator must enter a separate document type for invoice reduction with transaction MIRO in Customizing for Logistics Invoice Verification.
Regards
Hari.Hi Hari,
Procedure for posting the Invoice Reduction :
(1) Enter the T.Code MIRO - Select the Transaction as Invoice only.
(2) Give the reference number ( Example PO Number) for which you want to create an Invoice.
(3) In the Display Variant, Select Invocie Reduction.
(4) Maintain the required details and post the Invocie.
Example: Invoice Reduction due to Quantity Variance:
PO: 100 nos @ 10 EUR/No
GR: 40 nos
Invoice: 40 nos @ 12 EUR/No = 480 EUR
When you enter Invoice,
Order Qty Order Amount Invoiced Qty Invocied Amt
40 400
Select Reduce Invocie in the Display Variant.
Enter the Quantity and Amount stated in the Invocie in the fields Invoice quantity acc. vendor and Invoice amount acc. vendor.
Order Qty Order Amount Invoiced Qty Invocied Amt
40 400 40 480
When you post the Invocie, Purchase order history will be updated as follows:
Quantity Value
Total Delivered 40 400
Total Invoiced 40 400
Accounting Documents:
GR:
Stock Account = 400
GR/IR Clearing Account = 400(-)
Invoice:
Vendor Account = 480(-)
GR/IR Clearing Account = 400(-)
Invoice Reduction Clearing Account = 80(+)
Automatic Credit Memo:
Vendor Account = 80(+)
Invoice Reduction Clearing Account = 80(-)
Thanks
Sunil. -
Document type setting for flexible rel estae meanagement
Dear SAP experts,
Currently when we run RERAPP system is posting the documents with SA document type, now the the requirement is to change the Document type from SA to ** (ZC) for the documents posted from RERAPP.
Kindly suggest where thsi setting can be done.
Regards,
NagabhushanDear Nagabhushan,
please assure that there is no entry at all in this customizing view, not only no entry for posting process REPP. Then the system should use document type AB for posting. This is also described in documentation for the customizing view and corresponds to my own experience.
You may set a break point in program LACC9F20 at the following position to check the content of the field gs_accit-blart.
If gs_accit-blart is not initial then maybe it is filled before by a BAdI implementation.
Belegart
IF gs_accit-blart IS INITIAL.
gs_accit-blart = 'AB'. " allgemeiner Buchhaltungsbeleg
ENDIF.
Regards, Franz
Maybe you are looking for
-
Print, Export and Page Navigation Buttons in the Report
When I view a report through CR4E, the generated report has 3 buttons namely Print, Export and Page Navigation buttons. But when I click on either of the buttons I get a 'null pointer exception'. This is a critical error as I am unable to navigate pa
-
Flex 3: Does Google Ignore URLs with # in Sitemaps?
Hi, I'm making a sitemap for my Flex 3 site. Does Google ignore everything after the # in a url listed in a sitemap. For example, if my sitemap lists: www.brainpinata.com/# www.brainpinata.com/#view=2 www.brainpinata.com/#view=12 www.brainpinata.com/
-
How do you delete your skype messages
This is crazy, before i could delete my messages, now cannot. Seems others are having the smae problem. No one is getting the help they need.
-
Help to buield log (pa)intrface in write way
Hallow I doing an inteface to other system that log the pa in the first time and I wont to now if im in the write way? If not please give me ideas how to do it in better way. regards CALL FUNCTION 'HREIC_GET_LOGGED_INFTY_CHANGES' EXPORTING is_log_key
-
Please help me. I have bought lenovo a606 smartphone. I want to root it but no method works, please help me as I want to record my phones screen. If it isn't possible, then please update lenovo a606 to lollipop as lollipop OS allows to record screen